The site from above
Power and the grid
None energized or contracted yet
- On-site generation none proposed; the county's 2026 rules also cap accessory generation at 300 MW firm; no air permit filing found News report · March 2025
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Jan. 23, 2025Georgia large-load ruleState regulators let Georgia Power require minimum bills, up to 15-year contracts and collateral from customers of 100 MW or more. Utility regulator · Jan. 2025
- June 4, 2025Supply plan statedThe applicant says power would come from existing transmission lines that cross the site; no utility filing names the campus. Local government · June 2025
- As of Oct. 2026No air permit filingNo state air permit filing for on-site generation was found. see Permits
- Not setService agreement: none foundNo signed Georgia Power contract is on record; any contract of 100 MW or more must go to state regulators for review. Utility regulator · Jan. 2025
- A 500 kV line runs about half a kilometer from the site, and Plant Bowen is under 2 km away. OpenStreetMap · Oct. 2026
What is next door
- 10.45 km · Dalton Lateral (gas, Transcontinental Gas)
- 20.52 km · Villa Rica
- 31.69 km · Plant Bowen (Georgia Power)
- 42.08 km · Bowen NDPES Substation (46 kV, Georgia Power)
- 52.18 km · Unnamed (115 kV)
Distances from mapped lines and plants. OpenStreetMap · Oct. 2026
Permits checklist
1 granted · 3 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup generators), and what we found.
- ✓Rezoning and land-use map change GrantedBartow County Commissioner · June 4, 2025: approved with six conditions, including an 8.3 million sq ft cap and access from Taff Road only; the sole commissioner decides Local government · June 2025
- –Checked, nothing on file: Land disturbance and building permits, Air permit for on-site generation, Public water for cooling
What could slow it down
- HighNo power contractNo Georgia Power service agreement is on record, and the state's large-load rule lets the utility demand minimum bills and collateral at this size. Utility regulator · Jan. 2025
- HighNo tenantNo end user has been identified, and no financing is on record. News report · Oct. 2026
- MediumStricter county rulesA July 2026 ordinance, adopted after this rezoning, sets noise, cooling and generation limits for new data centers in the county. Local government · July 2026
- WatchLocal oppositionOnly two residents spoke against at the 2025 hearing and no organized group, petition or lawsuit was found. Local government · June 2025
Money on record
Not on record: tax breaks: no abatement, exemption or payment in lieu of taxes, full millage applies Local government · Aug. 2026; financing: no lender or financing found SEC filing · Oct. 2026
No arm's-length land purchase by the campus company is in county records. 2 related-party transfers are shown greyed. 1 sale or conveyance by the campus company or to public bodies is not listed. Parcel counts come from the deed; acreage is not recorded.
- July 2022 Gaines to Gaines Family Land LLC · price not recorded · 1 parcel · related-party transfer County deed records · July 2022
- June 2023 Gaines to Gaines Family Land LLC · price not recorded · 1 parcel · related-party transfer County deed records · June 2023
What happened, and what is due
- Sept. 2024Paper trail Taurus DC SPE LLC registered in Delaware
- March 2025Site A regional review filing reveals Project Bunkhouse: 12 buildings, $19B, 1,830 MW News report · March 2025
- May 2025Permits Planning commission recommends approval with conditions Local government · June 2025
- June 4, 2025Permits County commissioner approves the rezoning with six conditions; two residents speak against Local government · June 2025
- Feb. 2026Money Taurus and Digital Realty close on the 876-acre site (press) News report · Feb. 2026
- Feb. 17, 2026Site County administrator confirms the developers have closed on the land News report · Feb. 2026
- July 1, 2026Permits County adopts data center standards: closed-loop cooling, noise limits and a 300 MW cap on accessory generation Local government · Aug. 2026
- Aug. 3, 2026Money County policy statement names the Digital Realty project at 1.3 GW and $18B and rules out tax breaks Local government · Aug. 2026
- 2035Construction Full build-out date in county reporting News report · April 2026
Satellite captures by quarter
Since Feb. 2022: 71 satellite captures. The chart starts in the first quarter of 2023; 4 earlier records are not drawn.
Specs
Owners, partners and builders
- Taurus DC SPE LLC: applicant, developer of record and landowner since Feb. 2026
- Digital Realty: project sponsor, per its counsel and the county
- Taurus Investment Holdings: reported co-sponsor (press)
- Gaines Family Land, LLC: seller of the land
- Bartow County Commissioner: sole zoning authority
- Georgia Power: serving utility
- Bartow County Water Department: approves public water for cooling
- Kimley-Horn: engineer on the regional filing
- Schreeder, Wheeler & Flint: rezoning counsel
Open questions
- A tenant or end user.
- A signed Georgia Power agreement and in-service date.
- Land price and any financing (a $95M county deed from the landowner to Exeter 1762 LLC is not confirmed as this site's sale).
- When construction starts.
306 records from 19 documents
Drawn from public and commercial datasets, news reports, securities filings, business registries, local government records, utility regulator dockets, state agency records, our own analysis and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (23)
- IT capacity: 1,300 MW“Digital Realty investment in the Stilesboro area, planned for approximately 1.3 gigawatts of computing capacity”Local government · Aug. 2026 · grade A
- Regulatory standards: Ordinance Z-26-00027 (adopted Jul 1 2026), Zoning Ordinance Sec. 9.9: closed-loop cooling required; noise 65 dB day / 55 dB night at residential boundary; accessory generation capped at 300 MW firm;“generation is capped at three hundred megawatts of firm load to preserve its accessory character”Local government · July 2026 · grade A
- Utility: Georgia Power“all the power will come off the existing lines and into the substation at the corner of Brandon Farm Road and Taff Road”Local government · June 2025 · grade A
- Substation: Substation at Brandon Farm Road and Taff Road (Georgia Power)“all the power will come off the existing lines and into the substation at the corner of Brandon Farm Road and Taff Road”Local government · June 2025 · grade A
- Interconnection status: No Georgia Power or PSC filing naming the campus found; applicant states supply from existing transmission lines crossing the site“There will be no need to run any additional power lines because there is a sufficient number of existing lines running through the site”Local government · June 2025 · grade A
- Power plan: grid“all the power will come off the existing lines and into the substation at the corner of Brandon Farm Road and Taff Road”Local government · June 2025 · grade A
- Grid operator: none - SERC region; Georgia has no ISO/RTO market“Assessment from rows in this folder: the utility record is Georgia Power, a vertically integrated utility in the SERC region; Georgia has no ISO or RTO market”grade B
- Electric service agreement signed: No executed electric service agreement found; any Georgia Power contract at or above 100 MW must be submitted to the PSC for review under the Jan 2025 rule“any new customers using more than 100 megawatts of energy can be billed using terms and conditions beyond those used for standard customers”Utility regulator · Jan. 2025 · grade B
- Rate class: Georgia Power large-load terms under PSC rule from Docket 55378: minimum billing, contract lengths up to 15 years, collateral and termination payments, PSC review of contracts“In addition to site specific costs, the data centers would pay for costs incurred by upstream generation, transmission and distribution to these large-load power users”Utility regulator · Jan. 2025 · grade B
- Nearest substation: Bowen NDPES Substation (46 kV, Georgia Power) - 2.08 kmMeasured on OpenStreetMap map data.
- Nearest power line of 345 kV or more: Villa Rica - Bowen 500kV #1 (500 kV, Georgia Power) - 0.52 kmMeasured on OpenStreetMap map data.
- Nearest power line of 138 kV: unnamed (115 kV) - 2.18 kmMeasured on OpenStreetMap map data.
- Nearest gas pipeline: Dalton Lateral (gas, Transcontinental Gas Pipeline Company) - 0.45 kmMeasured on OpenStreetMap map data.
- Nearest generation plant: Plant Bowen (Georgia Power) - 1.69 kmMeasured on OpenStreetMap map data.
- Phases: No phase split or per-phase MW disclosed in any source opened“The campus is permitted for 12 buildings totaling 8.6 million square feet of data center space”News report · Oct. 2026 · grade C
- Buildings planned: 12 buildings“The campus is permitted for 12 buildings totaling 8.6 million square feet of data center space, with 1,830 megawatts of total power capacity and three on-site substations”News report · April 2026 · grade C
- Project name: Project Bunkhouse“A Development of Regional Impact application filed with the Georgia Department of State Affairs in March 2025 showed that the campus will be called Project Bunkhouse.”News report · March 2025 · grade C
- Stated campus size: 1,830 MW“A site plan obtained by The Atlanta Journal-Constitution shows Project Bunkhouse power needs could be 1,830 megawatts and would require three on-site substations”News report · March 2025 · grade C
- On-site substations: 3 substations“would require three on-site substations”News report · March 2025 · grade C
- On-site power technology: None proposed - grid-served campus; no on-site generation in the DRI or site-plan reporting“would require three on-site substations”News report · March 2025 · grade C
- DRI filing revealed by AJC: Project Bunkhouse, 12 buildings, ~8.6M sq ft, $19B estimated build-out value, 1,830 MW site-plan power need“Preliminary plans for Project Bunkhouse were revealed March 31”News report · March 2025 · grade C
- Stated campus size: 1,830 MW“Project Bunkhouse, which would be built on a nearly 900-acre site adjacent to a coal power plant in Bartow County, could consume 1,830 MW at full build-out”News report · March 2025 · grade C
- System context only, NOT a campus position: the Georgia PSC large-load rule approved Jan 23, 2025 (Docket 44280) lets Georgia Power bill new customers over 100 MW on non-standard terms covering site-specific plus upstrea“any new customers using more than 100 megawatts of energy can be billed using terms and conditions beyond those used for standard customers”News report · Jan. 2025 · grade C
Money and contracts (25)
- Stated capital cost: 18000000000 USD“has indicated a total build-out capital investment on the order of eighteen billion dollars”Local government · Aug. 2026 · grade A
- Incentives: No county tax abatement, exemption or PILOT: full assessed value taxed at the full applicable millage rate“Bartow County has granted no tax abatements in connection with these facilities. It has entered into no reduction, exemption, or payment-in-lieu-of-taxes arrangement”Local government · Aug. 2026 · grade A
- tax treatment: abatement / PILOT - none No reduction, exemption or payment-in-lieu-of-taxes arrangement; full assessed value on the digest at full millage“The full assessed value of each facility will be accordingly entered on the digest and taxed at the full applicable millage rate”Local government · Aug. 2026 · grade A
- Square feet: 8300000 sq ft“The total square footage of all buildings to be constructed on the property shall be limited to 8,300,000 square feet”Local government · June 2025 · grade A
- Conditions of approval: Six conditions in the Z-25-00020 approval: prohibited BPD uses list; buffers per Conceptual Site Plan before any certificate of occupancy; 8,300,000 sq ft total cap; primary access from Taff Road“o The total square footage of all buildings to be constructed on the property shall be limited to 8,300,000 square feet”Local government · June 2025 · grade A
- rezoning approval Z-25-00020: scope - permitted and prohibited uses Data center use; prohibited BPD uses: distribution facilities, manufacturing/fabricating/processing/assembling, manufacturing, outdoor storage (except d“The following Business Park uses permitted by Section 7.18.3 of the Zoning Ordinance are prohibited: Distribution Facilities; Manufacturing; Outdoor Storage (except during construction); Retail Uses; Warehousing”Local government · June 2025 · grade A
- rezoning approval Z-25-00020: size cap 8300000 sq ft“The total square footage of all buildings to be constructed on the property shall be limited to 8,300,000 square feet”Local government · June 2025 · grade A
- rezoning approval Z-25-00020: condition precedent to occupancy No certificate of occupancy for any building until the buffers adjoining it are in place and improved as depicted on the Conceptual Site Plan“no buildings shall be granted a certificate of occupancy until any buffers adjoining such building are in place and improved as depicted on the Site Plan”Local government · June 2025 · grade A
- rezoning approval Z-25-00020: access Primary access from Taff Road; Floyd Creek Church Road access limited to secondary uses including emergency vehicle access“Primary access to the improvements shall be from Taff Road. Any access from Floyd Creek Church Road shall be limited to secondary uses, including emergency vehicle access”Local government · June 2025 · grade A
- rezoning approval Z-25-00020: water and cooling condition Water-efficient HVAC required; public water for equipment or building cooling subject to Bartow County Water Department approval“The development shall utilize water efficient HVAC technology and the utilization of public water for equipment or building cooling shall be subject to approval by the Bartow County Water Department”Local government · June 2025 · grade A
- rezoning approval Z-25-00020: compliance condition Development must comply with the Data Center definition, Section 3.2 of the Bartow County Zoning Ordinance“The development shall comply with all requirements as specified in the definition of a Data Center as set forth in Section 3.2 of the Bartow County Zoning Ordinance”Local government · June 2025 · grade A
- Financing: None disclosed - no closed financing, lender or instrument found in sources opened; the $19B DRI figure is estimated build-out value, not committed capital“SEC EDGAR full-text searches for Taurus DC SPE, Project Bunkhouse and Bartow in Digital Realty filings returned zero hits”SEC filing · Oct. 2026 · grade B
- Land purchase (recorded deed): contract value 95000000 USD“Recorded: Jan. 30, 2026 · Price: $95,000,000 · Grantor: GAINES FAMILY LAND LLC · Grantee: EXETER 1762 LLC · Parcel number: 0032-1122-001 · Address: FLOYD CREEK CHURCH RD · City: TAYLORSVILLE”County deed records · Jan. 2026 · grade B
- electric service agreement: existence No executed ESA found; no PSC filing naming the campus located“any new Georgia Power contract with a company that fits the 100 MW usage category must be submitted to the PSC for review”Utility regulator · Jan. 2025 · grade B
- electric service framework (PSC rule, Docket 55378): termination and minimum-bill terms available to the utility Minimum billing requirements; contract lengths extended from 5 to 15 years; collateral and substantial term“The new rule also allows for longer contract lengths (from 5-year contracts to 15-year contracts) and minimum billing requirements for high-load customers”Utility regulator · Jan. 2025 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: June 15, 2023 · Grantor: GAINES · Grantee: GAINES FAMILY LAND LLC · Parcel number: 0032-1122-001 · Address: FLOYD CREEK CHURCH RD · City: TAYLORSVILLE”County deed records · June 2023 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: July 7, 2022 · Grantor: GAINES · Grantee: GAINES FAMILY LAND LLC · Parcel number: 0032B-0003-006 · Address: 51 FLOYD CREEK CHURCH RD · City: TAYLORSVILLE”County deed records · July 2022 · grade B
- Tenants: No tenant or end user identified in any source opened“No additional information could be found about the applicant, Taurus DC SPE LLC. The end user is also unknown.”News report · Oct. 2026 · grade C
- Tenant status: none found - no tenant announced“The end user is also unknown”News report · Oct. 2026 · grade C
- Land price: Not disclosed in any source opened“closed on 876 acres of cattle farm in Stilesboro in February 2026”News report · Oct. 2026 · grade C
- Projected annual tax revenue: 40000000-50000000 USD/yr“Bartow County is projecting $40-50 million in annual property tax revenue once the campus is fully operational”News report · April 2026 · grade C
- Land closing reported (Daily Tribune News via The Connector): Taurus Investment Holdings and Digital Realty closed on the 876-acre Stilesboro site, purchase from Gaines Family Land LLC“closed on 876 acres of cattle farm in Stilesboro in February 2026”News report · April 2026 · grade C
- land purchase: closing Closed February 2026; price not disclosed“Taurus Investment Holdings (Boston, MA) and Digital Realty (San Francisco, CA) closed on 876 acres of cattle farm in Stilesboro in February 2026”News report · Feb. 2026 · grade C
- Sponsor group (Taurus Investment Holdings / Digital Realty) closed on the 876-acre site in February 2026, after the June 2025 rezoning approval; full build-out is scheduled for 2035 per county reporting“Taurus Investment Holdings (Boston, MA) and Digital Realty (San Francisco, CA) closed on 876 acres of cattle farm in Stilesboro in February 2026”News report · Feb. 2026 · grade C
- Stated capital cost: 19000000000 USD“the applicant estimates the campus will be worth $19 billion if completed”News report · March 2025 · grade C
Permits and government (25)
- data center standards ordinance: adopted“the Commissioner adopted comprehensive data center development standards by Ordinance Z-26-00027, codified at Article IX, Section 9.9 of the County Zoning Ordinance”Local government · Aug. 2026 · grade A
- Bartow County issues data-center policy statement: no abatements or PILOTs, full taxation; names Digital Realty Stilesboro investment at ~1.3 GW computing capacity and ~$18B build-out; 800+ jobs forecast“Digital Realty investment in the Stilesboro area, planned for approximately 1.3 gigawatts of computing capacity, has indicated a total build-out capital investment on the order of eighteen billion dollars”Local government · Aug. 2026 · grade A
- Bartow County Commissioner: Adoption of Ordinance Z-26-00027 - comprehensive data center development standards (Zoning Ordinance Sec. 9.9)“the Commissioner adopted comprehensive data center development standards by Ordinance Z-26-00027, codified at Article IX, Section 9.9 of the County Zoning Ordinance”Local government · Aug. 2026 · grade A
- Cooling: Closed-loop cooling mandated countywide by Ordinance Z-26-00027 (Zoning Ordinance Sec. 9.9(7)), adopted July 1 2026“the data center standards adopted July 1, 2026, require every facility to use a closed-loop or functionally equivalent cooling system”Local government · July 2026 · grade A
- Developer: Digital Realty project, per applicants counsel on the record at the June 4 2025 county hearing; county policy statement names it Digital Realtys investment in the Stilesboro area“This is a Digital Realty project. It is not a Crypto center.”Local government · June 2025 · grade A
- Rezoning date: June 4, 2025“Commissioner Taylor approved the application with the following conditions”Local government · June 2025 · grade A
- Opposition: Two registered speakers at the Jun 4 2025 hearing: Gail Cochran (transmission lines / property) and Patty Everett (opposed; pasture and property values). No Bunkhouse-specific group, petition or lawsuit found“Ms. Patty Everett, 11 Apple Barrel Way, Taylorsville, spoke in opposition to the application”Local government · June 2025 · grade A
- rezoning: approved with conditions“Commissioner Taylor approved the application with the following conditions”Local government · June 2025 · grade A
- future land use map amendment: approved“change the Land Use Map from Agricultural to Industrial for the purpose of developing a Data Center”Local government · June 2025 · grade A
- planning commission recommendation: recommended approval with conditions“The Planning Commission recommended approval with a number of conditions”Local government · June 2025 · grade A
- Hearing opposition limited to two registered speakers and no organized campaign found - in contrast to other Bartow proposals (Atlas/Barnsley) that drew a ~1,700-signature petition and denial recommendations“Ms. Patty Everett, 11 Apple Barrel Way, Taylorsville, spoke in opposition to the application stating that she just does not want it”Local government · June 2025 · grade A
- Bartow County Planning Commission: Z-25-00020 - Taurus DC SPE LLC rezoning, 876.57 acres Taff Road (A-1 to BPD)“The Planning Commission recommended approval with a number of conditions”Local government · June 2025 · grade A
- Bartow County Commissioner (sole commissioner Steve Taylor): Z-25-00020 public hearing and decision - Project Bunkhouse data center“Commissioner Taylor approved the application with the following conditions”Local government · June 2025 · grade A
- air permit: no filing found“no Taurus, Stilesboro or Bunkhouse filing”grade B
- Permitting authority: Bartow County sole commissioner for zoning (Zoning Procedures Law); GA DCA / Northwest Georgia Regional Commission DRI review is advisory only; GA PSC regulates the utility contract, not the campus“Commissioner Taylor approved the application with the following conditions”Local government · June 2025 · grade B
- Georgia Power files its 2025 Integrated Resource Plan (Jan 31 2025) - portfolio context for large-load growth; not campus-specific“The Georgia Public Service Commission received Georgia Power's filing for the utility's 2025 Integrated Resource Plan on Jan. 31”Utility regulator · Feb. 2025 · grade B
- GA PSC unanimously approves large-load rule from Docket 55378: Georgia Power may impose minimum bills, up to 15-year contracts, collateral and termination payments on customers at or above 100 MW; contracts go to the PSC“The Georgia Public Service Commission voted unanimously on Thursday to approve a new rule that allows Georgia Power to charge new data centers in a manner that will protect ratepayers”Utility regulator · Jan. 2025 · grade B
- Construction stage: none - rezoning approved Jun 2025 and land closed Feb 2026, but no clearing, grading or construction reported in any source opened through Oct 2026“Taurus Investment Holdings and Digital Realty closed on 876 acres of cattle farm in Stilesboro in February 2026”News report · Oct. 2026 · grade C
- land disturbance / building permits: none found“closed on 876 acres of cattle farm in Stilesboro in February 2026”News report · Oct. 2026 · grade C
- Bartow County budget hearing: County Administrator report - Project Bunkhouse land closing“County Administrator Peter Olson confirmed the deal at the February 17 budget hearing”News report · Feb. 2026 · grade C
- Land closed: Taurus Investment Holdings and Digital Realty closed on the 876-acre Gaines Family Land parcel in February 2026 (county administrator confirmed the closing at the Feb 17, 2026 budget hearing)“Taurus Investment Holdings (Boston, MA) and Digital Realty (San Francisco, CA) closed on 876 acres of cattle farm in Stilesboro in February 2026”News report · Feb. 2026 · grade C
- Site acres: 876 acres“Bartow Planning Commission has recommended approval for a data center rezoning request for an 876-acre land parcel in Stilesboro to be rezoned from residential to industrial.”News report · June 2025 · grade C
- Land owner: Gaines Family Land, LLC“The land is currently owned by Gaines Family Land LLC, and the rezoning recommendation will have to be approved by the Bartow County Commissioners.”News report · June 2025 · grade C
- Developer of record: Taurus DC SPE LLC is the rezoning/DRI applicant of record for the 876-acre Stilesboro (Bartow County) site; the end user is undisclosed“No additional information could be found about the applicant, Taurus DC SPE LLC. The end user is also unknown.”News report · May 2025 · grade C
- development of regional impact review: filed; review advisory“A Development of Regional Impact application filed with the Georgia Department of State Affairs in March 2025 showed that the campus will be called Project Bunkhouse”News report · March 2025 · grade C
Legal (1)
- Lawsuits: None found naming Taurus DC SPE LLC or Project Bunkhouse in sources opened“No additional information could be found about the applicant, Taurus DC SPE LLC”News report · Oct. 2026 · grade C
Site and other (20)
- Workforce estimate: 800 jobs“Digital Realty forecasts total employment in excess of 800 jobs once the campus is complete”Local government · Aug. 2026 · grade A
- Developer: Taurus DC SPE LLC (applicant and developer of record)“Z-25-00020; an application by Taurus DC SPE LLC requesting to rezone and change the Land Use Map for 876.57 acres on Taff Road”Local government · June 2025 · grade A
- Owner companies: Taurus DC SPE LLC“an application by Taurus DC SPE LLC requesting to rezone and change the Land Use Map for 876.57 acres on Taff Road”Local government · June 2025 · grade A
- Address: Taff Road, Stilesboro (unincorporated), Bartow County, GA; both sides of Taff Road, south of Plant Bowen, below Highway 113“876.57 acres on Taff Road. The property is located south of Plant Bowen.”Local government · June 2025 · grade A
- Parcel IDs: 0032-1184-001; 0032-1122-001; 0032a-003-002; 0032b-003-006“Tax Parcel numbers 0032-1184-001, 0032-1122-001, 0032a-003-002, and 0032b-003-006”Local government · June 2025 · grade A
- Acres: 876.57 acres“rezone and change the Land Use Map for 876.57 acres on Taff Road”Local government · June 2025 · grade A
- Cooling: Water-efficient HVAC required by approval condition; public water for cooling subject to Bartow County Water Department approval“The development shall utilize water efficient HVAC technology and the utilization of public water for equipment or building cooling shall be subject to approval by the Bartow County Water Department”Local government · June 2025 · grade A
- County code: 13015“buildings: Bartow County County GA (13015)”Dataset · Oct. 2026 · grade B
- Stage: Entitled and land-closed; not under construction“Commissioner Taylor approved the application with the following conditions”Local government · Oct. 2026 · grade C
- Original target date: 2035“Full build-out is scheduled for 2035”News report · April 2026 · grade C
- Current target date: 2035“Full build-out is scheduled for 2035”News report · April 2026 · grade C
- Land control date: Feb. 2026“The Project Bunkhouse developers have closed on the land. That seems to be all systems go.”News report · Feb. 2026 · grade C
- Development stage: land closed preconstruction“Taurus Investment Holdings (Boston, MA) and Digital Realty (San Francisco, CA) closed on 876 acres of cattle farm in Stilesboro in February 2026”News report · Feb. 2026 · grade C
- Water use stated: 625000 gallons/day“Official estimates are that Project Bunkhouse will use 625,000 gallons of water daily”News report · Aug. 2025 · grade C
- Applicant: TAURUS DC SPE LLC“No additional information could be found about the applicant, Taurus DC SPE LLC. The end user is also unknown.”News report · June 2025 · grade C
- Site location description: Stilesboro, both sides of Taff Road, bounded by Floyd Creek Church Road (W) and Raccoon Creek (E), below Highway 113, Bartow County GA“the parcel is located on both sides of Taff Road, bounded by Floyd Creek Church Road on the west, Raccoon Creek on the right, and is slightly below Highway 113.”News report · June 2025 · grade C
- Name: Project Bunkhouse“A Development of Regional Impact application filed in March 2025 showed that the campus will be called Project Bunkhouse”News report · March 2025 · grade C
- Code names: Project Bunkhouse“A Development of Regional Impact application filed in March 2025 showed that the campus will be called Project Bunkhouse”News report · March 2025 · grade C
- Buildings: 12 buildings“Preliminary plans for Project Bunkhouse were revealed March 31 for a 12-building data center in Bartow County”News report · March 2025 · grade C
- Announced: March 31, 2025“Preliminary plans for Project Bunkhouse were revealed March 31”News report · March 2025 · grade C
Imagery and records: Satellite imagery: Maxar via Esri World Imagery Wayback. County deeds: ATTOM.