Power and the grid
- Consumers Energy grid Utility engagedutility engaged on the project; no MW disclosed and no state regulator case for the campus Local government · Oct. 2026
Getting on the grid
- The city manager reported Consumers Energy's assurance that the end user, not ratepayers, will pay project costs. Local government · Dec. 2025
- Any service would fall under the state regulator's Nov. 2025 large-load tariff for Consumers (100 MW threshold). Local government · Dec. 2025
- No MW figure has been disclosed by the township or Microsoft. Local government · Oct. 2026
Permits checklist
1 paused · 1 pending · 1 granted · 1 checked, nothing on file
Local actions on record. Nothing has been approved for the data center.
- ‖Franklin Partners rezoning application PausedLowell Charter Township · Dec. 18, 2025: suspended indefinitely at the applicant's request Local government · Dec. 2025
- ◷Microsoft conditional rezoning and zoning text amendment PendingLowell Township Planning Commission · April 13, 2026: hearing held June 8, 2026; no action yet News report · June 2026
- ✓Public Act 425 land agreement with the City of Lowell GrantedLowell Charter Township Board · Nov. 11, 2024: 5-2; city council approved 4-1 on Oct. 21, 2024 Local government · Nov. 2024
- –Checked, nothing on file: State air permit or utility case
What could slow it down
- HighNo water planThe city's exit from water and sewer talks leaves no active plan to extend municipal water to the site (press). News report · Aug. 2026
- HighFierce local oppositionHearings have overflowed, opponents organized, and recall petitions target officials who backed the process. News report · June 2026
- MediumNo approval yetThe Planning Commission has not acted on Microsoft's rezoning request. see Permits
- WatchLand not yet boughtMicrosoft has not purchased the property. Local government · Jan. 2026
Money on record
Not on record: local tax abatements requested: Microsoft, June 2026 (press) News report · June 2026
What happened, and what is due
- Nov. 11, 2024Permits Township Board approves a 50-year land agreement bringing the business park into the City of Lowell Local government · Nov. 2024
- Jan. 2025Site Township supervisor signs a non-disclosure agreement with Microsoft Local government · Jan. 2026
- Dec. 8, 2025Permits Planning hearing on the rezoning is postponed by an over-capacity crowd Local government · Dec. 2025
- Dec. 18, 2025Permits Franklin Partners' application is suspended indefinitely at its request Local government · Dec. 2025
- Jan. 7, 2026Site Microsoft reveals itself as the company behind the plan and ends the NDA Local government · Jan. 2026
- April 13, 2026Permits Microsoft files its own rezoning and zoning text amendment application News report · April 2026
- May 18, 2026Permits Township Board rejects a six-month data-center moratorium, 5-2 Local government · May 2026
- June 8, 2026Permits About 450 attend a six-hour planning hearing; no action taken News report · June 2026
- June 16, 2026Site Recall petition language approved against the supervisor and two trustees (press) News report · June 2026
- Aug. 17, 2026Site City of Lowell ends water and sewer talks with the township, leaving no plan to bring city water to the site News report · Aug. 2026
Specs
Owners, partners and builders
- Microsoft: proposed owner and operator
- Franklin Partners (Franklin Lowell LLC): original applicant and seller
- Lowell Charter Township Board and Planning Commission
- Supervisor Jerry Hale
- City of Lowell (Mayor Mike DeVore): land agreement and water and sewer
- Consumers Energy: serving utility
- No Lowell Data Center group
- Recall organizers
Open questions
- MW and Consumers Energy service plan.
- Water supply for the site.
- Planning Commission and Board decisions.
48 records from 7 documents
Drawn from news reports, local government records and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (3)
- Consumers Energy is the utility engaged on the Lowell project: township/City open-house notices list Consumers Energy representatives alongside Franklin Partners, and the city manager reported Consumers' assurance that p“City of Lowell and Lowell Township officials as well as representatives from Consumers Energy, The Right Place and property developer Franklin Partners will be available”Local government · Dec. 2025 · grade A
- August 2026: the City of Lowell discontinued negotiations with the township on joint water and sewer services after Mayor Mike DeVore publicly criticized township transparency, leaving no active plan to extend municipal“The stalled talks leave no active plan to extend municipal water to the site of a proposed Microsoft data center on Alden Nash Avenue near Interstate 96.”News report · Aug. 2026 · grade C
- Site acres planned: 300 acres“which would bring the total acreage to just under 300 acres, which would include a 42-acre off-site substation and preserve 28 acres of wetland.”News report · June 2026 · grade C
Money and contracts (7)
- Project identity: Microsoft data center campus, Covenant Business Park, 4687 Alden Nash Ave SE, Lowell Charter Township, Kent County, MI“the 425 cooperation agreement is only for the parcel at 4687 Alden Nash Ave”Local government · Oct. 2026 · grade A
- Tenant: Microsoft (proposed owner-operator; has not purchased the property)“Microsoft publicly revealed itself in January 2026 — although, it has not purchased the property.”Local government · Jan. 2026 · grade A
- Township Supervisor Jerry Hale signed an NDA with Microsoft in January 2025; Microsoft ended the NDA and publicly revealed itself in January 2026; residents criticized the closed process at hearings“Lowell Township Supervisor Jerry Hale signed a non-disclosure agreement (NDA) with Microsoft in January 2025.”Local government · Jan. 2026 · grade A
- Intergovernmental cooperation agreement (Michigan Public Act 425): conditional land transfer 50 years“This agreement brings this parcel into the City of Lowell for a period of 50 years.”Local government · Nov. 2024 · grade A
- Intergovernmental cooperation agreement (Michigan Public Act 425): tax sharing 15.7 mills levied by City of Lowell (6 mills returned to Lowell Charter Township)“The City will levy 15.7 mills on property owners in the business park, returning 6 mills of revenue to Lowell Charter Township.”Local government · Nov. 2024 · grade A
- Jan 7, 2026: Microsoft publicly revealed itself as the company behind the Covenant Business Park proposal, in a letter posted by the township; it ended the NDA Supervisor Jerry Hale had signed in January 2025 and said it“Microsoft is interested in building a data center at Covenant Business Park.”Local government · Jan. 2026 · grade B
- Microsoft stated at its June 8, 2026 presentation that it is not requesting any local tax abatements for the project (Lowell Ledger report of the meeting). No PILOT or abatement agreement exists for this campus.“Microsoft is not requesting any local tax abatements for the project.”News report · June 2026 · grade C
Permits and government (16)
- Lowell Charter Township Board:“The Township Board held the second reading of a proposed six-month moratorium on data centers during its May 18 meeting. Following discussion, the Board voted 5-2 against the moratorium.”Local government · May 2026 · grade A
- Applicant asked to table its zoning application and requested an indefinite susp: consideration put on hold - indefinite suspension at applicant's request“an indefinite suspension of the application and its approval process until such time that Franklin is prepared to resume the application approval process.”Local government · Dec. 2025 · grade A
- Franklin Lowell LLC (Franklin Partners, for Microsoft) asked to table its Covena: Rezoning application INDEFINITELY SUSPENDED at applicant request (Dec. 18, 2025)“an indefinite suspension of the application and its approval process until such time that Franklin is prepared to resume the application approval process”Local government · Dec. 2025 · grade A
- Dec 8, 2025 Planning Commission meeting postponed due to an over-capacity turnou: public hearing postponed“The rezoning was on the Dec. 8 Planning Commission agenda, but the meeting was postponed due to an over-capacity turnout.”Local government · Dec. 2025 · grade A
- Lowell Charter Township Board:“On Nov. 11, 2024, the Township Board voted 5-2 to approve a cooperative land agreement with the City of Lowell that will pave the way for the development of Covenant Business Park.”Local government · Nov. 2024 · grade A
- City of Lowell City Council:“On Oct. 21, the City Council voted 4-1 to approve the cooperative land agreement.”Local government · Oct. 2024 · grade A
- Project status: rezoning in Planning Commission review; six-month moratorium rejected 5-2 on May 18, 2026; no approval as of Oct 2026“The Township Board held the second reading of a proposed six-month moratorium on data centers during its May 18 meeting. Following discussion, the Board voted 5-2 against the moratorium.”Local government · May 2026 · grade B
- May 18, 2026: Township Board held the second reading of a proposed six-month data center moratorium (first reading April 20, 2026) and voted 5-2 against it; the Board instead created a temporary advisory committee (board“The Township Board held the second reading of a proposed six-month moratorium on data centers during its May 18 meeting. Following discussion, the Board voted 5-2 against the moratorium.”Local government · May 2026 · grade B
- Dec 18, 2025: Lowell Charter Township put consideration of the Franklin Partners rezoning application on hold at the applicant's written request, after the Dec 8 Planning Commission hearing was postponed for over-capacit“The applicant asked to table its zoning application and requested an indefinite suspension of the application and its approval process until such time that Franklin is prepared to resume the application approval process.”Local government · Dec. 2025 · grade B
- Announced: Dec. 2025“Monday, Dec. 8, 2025 at 7 p.m. – public hearing during Planning Commission meeting at Township Hall”Local government · Dec. 2025 · grade B
- Recall petition language against Supervisor Jerry Hale and Trustees Mark Anderson and William Thompson was approved June 16, 2026, driven by resident anger over the rezoning process and the defeated moratorium“Recall petitions on Lowell Township's Supervisor Jerry Hale, Trustee Mark Anderson and Trustee William Thompson are ready to be circulated immediately unless the officials decide to appeal.”News report · June 2026 · grade C
- Microsoft's Apr 13, 2026 application seeks conditional rezoning of five parcels : application submitted; public hearing held; no action taken“The Planning Commission has not yet taken any action on Microsoft's request.”News report · June 2026 · grade C
- Organized opposition (No Lowell Data Center group); the Dec 8, 2025 hearing was postponed for an over-capacity turnout and the June 8, 2026 hearing drew roughly 450 mostly opposed attendees“Many people brought signs protesting Microsoft's proposed data center campus, which they held high during a meeting of the Lowell Township Planning Commission on Monday, June 8”News report · June 2026 · grade C
- June 8, 2026: Microsoft introduced its rezoning proposal at a Planning Commission meeting moved to a barn at the Grand Agricultural Center; the meeting ran more than six hours before hundreds of mostly opposed residents,“A hostile audience responded with boos and jeers to Microsoft's presentation on a proposed data center, during a more than six-hour meeting of the Lowell Township Planning Commission”News report · June 2026 · grade C
- Lowell Charter Township Planning Commission:“Many people brought signs protesting Microsoft's proposed data center campus, which they held high during a meeting of the Lowell Township Planning Commission on Monday, June 8”News report · June 2026 · grade C
- Applicant: Franklin Partners, via Franklin Lowell LLC (original Dec 2025 application); Microsoft (Apr 13, 2026 application)“Microsoft submitted a zoning application to the township on April 13, asking to rezone the business park to light industrial and proposing a zoning text amendment.”News report · April 2026 · grade C
Legal (1)
- Recall petitions against Supervisor Jerry Hale and Trustees Mark Anderson and William Thompson: petition language approved June 16, 2026; organizers needed 894 eligible signatures by July 31, 2026 to reach the November b“Recall petitions on Lowell Township's Supervisor Jerry Hale, Trustee Mark Anderson and Trustee William Thompson are ready to be circulated immediately unless the officials decide to appeal.”News report · June 2026 · grade C
Site and other (1)
- County code: 26081“Covenant Business Park is located in Lowell Charter Township.”Local government · Nov. 2024 · grade B