Power and the grid
- Georgia Power grid service Infrastructure under way, no filingMW not disclosed; a Georgia Power transfer station is being built beside the site, per the city manager (press); no PSC filing News report · July 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- July 16, 2026Transfer station under constructionThe Hampton city manager says Georgia Power is building a transfer station next to the site. News report · July 2026
- As of Oct. 2026No PSC filingNo Georgia Public Service Commission docket names the project. State agency · Oct. 2026
- Utility delivery is moving ahead of any public MW figure or regulatory filing. News report · July 2026
Permits checklist
1 pending · 2 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ◷Concept plan review PendingCity of Hampton · Feb. 5, 2026: submitted; no rezoning is requested in the filing; no decision found State agency · Feb. 2026
- –Checked, nothing on file: Rezoning, site plan or council approval, Air permit
What could slow it down
- MediumLocal approval unsettledHampton weighed a 120-day data center moratorium in Feb. 2026, and no rezoning or council approval for the park has been found. Local government · Oct. 2026
- MediumNo user or power figureThe filing gives no information on power use or end user. see Permits
- WatchDeveloper undisclosedOnly the applicant LLC is named; the developer behind it is not. News report · Oct. 2026
What happened, and what is due
- Feb. 5, 2026Permits Developer submits a concept plan for city review State agency · Feb. 2026
- Feb. 10, 2026Permits Hampton's council agenda carries a proposed 120-day data center moratorium Local government · Oct. 2026
- Feb. 13, 2026Site Hampton Technology Park Owner files a regional impact filing for five buildings on 603 acres State agency · Feb. 2026
- June 2, 2026Permits The state determines the project warrants regional review State agency · June 2026
- June 16, 2026Permits The Atlanta Regional Commission issues its finding, closing the regional review State agency · June 2026
- July 16, 2026Power The city manager says Georgia Power is building a transfer station next to the site (press) News report · July 2026
Specs
5 buildings proposed, 4 million sq ft in total. State agency · Feb. 2026
Owners, partners and builders
- Hampton Technology Park Owner, LLC (c/o Dillard Sellers): applicant
- City of Hampton: concept plan and any rezoning
- Atlanta Regional Commission and Georgia DCA: regional review, now closed
- Georgia Power: transfer station
Open questions
- MW, tenant and cost.
- City approval and moratorium outcome.
- Developer identity behind the LLC.
- Whether construction has begun.
44 records from 7 documents
Drawn from state agency records, news reports and local government records, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (6)
- Stated campus size: 1,500 MW“What is the project's estimated peak connected electrical load (in Megawatts)? 1,500 MW peak”State agency · April 2026 · grade A
- Utility: Georgia Power“Name of energy supply provider(s) for this site: Georgia Power”State agency · April 2026 · grade A
- Equinix's 240 MW four-building Hampton-area campus is a separate project; its 240 MW must not be attributed to Hampton Technology Park“Equinix is developing a 240MW, four-building campus in the area.”News report · Oct. 2026 · grade C
- Georgia Power is building a transfer station immediately adjacent to the Hampton Technology Park site (per the Hampton city manager, reported July 2026) - utility delivery infrastructure is moving ahead of any public MW“Immediately behind the cemetery, the city manager told reporters, Georgia Power is building a transfer station. It rises alongside Hampton Technology Park”News report · July 2026 · grade C
- DRI application filed with the Georgia Department of Community Affairs: 603 acres on Lower Woolsey Road, up to five buildings and 4 million sq ft, build-out to 2033. No MW, tenant or project cost is disclosed in coverage“The 603-acre Hampton Technology Park could total five buildings and 4 million sq ft (371,610 sqm). The project, along Lower Woolsey Road, could be built out to 2033.”News report · Feb. 2026 · grade C
- Hampton Technology Park Owner LLC filed a DRI application with Georgia DCA for a campus in the city of Hampton; five buildings, 4 million sq ft, Lower Woolsey Road, build-out to 2033; no power figure or end user stated i“Hampton Technology Park Owner, LLC has filed a Developments of Regional Impact (DRI) application with the Georgia Department of Community Affairs”News report · Feb. 2026 · grade C
Money and contracts (1)
- energy supply (DRI-stated): electric service arrangement“new substation infrastructure will be located on development site with Georgia Power”State agency · April 2026 · grade A
Permits and government (12)
- The Atlanta Regional Commission issued its regional-development-center finding o: RDC finding issued for DRI #4624 (June 16, 2026)“RDC Finding: 6/16/2026”State agency · June 2026 · grade A
- DRI regional finding: RDC finding issued“RDC Finding: 6/16/2026”State agency · June 2026 · grade A
- JURISDICTION VERIFIED from the state record: Hampton Technology Park, city of Ha: DRI #4624: determination 'Warrants regional review' (June 2, 2026); regional review completed“DRI Determination: 6/2/2026 Warrants regional review”State agency · June 2026 · grade A
- DRI determination: DRI determination: warrants regional review“DRI Determination: 6/2/2026 Warrants regional review”State agency · June 2026 · grade A
- The only local-government action requested in the DRI initial form is Concept Plan Review (submitted 2/5/26); no rezoning requested of the City of Hampton in that filing“The action being requested of the local government for this project: Concept Plan Review (submitted 2/5/26)”State agency · Feb. 2026 · grade A
- The only local-government action requested in the DRI form is Concept Plan Review, submitted Feb. 5, 2026; no rezoning is stated in the form“The action being requested of the local government for this project: Concept Plan Review (submitted 2/5/26)”State agency · Feb. 2026 · grade A
- Byron council minutes of Sept 2, 2026 record the Hampton Technology Park site (70 Woolsey Road) as 'under construction' and refer to it as 'the QTS Data Center'; the council noted transmission line location and ~558.38 a“This data center was under construction”Local government · Sept. 2026 · grade B
- Southeast Property Holdings'“Southeast Property Holdings, LLC applied for a conditional use permit to permit a data center campus on 133 acres in Hampton.”News report · Oct. 2026 · grade C
- The City of Hampton was considering a 120-day moratorium on data center development while the Hampton Technology Park DRI was in review - the local-approval climate for the campus's later phases is unsettled even though“It is currently considering a 120-day moratorium on data center development in order to give the city time to better assess their impact”News report · Oct. 2026 · grade C
- Site location: Lower Woolsey Road, Hampton GA (DRI land lots; Byron council minutes place the site at 70 Woolsey Road)“The 603-acre Hampton Technology Park could total five buildings and 4 million sq ft (371,610 sqm). The project, along Lower Woolsey Road, could be built out to 2033.”News report · Feb. 2026 · grade C
- The City of Hampton (this campus's jurisdiction) is considering a 120-day moratorium on data center development to give the city time to assess impacts. Status of the moratorium after Feb 2026 was not retrieved in this p“It is currently considering a 120-day moratorium on data center development in order to give the city time to better assess their impact.”News report · Feb. 2026 · grade C
- Hampton was considering a 120-day moratorium on data center development while assessing impacts; status of the moratorium after Feb 2026 was not retrieved in this pass“Hampton is a city in southwestern Henry County, some 35 miles south of Atlanta. It is currently considering a 120-day moratorium on data center development in order to give the city time to better assess their impact.”News report · Feb. 2026 · grade C
Site and other (6)
- Georgia DCA DRI #4624 process completed 7/2/2026 (determination 'warrants regional review' 6/2/2026; ARC finding 6/16/2026)“Current Status: Completed; Projected Process Completion Date: 7/2/2026”State agency · July 2026 · grade A
- Georgia DCA / Atlanta Regional Commission process: DRI determination June 2, 2026 warrants regional review; completeness certification and request for comments same date; RDC finding June 16, 2026“DRI Determination: 6/2/2026 Warrants regional review; Completeness Certification: 6/2/2026; RDC Finding: 6/16/2026”State agency · June 2026 · grade A
- Project identity: Hampton Technology Park - proposed technology facility, five buildings (4,000,000 sf) on approximately 603.56 acres, Lower Woolsey Road, Hampton GA (GA DCA DRI #4624)“Proposed Technology Facility with five buildings (4,000,000 sf) located on approximately 603.56 acres.”State agency · Feb. 2026 · grade A
- Announced: Feb. 13, 2026“Initial DRI Information Form Submitted: 2/13/2026”State agency · Feb. 2026 · grade A
- Project status: under construction (observed Sept. 2, 2026)“This data center was under construction”Local government · Sept. 2026 · grade B
- County code: 13151“Hampton is a city in southwestern Henry County, some 35 miles south of Atlanta.”News report · Feb. 2026 · grade C