Data center profile · Taff Road, Stilesboro, Bartow County, Georgia (south of Plant Bowen)

Project Bunkhouse (Digital Realty, Stilesboro)

Digital Realty and Taurus' planned 1.3 GW, $18B grid-served campus on 876 acres in Bartow County, Georgia: zoned, land bought, no tenant or power contract.

Zoned, land bought. The county commissioner approved the rezoning in June 2025 and the sponsors closed on the land in Feb. 2026. No tenant, electric service agreement, land disturbance or building permit has been found through Oct. 2026, and the county puts full build-out at 2035.
Project Bunkhouse main build site (mass-grading core, west-center parcel), Satellite image, Aug. 25, 2024
1.3 GW
computing capacity, county says
the 2025 regional review put the site-plan power need at 1,830 MW
$18B
build-out value, county says
an earlier regional filing said $19B; estimated value, not committed money
876 acres
land closed Feb. 2026
price not disclosed; bought from Gaines Family Land
2035
full build-out target
county reporting; no phase schedule disclosed
OperatorTaurus DC SPE LLC (developer of record); Digital Realty named as the project sponsor at the county hearing
CustomerNone identified
Planned IT capacity1.3 GW at full build-out (company IT figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet).
Next deadline2035: Full build-out date in county reporting; no nearer dated step is on record
The site

The site from above

Satellite overview1
Satellite image, Aug. 25, 2024. Pin: Project Bunkhouse main build site, mass-grading core, west-center parcel.
Power

Power and the grid

None energized or contracted yet

Georgia Power grid servicePlanned, no contract on record
1,830 MW
site-plan power need in the 2025 regional review; the county cites 1.3 GW of computing capacity; no signed service agreement found News report · March 2025
Proposed
Not used, not on record, or dropped

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. Jan. 23, 2025
    Georgia large-load rule
    State regulators let Georgia Power require minimum bills, up to 15-year contracts and collateral from customers of 100 MW or more. Utility regulator · Jan. 2025
  2. June 4, 2025
    Supply plan stated
    The applicant says power would come from existing transmission lines that cross the site; no utility filing names the campus. Local government · June 2025
  3. As of Oct. 2026
    No air permit filing
    No state air permit filing for on-site generation was found. see Permits
  4. Not set
    Service agreement: none found
    No signed Georgia Power contract is on record; any contract of 100 MW or more must go to state regulators for review. Utility regulator · Jan. 2025

What is next door

campus0.45 km · Dalton Lateral (gas, Transcontinental Gas)0.52 km · Villa Rica1.69 km · Plant Bowen (Georgia Power)2.08 km · Bowen NDPES Substation (46 kV, Georgia Power)2.18 km · Unnamed (115 kV)campus12345
  1. 10.45 km · Dalton Lateral (gas, Transcontinental Gas)
  2. 20.52 km · Villa Rica
  3. 31.69 km · Plant Bowen (Georgia Power)
  4. 42.08 km · Bowen NDPES Substation (46 kV, Georgia Power)
  5. 52.18 km · Unnamed (115 kV)

Distances from mapped lines and plants. OpenStreetMap · Oct. 2026

Permits

Permits checklist

1 granted · 3 checked, nothing on file

Approvals a campus like this normally needs (including an air permit for backup generators), and what we found.

Risks

What could slow it down

Money

Money on record

$18B
build-out value
county figure; the $19B in the 2025 filing is also an estimate Local government · Aug. 2026
$40M to $50M
projected yearly county tax revenue
county reporting, April 2026 News report · April 2026

Not on record: tax breaks: no abatement, exemption or payment in lieu of taxes, full millage applies Local government · Aug. 2026; financing: no lender or financing found SEC filing · Oct. 2026

Land assembly

No arm's-length land purchase by the campus company is in county records. 2 related-party transfers are shown greyed. 1 sale or conveyance by the campus company or to public bodies is not listed. Parcel counts come from the deed; acreage is not recorded.

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Sept. 2024
    Paper trail Taurus DC SPE LLC registered in Delaware
  2. March 2025
    Site A regional review filing reveals Project Bunkhouse: 12 buildings, $19B, 1,830 MW News report · March 2025
  3. May 2025
    Permits Planning commission recommends approval with conditions Local government · June 2025
  4. June 4, 2025
    Permits County commissioner approves the rezoning with six conditions; two residents speak against Local government · June 2025
  5. Feb. 2026
    Money Taurus and Digital Realty close on the 876-acre site (press) News report · Feb. 2026
  6. Feb. 17, 2026
    Site County administrator confirms the developers have closed on the land News report · Feb. 2026
  7. July 1, 2026
    Permits County adopts data center standards: closed-loop cooling, noise limits and a 300 MW cap on accessory generation Local government · Aug. 2026
  8. Aug. 3, 2026
    Money County policy statement names the Digital Realty project at 1.3 GW and $18B and rules out tax breaks Local government · Aug. 2026
  9. 2035
    Construction Full build-out date in county reporting News report · April 2026
Construction activity

Satellite captures by quarter

Since Feb. 2022: 71 satellite captures. The chart starts in the first quarter of 2023; 4 earlier records are not drawn.

Satellite
’23
’24
’25
’26
Dot size: records in the quarter, largest = 6. Two-digit years mark each first quarter.
The buildings

Specs

12 buildings
planned, in about 8.3 million sq ft (the rezoning cap)
3 substations
on site, in the regional review filing
625,000 gallons a day
water use stated in 2025; closed-loop cooling is now required countywide
65 dB day, 55 dB night
noise limits at residential boundaries under the July 2026 county ordinance
800+ jobs
forecast by the county
Who is involved

Owners, partners and builders

Owners and developers
  • Taurus DC SPE LLC: applicant, developer of record and landowner since Feb. 2026
  • Digital Realty: project sponsor, per its counsel and the county
  • Taurus Investment Holdings: reported co-sponsor (press)
  • Gaines Family Land, LLC: seller of the land
Decision-makers
  • Bartow County Commissioner: sole zoning authority
  • Georgia Power: serving utility
  • Bartow County Water Department: approves public water for cooling
Advisers
  • Kimley-Horn: engineer on the regional filing
  • Schreeder, Wheeler & Flint: rezoning counsel
Still unknown

Open questions

Where this comes from

306 records from 19 documents

Drawn from public and commercial datasets, news reports, securities filings, business registries, local government records, utility regulator dockets, state agency records, our own analysis and satellite captures, each kept with its date and source. The bar shows documents by type.

Dataset 9News report 6SEC filing 3Local government 2Utility regulator 1State agency 1Analysis 1Satellite 0
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (23)
  • IT capacity: 1,300 MW
    “Digital Realty investment in the Stilesboro area, planned for approximately 1.3 gigawatts of computing capacity”
  • Regulatory standards: Ordinance Z-26-00027 (adopted Jul 1 2026), Zoning Ordinance Sec. 9.9: closed-loop cooling required; noise 65 dB day / 55 dB night at residential boundary; accessory generation capped at 300 MW firm;
    “generation is capped at three hundred megawatts of firm load to preserve its accessory character”
  • Utility: Georgia Power
    “all the power will come off the existing lines and into the substation at the corner of Brandon Farm Road and Taff Road”
  • Substation: Substation at Brandon Farm Road and Taff Road (Georgia Power)
    “all the power will come off the existing lines and into the substation at the corner of Brandon Farm Road and Taff Road”
  • Interconnection status: No Georgia Power or PSC filing naming the campus found; applicant states supply from existing transmission lines crossing the site
    “There will be no need to run any additional power lines because there is a sufficient number of existing lines running through the site”
  • Power plan: grid
    “all the power will come off the existing lines and into the substation at the corner of Brandon Farm Road and Taff Road”
  • Grid operator: none - SERC region; Georgia has no ISO/RTO market
    “Assessment from rows in this folder: the utility record is Georgia Power, a vertically integrated utility in the SERC region; Georgia has no ISO or RTO market”
    grade B
  • Electric service agreement signed: No executed electric service agreement found; any Georgia Power contract at or above 100 MW must be submitted to the PSC for review under the Jan 2025 rule
    “any new customers using more than 100 megawatts of energy can be billed using terms and conditions beyond those used for standard customers”
  • Rate class: Georgia Power large-load terms under PSC rule from Docket 55378: minimum billing, contract lengths up to 15 years, collateral and termination payments, PSC review of contracts
    “In addition to site specific costs, the data centers would pay for costs incurred by upstream generation, transmission and distribution to these large-load power users”
  • Nearest substation: Bowen NDPES Substation (46 kV, Georgia Power) - 2.08 km
    Measured on OpenStreetMap map data.
  • Nearest power line of 345 kV or more: Villa Rica - Bowen 500kV #1 (500 kV, Georgia Power) - 0.52 km
    Measured on OpenStreetMap map data.
  • Nearest power line of 138 kV: unnamed (115 kV) - 2.18 km
    Measured on OpenStreetMap map data.
  • Nearest gas pipeline: Dalton Lateral (gas, Transcontinental Gas Pipeline Company) - 0.45 km
    Measured on OpenStreetMap map data.
  • Nearest generation plant: Plant Bowen (Georgia Power) - 1.69 km
    Measured on OpenStreetMap map data.
  • Phases: No phase split or per-phase MW disclosed in any source opened
    “The campus is permitted for 12 buildings totaling 8.6 million square feet of data center space”
  • Buildings planned: 12 buildings
    “The campus is permitted for 12 buildings totaling 8.6 million square feet of data center space, with 1,830 megawatts of total power capacity and three on-site substations”
  • Project name: Project Bunkhouse
    “A Development of Regional Impact application filed with the Georgia Department of State Affairs in March 2025 showed that the campus will be called Project Bunkhouse.”
  • Stated campus size: 1,830 MW
    “A site plan obtained by The Atlanta Journal-Constitution shows Project Bunkhouse power needs could be 1,830 megawatts and would require three on-site substations”
  • On-site substations: 3 substations
    “would require three on-site substations”
  • On-site power technology: None proposed - grid-served campus; no on-site generation in the DRI or site-plan reporting
    “would require three on-site substations”
  • DRI filing revealed by AJC: Project Bunkhouse, 12 buildings, ~8.6M sq ft, $19B estimated build-out value, 1,830 MW site-plan power need
    “Preliminary plans for Project Bunkhouse were revealed March 31”
  • Stated campus size: 1,830 MW
    “Project Bunkhouse, which would be built on a nearly 900-acre site adjacent to a coal power plant in Bartow County, could consume 1,830 MW at full build-out”
  • System context only, NOT a campus position: the Georgia PSC large-load rule approved Jan 23, 2025 (Docket 44280) lets Georgia Power bill new customers over 100 MW on non-standard terms covering site-specific plus upstrea
    “any new customers using more than 100 megawatts of energy can be billed using terms and conditions beyond those used for standard customers”
Money and contracts (25)
  • Stated capital cost: 18000000000 USD
    “has indicated a total build-out capital investment on the order of eighteen billion dollars”
  • Incentives: No county tax abatement, exemption or PILOT: full assessed value taxed at the full applicable millage rate
    “Bartow County has granted no tax abatements in connection with these facilities. It has entered into no reduction, exemption, or payment-in-lieu-of-taxes arrangement”
  • tax treatment: abatement / PILOT - none No reduction, exemption or payment-in-lieu-of-taxes arrangement; full assessed value on the digest at full millage
    “The full assessed value of each facility will be accordingly entered on the digest and taxed at the full applicable millage rate”
  • Square feet: 8300000 sq ft
    “The total square footage of all buildings to be constructed on the property shall be limited to 8,300,000 square feet”
  • Conditions of approval: Six conditions in the Z-25-00020 approval: prohibited BPD uses list; buffers per Conceptual Site Plan before any certificate of occupancy; 8,300,000 sq ft total cap; primary access from Taff Road
    “o The total square footage of all buildings to be constructed on the property shall be limited to 8,300,000 square feet”
  • rezoning approval Z-25-00020: scope - permitted and prohibited uses Data center use; prohibited BPD uses: distribution facilities, manufacturing/fabricating/processing/assembling, manufacturing, outdoor storage (except d
    “The following Business Park uses permitted by Section 7.18.3 of the Zoning Ordinance are prohibited: Distribution Facilities; Manufacturing; Outdoor Storage (except during construction); Retail Uses; Warehousing”
  • rezoning approval Z-25-00020: size cap 8300000 sq ft
    “The total square footage of all buildings to be constructed on the property shall be limited to 8,300,000 square feet”
  • rezoning approval Z-25-00020: condition precedent to occupancy No certificate of occupancy for any building until the buffers adjoining it are in place and improved as depicted on the Conceptual Site Plan
    “no buildings shall be granted a certificate of occupancy until any buffers adjoining such building are in place and improved as depicted on the Site Plan”
  • rezoning approval Z-25-00020: access Primary access from Taff Road; Floyd Creek Church Road access limited to secondary uses including emergency vehicle access
    “Primary access to the improvements shall be from Taff Road. Any access from Floyd Creek Church Road shall be limited to secondary uses, including emergency vehicle access”
  • rezoning approval Z-25-00020: water and cooling condition Water-efficient HVAC required; public water for equipment or building cooling subject to Bartow County Water Department approval
    “The development shall utilize water efficient HVAC technology and the utilization of public water for equipment or building cooling shall be subject to approval by the Bartow County Water Department”
  • rezoning approval Z-25-00020: compliance condition Development must comply with the Data Center definition, Section 3.2 of the Bartow County Zoning Ordinance
    “The development shall comply with all requirements as specified in the definition of a Data Center as set forth in Section 3.2 of the Bartow County Zoning Ordinance”
  • Financing: None disclosed - no closed financing, lender or instrument found in sources opened; the $19B DRI figure is estimated build-out value, not committed capital
    “SEC EDGAR full-text searches for Taurus DC SPE, Project Bunkhouse and Bartow in Digital Realty filings returned zero hits”
  • Land purchase (recorded deed): contract value 95000000 USD
    “Recorded: Jan. 30, 2026 · Price: $95,000,000 · Grantor: GAINES FAMILY LAND LLC · Grantee: EXETER 1762 LLC · Parcel number: 0032-1122-001 · Address: FLOYD CREEK CHURCH RD · City: TAYLORSVILLE”
  • electric service agreement: existence No executed ESA found; no PSC filing naming the campus located
    “any new Georgia Power contract with a company that fits the 100 MW usage category must be submitted to the PSC for review”
  • electric service framework (PSC rule, Docket 55378): termination and minimum-bill terms available to the utility Minimum billing requirements; contract lengths extended from 5 to 15 years; collateral and substantial term
    “The new rule also allows for longer contract lengths (from 5-year contracts to 15-year contracts) and minimum billing requirements for high-load customers”
  • Land purchase (recorded deed): contract value USD
    “Recorded: June 15, 2023 · Grantor: GAINES · Grantee: GAINES FAMILY LAND LLC · Parcel number: 0032-1122-001 · Address: FLOYD CREEK CHURCH RD · City: TAYLORSVILLE”
  • Land purchase (recorded deed): contract value USD
    “Recorded: July 7, 2022 · Grantor: GAINES · Grantee: GAINES FAMILY LAND LLC · Parcel number: 0032B-0003-006 · Address: 51 FLOYD CREEK CHURCH RD · City: TAYLORSVILLE”
  • Tenants: No tenant or end user identified in any source opened
    “No additional information could be found about the applicant, Taurus DC SPE LLC. The end user is also unknown.”
  • Tenant status: none found - no tenant announced
    “The end user is also unknown”
  • Land price: Not disclosed in any source opened
    “closed on 876 acres of cattle farm in Stilesboro in February 2026”
  • Projected annual tax revenue: 40000000-50000000 USD/yr
    “Bartow County is projecting $40-50 million in annual property tax revenue once the campus is fully operational”
  • Land closing reported (Daily Tribune News via The Connector): Taurus Investment Holdings and Digital Realty closed on the 876-acre Stilesboro site, purchase from Gaines Family Land LLC
    “closed on 876 acres of cattle farm in Stilesboro in February 2026”
  • land purchase: closing Closed February 2026; price not disclosed
    “Taurus Investment Holdings (Boston, MA) and Digital Realty (San Francisco, CA) closed on 876 acres of cattle farm in Stilesboro in February 2026”
  • Sponsor group (Taurus Investment Holdings / Digital Realty) closed on the 876-acre site in February 2026, after the June 2025 rezoning approval; full build-out is scheduled for 2035 per county reporting
    “Taurus Investment Holdings (Boston, MA) and Digital Realty (San Francisco, CA) closed on 876 acres of cattle farm in Stilesboro in February 2026”
  • Stated capital cost: 19000000000 USD
    “the applicant estimates the campus will be worth $19 billion if completed”
Permits and government (25)
  • data center standards ordinance: adopted
    “the Commissioner adopted comprehensive data center development standards by Ordinance Z-26-00027, codified at Article IX, Section 9.9 of the County Zoning Ordinance”
  • Bartow County issues data-center policy statement: no abatements or PILOTs, full taxation; names Digital Realty Stilesboro investment at ~1.3 GW computing capacity and ~$18B build-out; 800+ jobs forecast
    “Digital Realty investment in the Stilesboro area, planned for approximately 1.3 gigawatts of computing capacity, has indicated a total build-out capital investment on the order of eighteen billion dollars”
  • Bartow County Commissioner: Adoption of Ordinance Z-26-00027 - comprehensive data center development standards (Zoning Ordinance Sec. 9.9)
    “the Commissioner adopted comprehensive data center development standards by Ordinance Z-26-00027, codified at Article IX, Section 9.9 of the County Zoning Ordinance”
  • Cooling: Closed-loop cooling mandated countywide by Ordinance Z-26-00027 (Zoning Ordinance Sec. 9.9(7)), adopted July 1 2026
    “the data center standards adopted July 1, 2026, require every facility to use a closed-loop or functionally equivalent cooling system”
  • Developer: Digital Realty project, per applicants counsel on the record at the June 4 2025 county hearing; county policy statement names it Digital Realtys investment in the Stilesboro area
    “This is a Digital Realty project. It is not a Crypto center.”
  • Rezoning date: June 4, 2025
    “Commissioner Taylor approved the application with the following conditions”
  • Opposition: Two registered speakers at the Jun 4 2025 hearing: Gail Cochran (transmission lines / property) and Patty Everett (opposed; pasture and property values). No Bunkhouse-specific group, petition or lawsuit found
    “Ms. Patty Everett, 11 Apple Barrel Way, Taylorsville, spoke in opposition to the application”
  • rezoning: approved with conditions
    “Commissioner Taylor approved the application with the following conditions”
  • future land use map amendment: approved
    “change the Land Use Map from Agricultural to Industrial for the purpose of developing a Data Center”
  • planning commission recommendation: recommended approval with conditions
    “The Planning Commission recommended approval with a number of conditions”
  • Hearing opposition limited to two registered speakers and no organized campaign found - in contrast to other Bartow proposals (Atlas/Barnsley) that drew a ~1,700-signature petition and denial recommendations
    “Ms. Patty Everett, 11 Apple Barrel Way, Taylorsville, spoke in opposition to the application stating that she just does not want it”
  • Bartow County Planning Commission: Z-25-00020 - Taurus DC SPE LLC rezoning, 876.57 acres Taff Road (A-1 to BPD)
    “The Planning Commission recommended approval with a number of conditions”
  • Bartow County Commissioner (sole commissioner Steve Taylor): Z-25-00020 public hearing and decision - Project Bunkhouse data center
    “Commissioner Taylor approved the application with the following conditions”
  • air permit: no filing found
    “no Taurus, Stilesboro or Bunkhouse filing”
    grade B
  • Permitting authority: Bartow County sole commissioner for zoning (Zoning Procedures Law); GA DCA / Northwest Georgia Regional Commission DRI review is advisory only; GA PSC regulates the utility contract, not the campus
    “Commissioner Taylor approved the application with the following conditions”
  • Georgia Power files its 2025 Integrated Resource Plan (Jan 31 2025) - portfolio context for large-load growth; not campus-specific
    “The Georgia Public Service Commission received Georgia Power's filing for the utility's 2025 Integrated Resource Plan on Jan. 31”
  • GA PSC unanimously approves large-load rule from Docket 55378: Georgia Power may impose minimum bills, up to 15-year contracts, collateral and termination payments on customers at or above 100 MW; contracts go to the PSC
    “The Georgia Public Service Commission voted unanimously on Thursday to approve a new rule that allows Georgia Power to charge new data centers in a manner that will protect ratepayers”
  • Construction stage: none - rezoning approved Jun 2025 and land closed Feb 2026, but no clearing, grading or construction reported in any source opened through Oct 2026
    “Taurus Investment Holdings and Digital Realty closed on 876 acres of cattle farm in Stilesboro in February 2026”
  • land disturbance / building permits: none found
    “closed on 876 acres of cattle farm in Stilesboro in February 2026”
  • Bartow County budget hearing: County Administrator report - Project Bunkhouse land closing
    “County Administrator Peter Olson confirmed the deal at the February 17 budget hearing”
  • Land closed: Taurus Investment Holdings and Digital Realty closed on the 876-acre Gaines Family Land parcel in February 2026 (county administrator confirmed the closing at the Feb 17, 2026 budget hearing)
    “Taurus Investment Holdings (Boston, MA) and Digital Realty (San Francisco, CA) closed on 876 acres of cattle farm in Stilesboro in February 2026”
  • Site acres: 876 acres
    “Bartow Planning Commission has recommended approval for a data center rezoning request for an 876-acre land parcel in Stilesboro to be rezoned from residential to industrial.”
  • Land owner: Gaines Family Land, LLC
    “The land is currently owned by Gaines Family Land LLC, and the rezoning recommendation will have to be approved by the Bartow County Commissioners.”
  • Developer of record: Taurus DC SPE LLC is the rezoning/DRI applicant of record for the 876-acre Stilesboro (Bartow County) site; the end user is undisclosed
    “No additional information could be found about the applicant, Taurus DC SPE LLC. The end user is also unknown.”
  • development of regional impact review: filed; review advisory
    “A Development of Regional Impact application filed with the Georgia Department of State Affairs in March 2025 showed that the campus will be called Project Bunkhouse”
Legal (1)
  • Lawsuits: None found naming Taurus DC SPE LLC or Project Bunkhouse in sources opened
    “No additional information could be found about the applicant, Taurus DC SPE LLC”
Site and other (20)
  • Workforce estimate: 800 jobs
    “Digital Realty forecasts total employment in excess of 800 jobs once the campus is complete”
  • Developer: Taurus DC SPE LLC (applicant and developer of record)
    “Z-25-00020; an application by Taurus DC SPE LLC requesting to rezone and change the Land Use Map for 876.57 acres on Taff Road”
  • Owner companies: Taurus DC SPE LLC
    “an application by Taurus DC SPE LLC requesting to rezone and change the Land Use Map for 876.57 acres on Taff Road”
  • Address: Taff Road, Stilesboro (unincorporated), Bartow County, GA; both sides of Taff Road, south of Plant Bowen, below Highway 113
    “876.57 acres on Taff Road. The property is located south of Plant Bowen.”
  • Parcel IDs: 0032-1184-001; 0032-1122-001; 0032a-003-002; 0032b-003-006
    “Tax Parcel numbers 0032-1184-001, 0032-1122-001, 0032a-003-002, and 0032b-003-006”
  • Acres: 876.57 acres
    “rezone and change the Land Use Map for 876.57 acres on Taff Road”
  • Cooling: Water-efficient HVAC required by approval condition; public water for cooling subject to Bartow County Water Department approval
    “The development shall utilize water efficient HVAC technology and the utilization of public water for equipment or building cooling shall be subject to approval by the Bartow County Water Department”
  • County code: 13015
    “buildings: Bartow County County GA (13015)”
  • Stage: Entitled and land-closed; not under construction
    “Commissioner Taylor approved the application with the following conditions”
  • Original target date: 2035
    “Full build-out is scheduled for 2035”
  • Current target date: 2035
    “Full build-out is scheduled for 2035”
  • Land control date: Feb. 2026
    “The Project Bunkhouse developers have closed on the land. That seems to be all systems go.”
  • Development stage: land closed preconstruction
    “Taurus Investment Holdings (Boston, MA) and Digital Realty (San Francisco, CA) closed on 876 acres of cattle farm in Stilesboro in February 2026”
  • Water use stated: 625000 gallons/day
    “Official estimates are that Project Bunkhouse will use 625,000 gallons of water daily”
  • Applicant: TAURUS DC SPE LLC
    “No additional information could be found about the applicant, Taurus DC SPE LLC. The end user is also unknown.”
  • Site location description: Stilesboro, both sides of Taff Road, bounded by Floyd Creek Church Road (W) and Raccoon Creek (E), below Highway 113, Bartow County GA
    “the parcel is located on both sides of Taff Road, bounded by Floyd Creek Church Road on the west, Raccoon Creek on the right, and is slightly below Highway 113.”
  • Name: Project Bunkhouse
    “A Development of Regional Impact application filed in March 2025 showed that the campus will be called Project Bunkhouse”
  • Code names: Project Bunkhouse
    “A Development of Regional Impact application filed in March 2025 showed that the campus will be called Project Bunkhouse”
  • Buildings: 12 buildings
    “Preliminary plans for Project Bunkhouse were revealed March 31 for a 12-building data center in Bartow County”
  • Announced: March 31, 2025
    “Preliminary plans for Project Bunkhouse were revealed March 31”

Imagery and records: Satellite imagery: Maxar via Esri World Imagery Wayback. County deeds: ATTOM.