The site from above
Power and the grid
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Aug. 26, 2026Utility MW on record3,200 MW. Company · Aug. 2026
Permits checklist
5 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- –Checked, nothing on file: Zoning approval, Site plan, Building permit, Water and wetlands permits, Utility and grid approval
What could slow it down
- MediumLawsuitA second lawsuit filed Sept. 21, 2026 by One Hundred Miles and residents against the Effingham County Industrial Development Authority (ECIDA) challenges open-meetings and records compliance and the tax abatement. News report · Sept. 2026
- MediumLawsuitA resident lawsuit filed Sept. 2, 2026 in Effingham County Superior Court challenges the county's data center ordinance that made data centers a by-right use. Company · Sept. 2026
2 cases on record
- Pending A resident lawsuit filed Sept. 2, 2026 in Effingham County Superior Court· filed Sept. 2, 2026A resident lawsuit filed Sept. 2, 2026 in Effingham County Superior Court challenges the county's data center ordinance that made data centers a by-right use.
- Pending A second lawsuit filed Sept. 21, 2026 by One Hundred Miles· filed Sept. 21, 2026A second lawsuit filed Sept. 21, 2026 by One Hundred Miles and residents against the Effingham County Industrial Development Authority (ECIDA) challenges open-meetings and records compliance and the tax abatement.
What happened, and what is due
- July 22, 2026Site Project first appears in the public record
- Sept. 2, 2026Legal A resident lawsuit filed Sept. 2, 2026 in Effingham County Superior Court challenges the county's data center ordinance that made data. Company · Sept. 2026
- Sept. 21, 2026Legal A second lawsuit filed Sept. 21, 2026 by One Hundred Miles and residents against the Effingham County Industrial Development Authority (ECIDA) challenges open-meetings and records compliance. News report · Sept. 2026
Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026
Owners, partners and builders
- Octans GA, developer
- OpenAI, tenant
- Effingham County Industrial Development Authority, public agency
Open questions
- Signed electric service agreement and delivery date.
- Whether site work has started.
21 records from 8 documents
Drawn from news reports, company statements, public and commercial datasets and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (3)
- Project status: announced“Today, Georgia Power announced that its contract to serve OpenAI's new project in Effingham County has been approved”Company · Aug. 2026 · grade B
- Utility service: 3,200 MW“The company's contract with OpenAI was filed with the Georgia PSC in July and includes 3,200 megawatts (MW) of new demand”Company · Aug. 2026 · grade B
- Utility: Georgia Power“Georgia Power announced that its contract to serve OpenAI's new project in Effingham County has been approved”Company · Aug. 2026 · grade B
Money and contracts (4)
- County code: 13103“its contract to serve OpenAI's new project in Effingham County has been approved”Company · Aug. 2026 · grade B
- power supply contract: approved“OpenAI will pay the full cost of the infrastructure needed to serve it and has committed up to 1,000 MW of flexible demand response”Company · Aug. 2026 · grade B
- land sale: closed“the sale of the property to Octans Ga. LLC, the listed developer for Project Camellia”News report · Aug. 2026 · grade C
- tax abatement: approved“The package provides OpenAI with a 50% property tax abatement for 15 years”News report · Aug. 2026 · grade C
Legal (2)
- A second lawsuit filed Sept. 21, 2026 by One Hundred Miles and residents against ECIDA challenges open-meetings and records compliance and the tax abatement.“One Hundred Miles joined three Effingham County residents in the suit filed Monday in Effingham County Superior Court”News report · Sept. 2026 · grade C
- A resident lawsuit filed Sept. 2, 2026 in Effingham County Superior Court challenges the county's data center ordinance (Ordinance 2026-352) that made data centers a by-right use.“filed suit on September 2, 2026, against Effingham County, Georgia, to overturn the County's new 'data center ordinance'”Company · Sept. 2026 · grade C
Site and other (5)
- Announced: July 22, 2026“Project Camellia is a long-term AI infrastructure project that OpenAI is designing and developing in Effingham County”Company · July 2026 · grade A
- Building count: 4 buildings“The submitted form describes four data center buildings encompassing about 101 acres”News report · Sept. 2026 · grade C
- The Development of Regional Impact review released Sept. 16, 2026 (Coastal Regional Commission) covers the site, which includes wetlands and a state-protected plant species.“The Development of Regional Impact (DRI) review was released on September 16, 2026”News report · Sept. 2026 · grade C
- Campus name: Project Camellia“OpenAI, which announced its 1,400-acre Project Camellia data center in Effingham County last month”News report · Aug. 2026 · grade C
- Site acreage: 1400 acres“announced its 1,400-acre Project Camellia data center in Effingham County”News report · Aug. 2026 · grade C
Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).