The site from above
Watch the site change
One clear satellite frame per quarter, April 2024 to October 2026. Drag the slider or press play.

Sentinel-2 satellite, 10 m resolution (coarser than the photos above).
What radar sees on the ground
From orbit, radar echoes from walls and steel start climbing in Nov. 2025. The optical (Sentinel-2) series for this campus is not in yet, so there is no roof or clearing reading. That fits our stage: vertical construction.
How this works: Sentinel-1 radar sees through cloud every 6–12 days. Over the campus outline (about 790 acres) we count the share of very bright radar echoes: walls and steel bounce the signal straight back, so that share rises as buildings go up. Wet ground can lift it for a few weeks, so we read the trend, not single readings. Black ticks mark our stage dates. Data: Copernicus Sentinel-1 and Sentinel-2, via the Copernicus Data Space Ecosystem.
Power and the grid
None energized or contracted yet
- Aligned backup diesel generators (172) State air permit granted Jan. 30, 2025 (press)508 MW; backup only; not prime power State agency · March 2026
- Amazon backup diesel generators (99) State air permit effective Mar. 25, 2026258 MW; state-stated total; barred from serving as primary power or joining demand response State agency · March 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Oct. 2022Substation announcedPotomac Edison plans a 230 kV substation near the center of the park, sized for 240 MW in the first phase and up to 1,000 MW later. Company · Oct. 2022
- Aug. 14, 2024Substation site plan approvedThe Planning Commission conditionally approves an electric substation on a 7.7-acre area, valid to Aug. 14, 2027. Local government · Aug. 2024
- Sept. 20, 2024Substation building permits issuedThe county issues permits for substation foundations and a control building (about $0.4M to $1.9M each). Local building-permit records · Sept. 2024
- March 12, 2025Second substation site plan approvedThe Planning Commission approves an Aligned electric substation site plan. Local government · March 2025
- Not setUtility service agreement: not on recordOnly the 240 MW first-phase utility figure from 2022 is public; no delivered megawatts or in-service dates for the full park appear. Company · Oct. 2022
- Both generator permits limit the diesel fleets to emergency and testing use; the state says Amazon's 99 units may not serve as primary power. State agency · March 2026
- In 2023 the state utility commission treated Aligned's generators as a single 504 MW power station and denied an exemption; Aligned withdrew in Oct. 2023 and returned in 2024 after a state law reclassified backup generation. Utility regulator · Oct. 2023
- The owner says it spent roughly $200M to secure power supply for the park. Local government · Sept. 2026
Grid upgrades
No grid upgrade for this campus's load is on record. Related grid records in the area:
- PJM's supplemental list carries only Allegheny Power (FirstEnergy) equipment work at this campus's 500 kV point-of-interconnection area: S3540.1 replaces the line trap, substation conductor and relaying at Doubs… Dataset · Dec. 2025
What is next door
Distances from mapped lines and plants. OpenStreetMap · Oct. 2026
Permits checklist
1 denied · 1 withdrawn · 2 pending · 7 granted
Approvals a campus like this normally needs, and what we found.
- ✕Long-term development agreement (8-year zoning freeze, $100M+ in benefits) DeniedFrederick County Executive · Sept. 14, 2026: rejected the same day the pause was extended; never signed Local government · Sept. 2026
- ↩Generator exemption from a power-plant certificate (Aligned) WithdrawnMaryland Public Service Commission · Oct. 25, 2023: denied Aug. 2, 2023 as a 504 MW station; Aligned rejected a 70 MW provisional order Oct. 25, 2023; returned in 2024 under a new state law Utility regulator · Oct. 2023
- ◷Amazon air permit for a second facility PendingMaryland Department of the Environment · March 25, 2026: applied; public meeting held May 28, 2026 State agency · March 2026
- ◷Aligned building 1, full construction (about 447,600 sq ft) PendingFrederick building department · April 3, 2025: filed Apr. 2025 with a $400M job value, architect HKS; no issue date on record Local building-permit records · April 2025
- ✓Data center overlay zone and rezoning GrantedFrederick County Council · Jan. 20, 2026: ordinance mapping 2,614.9 acres; upheld against a referendum bid in June 2026 Local government · Jan. 2026
- ✓Preliminary plan and water and sewer capacity (18.3M sq ft) GrantedFrederick County Planning Commission · Dec. 15, 2021: amended in 2023 and 2024 Local government · Dec. 2021
- ✓Aligned first building site plan GrantedFrederick County Planning Commission · May 10, 2023: conditional approval for 450,000 sq ft Local government · May 2023
- ✓Rowan site plans for three buildings GrantedFrederick County Planning Commission · 2025: first building approved 5-0 in Jan. 2025; the next two in May 2025 (press) News report · Jan. 2025
- ✓Aligned air permit (172 backup generators) GrantedMaryland Department of the Environment · Jan. 30, 2025: press account News report · Jan. 2025
- ✓Amazon air permit (99 backup generators) GrantedMaryland Department of the Environment · March 25, 2026: emergency use only; no appeal confirmed State agency · March 2026
- ✓Foundation package for Aligned's first building (2-story, about 447,000 sq ft) GrantedFrederick building department · Feb. 13, 2025: job value $11.8M Local building-permit records · Feb. 2025
What could slow it down
- HighExpansion frozen by the countyThe County Executive rejected the owner's agreement and paused new applications to Jul. 1, 2027; the pause excludes projects under construction or approved before Jun. 17, 2025. Local government · Sept. 2026
- HighPark-scale power not shownThe only public utility figure is 240 MW for the first phase, and both generator permits are for backup use only. Company · Oct. 2022
- MediumState review of large campusesOn Sept. 23, 2026 the Governor ordered a statewide review framework for campuses of 25 MW or more. News report · Sept. 2026
- MediumOwner v. county and a failed land saleThe owner says the pause was election-driven and that a land deal above $500M collapsed after the agreement was rejected (allegations in its suit). see Lawsuits
- WatchDiesel fleet emissionsAt a Dec. 8, 2025 meeting, state staff said current law weighs generator emissions site by site, not across the whole park. State agency · Dec. 2025
3 cases on record
- Decided: referendum blocked In re Frederick County Data Center Referendum CommitteeFrederick County Circuit Court, then Supreme Court of Maryland · filed June 18, 2026 News report · June 2026The circuit court ruled Jun. 18, 2026 that the overlay ordinance is not subject to referendum; the Supreme Court of Maryland affirmed on Jun. 30 and issued its opinion on Jul. 24, after 21,029 valid petition signatures.
- Pending Quantum Maryland LLC v. Fitzwater, Frederick County and the Planning CommissionFrederick County Circuit Court · filed Oct. 2026 News report · Oct. 2026Seeks to void the pause on applications and recover damages, alleging the County Executive overstepped her authority (press).
- Decided Jul. 14, 2026 Sugarloaf Alliance v. Frederick CountySupreme Court of Maryland · filed July 14, 2026 Court filing · July 2026Public-records fee case: the court held a $25,000 award to Sugarloaf was an abuse of discretion; the underlying case released records showing county staff drafted the data center zone with Amazon representatives in 2021.
Money on record
6 recorded land documents for the campus company in county records (June 2021 to Dec. 2025); 6 list a price. 1 sale or conveyance by the campus company or to public bodies is not listed. Parcel counts come from the deed; acreage is not recorded.
- June 2021 Eastalco Aluminum Company and Alumax of Maryland Inc to Quantum Maryland LLC · $100M · 10 parcels County deed records · June 2021
- Sept. 2022 Quantum Maryland LLC to Aligned Data Centers Propco LLC · $37.4M · 1 parcel County deed records · Sept. 2022
- May 2024 Quantum Maryland LLC to Rowan Frederick LLC · $158.5M · 1 parcel County deed records · May 2024
- Feb. 2025 Quantum Maryland LLC to Rowan Frederick II LLC · $180.8M · 2 parcels County deed records · Feb. 2025
- Aug. 2025 Quantum Maryland LLC to Rowan Frederick III LLC · $99.4M · 1 parcel County deed records · Aug. 2025
+1 more
- Dec. 2025 Quantum Maryland LLC to Rowan Terra LLC · $320.3M County deed records · Dec. 2025
What happened, and what is due
- Jan. 4, 2021Paper trail Quantum Maryland LLC registered in Delaware
- June 16, 2021Site Quantum Maryland buys 2,125 acres of the former Eastalco aluminum site for about $100M Local government · June 2021
- Dec. 15, 2021Permits The Planning Commission approves the first preliminary plan and the 18.3M sq ft capacity agreement Local government · Dec. 2021
- May 22, 2023Paper trail Rowan Frederick LLC registered in Delaware
- Oct. 25, 2023Power Aligned drops the project after state regulators limit its generators; it returns in 2024 Utility regulator · Oct. 2023
- Jan. 30, 2024Paper trail Rowan Frederick II LLC registered in Delaware
- Feb. 3, 2025Construction Aligned announces groundbreaking on its first building News report · Feb. 2025
- Feb. 2025Money Rowan closes $1.24B of construction financing for its second phase (press) News report · Feb. 2025
- May 2025Permits Planning Commission approves Rowan's second and third buildings and three more Aligned buildings (press) News report · May 2025
- Dec. 2025Construction Rowan's first building is turned over to Amazon after base construction finishes (press) News report · Dec. 2025
- Dec. 23, 2025Money Quantum Maryland sells land to Rowan Terra LLC in a $320.3M deed (county deed records) County deed records · Dec. 2025
- Jan. 20, 2026Permits County Council enacts the data center overlay zone covering 2,614.9 acres Local government · Jan. 2026
- March 25, 2026Permits State approves Amazon's air permit for 99 backup generators State agency · March 2026
- June 2026Legal Maryland's highest court blocks a voter referendum on the overlay zone News report · June 2026
- Sept. 14, 2026Permits County Executive rejects the owner's development agreement and extends the application pause to Jul. 1, 2027 Local government · Sept. 2026
- Oct. 2026Legal Quantum Maryland sues the County Executive, the county and the Planning Commission over the pause (press) News report · Oct. 2026
- July 1, 2027Permits Pause on new data center applications is set to end Local government · Sept. 2026
Building activity by quarter
Since Oct. 2015: 50 building permits (19 issued or finished, 19 pending or open, 12 withdrawn or expired); the largest lists a $400M job value; 11 FAA filings (Jan. 2023 to May 2026): tallest permanent building 87 ft (filed Jan. 2023) and tallest crane 350 ft (Dec. 2025); 8 OSHA inspections; and 13 satellite captures. Job values are not added up: trade permits often repeat the whole project's value. The chart starts in the first quarter of 2021; 1 earlier record is not drawn.
Specs
Owners, partners and builders
- Quantum Maryland LLC: landowner of record
- TPG Real Estate Partners: sponsor, took full control in Dec. 2024 (press)
- Catellus Maryland: TPG's developer-manager
- Quantum Loophole: original developer, removed by TPG in 2024 (press)
- Rowan Digital Infrastructure: developer of three planned buildings
- Aligned Data Centers: builder of IAD-04
- Amazon Data Services: air-permit holder, took over Rowan's first building (press)
- SMBC and MUFG: led Rowan's construction financing (press)
- Mizuho and TD Securities: lead arrangers on the second phase (press)
- Potomac Edison (FirstEnergy): utility, planned substation
- Frederick County Council and Planning Commission
- County Executive Jessica Fitzwater
- Maryland Department of the Environment and Public Service Commission
- Gov. Wes Moore: statewide review order
- Sugarloaf Alliance and the Frederick County Data Center Referendum Committee
- Envision Frederick County, CCAN Action Fund, Mobilize Frederick
- Hitt Contracting, Inc.: contractor on site per OSHA inspection 348288671; 1 OSHA inspection
- Phoenix Steel Erectors, Inc.: contractor on site per OSHA inspection 348288747; 1 OSHA inspection
- L. R. Willson & Sons, Inc.: contractor on site per OSHA inspection 348290065
- Metromont LLC: contractor on site per OSHA inspection 348524240
- Brothers RC Contractors LLC: contractor on site per OSHA inspection 348805532
- DMV Building Services LLC: contractor on site per OSHA inspection 347262107
- and 7 more contractors in the permit and inspection records
Open questions
- Utility service agreement and delivered megawatts for the full park.
- Whether Amazon's second air permit is granted.
- Outcome of the owner's suit over the pause.
- Which buildings are in service today.
334 records from 51 documents
Drawn from news reports, state agency records, local government records, business registries, public and commercial datasets, court filings, securities filings, satellite captures, company statements and utility regulator dockets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (31)
- ECHO Air 10 mi radius returned 363 facilities with no Quantum Frederick / Aligned record: the MDE air application filed July 1, 2024 (168 diesel gens @ 3000 kW + 4 @ 1000 kW) is [S]-level gold that ECHO Air does not carry.“363 facilities in radius”State agency · Oct. 2026 · grade A
- 2026-AEA-6439-OE: 251 ft Catenary Wire 'SPAN FROM STR 100 SPLICE TO STR 101' at 39.29357664,-77.51214764; grid infrastructure near the campus, not a data-center crane; status Determined - No Hazard“SPAN FROM STR 100 SPLICE TO STR 101 | 251 ft AGL | submitted 06/02/2026”FAA · June 2026 · grade A
- On-site generation: 258“Amazon is installing ninety-nine emergency generators with a total maximum electrical output of 258 megawatts”State agency · March 2026 · grade A
- On-site generation: 508“Aligned is installing one-hundred and seventy-two emergency generators with a total maximum electrical output of 508 megawatts”State agency · March 2026 · grade A
- Address: 3250 Digital Drive, Frederick MD 21703 (Amazon BWI-150..153)“approving an air quality permit for Amazon Data Services, Inc., authorizing the installation of emergency backup generators for a new data center campus located at 3250 Digital Drive in Frederick”State agency · March 2026 · grade A
- Backup generators: 99 units“the 99 diesel-fired emergency generators are strictly prohibited from operating as the primary power source for the data center or participating in demand response programs”State agency · March 2026 · grade A
- 2026-AEA-59-OE: 197 ft Transmission Line Tower 'Lovettsville-Doubs STR 248' at 39.29956667,-77.538875; grid infrastructure near the campus, not a data-center crane; status Determined - No Hazard“Lovettsville-Doubs STR 248 | 197 ft AGL | submitted 01/22/2026”FAA · Jan. 2026 · grade A
- 2026-AEA-58-OE: 191 ft Transmission Line Tower 'Lovettsville-Doubs STR 249' at 39.2996,-77.53596944; grid infrastructure near the campus, not a data-center crane; status Determined - No Hazard“Lovettsville-Doubs STR 249 | 191 ft AGL | submitted 01/22/2026”FAA · Jan. 2026 · grade A
- Acres: 151 acres“Critical Digital Infrastructure Electric Substation located on a 7.7-acre project area, within a 151.17-acre parcel”Local government · Aug. 2024 · grade A
- Backup generators: 172 units“168 emergency generators, each equipped with a diesel fired engine rated at 3,000-kilowatts, and each controlled by a Selective Catalytic Reduction (SCR) system; and four (4) emergency generators rated at 1,000-kilowatts”State agency · July 2024 · grade A
- PJM 2023 Load Forecast APS-zone figure as explained by the Maryland Office of People's Counsel: an additional 799 MW of new load in the APS zone in 2028, which OPC says can reasonably be inferred to sit at Quantum Loopho“According to PJM's 2023 Load Forecast, in 2028, there will be an additional 799 MW of new electricity load in the APS zone”State agency · Oct. 2026 · grade B
- Nearest power line: 230 kV at 0.65 kmMeasured on OpenStreetMap map data.
- Nearest 500 kV line: 'Brighton Sub PEPCO to Doubs Sub DOMINION 500KV' at 4.71 kmMeasured on OpenStreetMap map data.
- Nearest substation: unnamed at 2.47 kmMeasured on OpenStreetMap map data.
- Nearest gas pipeline: Dominion Transmission 'Leidy South Gas Pipeline' at 11.83 km; none within 5 kmMeasured on OpenStreetMap map data.
- Owner built the QLoop campus-wide fiber network and specialized water/sewer infrastructure for data-center cooling and spent roughly $200M to secure power supply; ~3,754,247 sq ft of the 18.3M sq ft program under constru“Owner constructed the unique, campus-wide fiber network... and spent roughly $200 million to secure the necessary power supply”Local government · Sept. 2026 · grade B
- Utility service: 240 MW“The 230-kilovolt substation will be located near the center of the Quantum Frederick campus and is expected to support the 240 megawatts of power anticipated for its first phase.”Company · Oct. 2022 · grade B
- Utility service: 1,000 MW“The substation yard design will accommodate up to 1,000 megawatts in future phases.”Company · Oct. 2022 · grade B
- Interconnection status: Interconnection study / build-out stage (PJM / Potomac Edison, FirstEnergy): utility-planned 230 kV on-site substation for the first phase, subject to PJM stakeholder review and Maryland PSC / Fre“The substation is subject to review by regional transmission organization PJM and its stakeholders”Company · Oct. 2022 · grade B
- large load interconnection request: planning announced; substation and line work subject to PJM stakeholder review and Maryland PSC / Frederick County approval“The 230-kilovolt substation will be located near the center of the Quantum Frederick campus and is expected to support the 240 megawatts of power anticipated for its first phase.”Company · Oct. 2022 · grade B
- Substation kV: 230“The 230-kilovolt substation will be located near the center of the Quantum Frederick campus and is expected to support the 240 megawatts of power anticipated for its first phase. The substation yard design will accommodate up to 1,000 megawatts in”Company · Oct. 2022 · grade B
- Utility service: 240 MW“expected to support the 240 megawatts of power anticipated for its first phase. The substation yard design will accommodate up to 1,000 megawatts in future phases.”Company · Oct. 2022 · grade B
- Opposition: Frederick County Data Center Referendum Committee (chair Elizabeth Bauer) + Sugarloaf Alliance, Envision Frederick County, CCAN Action Fund, Mobilize Frederick, Farm Bureau, Landmarks Foundation; petition 24,“The petitioners submitted 24,053 signatures. The referendum coalition later reported that 21,029 were validated, and the County Election Director found the petition sufficient.”News report · April 2026 · grade C
- Backup generators: 92 units“The filing requests permission to deploy 92 2.75MW generators, six 750kW generators, and one 250kW generator, all supplied by Caterpillar.”News report · March 2026 · grade C
- PJM's supplemental list carries only Allegheny Power (FirstEnergy) equipment work at this campus's 500 kV point-of-interconnection area: S3540.1 replaces the line trap, substation conductor and relaying at Doubs ($6.30M,“At Doubs, replace line trap, substation conductor and relaying.”Dataset · Dec. 2025 · grade C
- Stated campus size: 2,000 MW“The company is developing a 2,100-acre, 2GW data center park for other developers to build data centers in.”News report · Feb. 2025 · grade C
- On-site generation: 508 MW“The Maryland Department of the Environment also granted a construction permit to Aligned on Jan. 30, allowing the company to build 172 emergency diesel generators... 168 three-megawatt generators and four one-megawatt generators, a combined total power capacity of 508 megawatts.”News report · Jan. 2025 · grade C
- Buildings: 4 buildings“Known as Bauxite I, the 300MW site will total four single-story buildings across 777,150 sq ft (72,200 sqm).”News report · Jan. 2025 · grade C
- Square feet: 777150 sq ft“the 300MW site will total four single-story buildings across 777,150 sq ft”News report · Jan. 2025 · grade C
- Stated campus size: 300 MW“Known as Bauxite I, the 300MW site”News report · Jan. 2025 · grade C
- Backup generators: 42 units“In May 2023, Aligned received conditional site-plan approval from the Frederick County Planning Commission to build a data center with 42 diesel backup generators.”News report · May 2023 · grade C
Money and contracts (31)
- Md parcel transfer: $100,000,000 consideration, transfer date June 29, 2021“CONSIDR1 $100,000,000 and TRADATE 20210629 match the June 2021 Alcoa sale of Eastalco to the Quantum Loophole/TPG JV”State agency · Oct. 2026 · grade A
- Development Rights and Responsibilities Agreement (PROPOSED - REJECTED): status: rejected County Executive rejected Catellus's DRRA application Sep 14, 2026; benefits package is NOT secured funding or an enforceable comm“On September 14, County Executive Fitzwater rejected the application for a Development Rights and Responsibilities Agreement sought by Catellus for the Frederick Digital Campus in Adamstown.”Local government · Sept. 2026 · grade A
- County Executive rejected Catellus's DRRA application for the Frederick Digital Campus and signed an executive order extending the application pause to Jul 1, 2027; the ~$110M community-benefits package died with the app“On September 14, County Executive Fitzwater rejected the application for a Development Rights and Responsibilities Agreement sought by Catellus for the Frederick Digital Campus in Adamstown.”Local government · Sept. 2026 · grade A
- Development Rights and Responsibilities Agreement (PROPOSED - REJECTED): petition filed over $100,000,000 monetary benefits per draft text; $110M package as publicly announced USD“On September 1, 2026, Owner petitioned the County Executive to enter into this Agreement... which included a package of Enhanced Public Benefits... totaling over One Hundred Million Dollars ($100,000,000) of direct monetary investments”Local government · Sept. 2026 · grade A
- Development Rights and Responsibilities Agreement (PROPOSED - REJECTED): density reduction 18,300,000 -> 15,000,000 sq ft“Owner has agreed... i) reduce the density of the Frederick Digital Campus from 18,300,000 to 15,000,000 square feet”Local government · Sept. 2026 · grade A
- Development Rights and Responsibilities Agreement (PROPOSED - REJECTED): community benefit line items Carroll Manor Elementary renovations $30M; Adamstown Regional Park $30M (37.7 ac); Workforce Development Training Cent“Fund the design and construction for renovations to Carroll Manor Elementary School ($30,000,000); Fund the design and construction of improvements to... establish an Adamstown Regional Park ($30,000,000)”Local government · Sept. 2026 · grade A
- Development Rights and Responsibilities Agreement (PROPOSED - REJECTED): land dedication / conservation Up to 228 acres dedicated for Community Benefit Areas; ~433 acres Tuscarora Stream Valley conservation easement (per“transfer, dedicate, and/or convey up to 228 acres of land... subject approximately 433 acres of the Property... to conservation easement(s) that establish a permanent nature reserve”Local government · Sept. 2026 · grade A
- Development Rights and Responsibilities Agreement (PROPOSED - REJECTED): zoning freeze term 8 years, extendable up to 5 years (County Code 1-25-12) years“legally establish the terms and conditions upon which the Frederick Digital Campus will develop over the next eight (8) years, as the same may be extended for up to five (5) years pursuant to 1-25-12 of the County Code”Local government · Sept. 2026 · grade A
- Tenant operator: Amazon Data Services, Inc. (permitted operator of the 3250 Digital Drive facility, buildings BWI150-BWI153)“FINAL DETERMINATION CONCERNING A PERMIT-TO-CONSTRUCT APPLICATION SUBMITTED BY AMAZON DATA SERVICES, INC. FOR THEIR PROPOSED FREDERICK, MARYLAND DATA CENTER CAMPUS”State agency · March 2026 · grade A
- Aligned rejected PSC provisional order (70 MW cap) and exited the project; returned May 2024 after the Critical Infrastructure Streamlining Act (SB474) reclassified backup generation; MDE application Jul 1, 2024; groundb“Aligned does not accept the provisional exemption and, instead, will not proceed with its planned mission critical data center project.”Utility regulator · Oct. 2023 · grade A
- Square feet: 450000 sq ft“The Applicant is requesting Site Plan approval to construct a 450,000 SF gross floor area Critical Digital Infrastructure Facility on a 74.89-acre property”Local government · May 2023 · grade A
- APFO Letter of Understanding: scope of approved development 18,300,000 sq ft data-center development; water ~5.3 MGD; sewer ~2.8 MGD; 3,317 vehicle trips/day sq ft / MGD“APFO LOU means the Adequate Public Facilities Ordinance Letter of Understanding A266569, which was previously approved on December 15, 2021... which permit the construction of 18,300,000 square feet of data-center development, utilizing water capacity of approximately 5.3 million gallons per”Local government · Dec. 2021 · grade A
- Quantum Loophole, Inc. (CIK 1811035) is an EDGAR filer: Form D filed July 9, 2021 reports $25,291,492 sold (first sale June 23, 2021); Form D filed May 12, 2020 reports $3,050,000 sold. Sponsor-entity Reg D sales, not campus-sp“entityName Quantum Loophole, Inc.; totalAmountSold 25291492; dateOfFirstSale 2021-06-23”SEC filing · July 2021 · grade A
- Land control date: June 16, 2021 (Quantum Maryland LLC purchased 2,125 acres from Eastalco Aluminum Company)“On June 16, 2021, Owner purchased the 2,125 acres of land shown and described on Exhibit A to this Agreement from Eastalco Aluminum Company”Local government · June 2021 · grade A
- Quantum Maryland LLC purchased 2,125 acres (Eastalco Property) from Eastalco Aluminum Company; Alcoa announced ~$100M sale to Quantum Loophole-TPG JV (Jun 23-28, 2021)“On June 16, 2021, Owner purchased the 2,125 acres of land... from Eastalco Aluminum Company”Local government · June 2021 · grade A
- Land purchase (recorded deed): contract value 320321600 USD“Recorded: Dec. 23, 2025 · Price: $320,321,600 · Grantor: QUANTUM MARYLAND LLC · Grantee: ROWAN TERRA LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Dec. 2025 · grade B
- Land purchase (recorded deed): contract value 99400750 USD“Recorded: Aug. 6, 2025 · Price: $99,400,750 · Grantor: QUANTUM MARYLAND LLC · Grantee: ROWAN FREDERICK III LLC · Parcel number: 01-000152 · Address: 5601 MANOR WOODS RD · City: FREDERICK”County deed records · Aug. 2025 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: June 16, 2025 · Grantor: QUANTUM MARYLAND LLC · Grantee: FREDERICK COUNTY · Parcel number: 01-605688 · Address: 5690 HAPPY LANDING RD · City: FREDERICK”County deed records · June 2025 · grade B
- Land purchase (recorded deed): contract value 180765875 USD“Recorded: Feb. 19, 2025 · Price: $180,765,875 · Mortgage1amount: 123733912 · Grantor: QUANTUM MARYLAND LLC · Grantee: ROWAN FREDERICK II LLC · Parcel number: 01-607700 · Address: 3300 RADIANT WAY · City: FREDERICK”County deed records · Feb. 2025 · grade B
- Land purchase (recorded deed): contract value 158476391 USD“Recorded: May 14, 2024 · Price: $158,476,391 · Grantor: QUANTUM MARYLAND LLC · Grantee: ROWAN FREDERICK LLC · Parcel number: 01-607167 · Address: 3250 DIGITAL DR # A · City: FREDERICK”County deed records · May 2024 · grade B
- Land purchase (recorded deed): contract value 37445000 USD“Recorded: Sept. 29, 2022 · Price: $37,445,000 · Grantor: QUANTUM MARYLAND LLC · Grantee: ALIGNED DATA CENTERS PROPCO LLC · Parcel number: 01-005383 · Address: 5631 MANOR WOODS RD · City: FREDERICK”County deed records · Sept. 2022 · grade B
- Land purchase (recorded deed): contract value 100000000 USD“Recorded: June 29, 2021 · Price: $100,000,000 · Grantor: EASTALCO ALUMINUM COMPANY · Grantee: QUANTUM MARYLAND LLC · Parcel number: 01-602350 · Address: 5601 MANOR WOODS RD · City: FREDERICK”County deed records · June 2021 · grade B
- Tenants: Rowan Digital Infrastructure; Aligned Data Centers; Amazon Data Services / AWS (BWI-150, BWI-151, BWI-152, BWI-153)“According to the permit, Amazon is developing four buildings - BWI-150, BWI-151, BWI-152, and BWI-153 - at 3250 Digital Drive in Frederick.”News report · March 2026 · grade C
- Tenant status: Amazon took over Rowan's Bauxite I after base construction completed late 2025; Rowan remains property steward; Amazon AZ expected to open 2026“Bauxite I was developed by Rowan Digital Infrastructure and was turned over to Amazon after base construction completed late last year.”News report · March 2026 · grade C
- Amazon took over Bauxite I from Rowan after base construction completed late 2025; Rowan remains steward of the property and core electrical infrastructure with an on-site team“Bauxite I was developed by Rowan Digital Infrastructure and was turned over to Amazon after base construction completed late last year. Rowan continues to serve as a steward of the property and its core electrical infrastructure”News report · Dec. 2025 · grade C
- Square feet: 1149000 sq ft“Buildings 2, 3 and 4 total 1.15-million square feet. The commission approved the submitted plan unanimously”News report · May 2025 · grade C
- APFO water allocation: Phase 1 cooling water cap 1.3 MGD combined Phase 1 cooling demand“According to the Adequate Public Facilities Ordinance (APFO) agreement signed between Quantum Frederick and the county, the first phase of development on the site is limited to projects whose total combined cooling water demand does not exceed 1.3 million gallons”News report · May 2025 · grade C
- Square feet: 822620 sq ft“Bauxite II will span 822,620 sq ft (76,400 sqm) on an 111.5-acre site, while Bauxite III will span 591,913 sq ft (54,990 sqm) on a 55-acre site”News report · Feb. 2025 · grade C
- Square feet: 591913 sq ft“Bauxite III will span 591,913 sq ft (54,990 sqm) on a 55-acre site”News report · Feb. 2025 · grade C
- Rowan closed $1.24B construction financing for Bauxite II (phase 2): SMBC + MUFG co-structuring agents; SMBC, MUFG, Mizuho, TD Securities coordinating lead arrangers / joint bookrunners; 14 lenders; secondary syndication“The financing was led by Sumitomo Mitsui Banking Corporation (SMBC) and MUFG Bank, Ltd. (MUFG) as co-structuring agents... Fourteen lenders took part in the financing”News report · Feb. 2025 · grade C
- Rowan closed $975M construction financing for Bauxite I (MUFG, SMBC, Mizuho among lenders)“The company secured $975 million in financing to fund Bauxite I's build-out last month. MUFG, SMBC, and Mizuho were also involved in that financing.”News report · Jan. 2025 · grade C
Permits and government (104)
- L. R. WILLSON & SONS, INC. - OSHA Planned inspection at 3363 BALLENGER CREEK PIKE, FREDERICK, MD 21703, opened June 4, 2025 (activity 348290065); NAICS 238120. OSHA issued 5 citation item(s) (O, S) under this inspection, c“R; WILLSON & SONS, INC.”State agency · Oct. 2026 · grade A
- Md parcel acres: 324.01 deeded acres (POLYACRES 796.29)“ACRES 324.01; polygon acres 796.29; zoning GI (General Industrial); owner name not carried, owner mailing address 20251 Century Blvd Ste 170, Germantown, MD 20874”State agency · Oct. 2026 · grade A
- QUANTUM FREDERICK, 5601 Manor Woods Road, Frederick MD 21703; MD construction st: permit record in radius search“QUANTUM FREDERICK; 5601 MANOR WOODS ROAD; FREDERICK MD”State agency · Oct. 2026 · grade A
- Moratoria: Executive pause on new data center applications ordered Jul 1, 2026 (through Dec 31, 2026); extended Sep 14, 2026 to July 1, 2027; does not stop projects under construction or pre-Jun 17, 2025 approvals“On July 1, 2026, County Executive Jessica Fitzwater ordered a pause on new data center development until December 31, 2026... She also signed an Executive Order extending the pause on data center applications until July 1, 2027.”Local government · Sept. 2026 · grade A
- County Executive Fitzwater ordered a pause on new data center applications (through Dec 31, 2026), the day after the Supreme Court referendum ruling; pause requires PSC large-load registry proof in development review; do“On July 1, 2026, County Executive Jessica Fitzwater ordered a pause on new data center development until December 31, 2026”Local government · July 2026 · grade A
- MDE final determination approving the Amazon Data Services permit-to-construct: : final determination issued (permit-to-construct approved)“The Department has made a final determination to issue the permit-to-construct, effective March 25, 2026”State agency · March 2026 · grade A
- Amazon Data Services application for an additional data center facility in Frede: second permit-to-construct application announced (additional facility, pending)“Amazon has submitted an application for an additional data center facility in Frederick, for which the department will schedule a public meeting”State agency · March 2026 · grade A
- Air quality permit to construct: Final determination - permit effective“The Department has made a final determination to issue the permit-to-construct, effective March 25, 2026.”State agency · March 2026 · grade A
- MDE ARA final determination effective March 25, 2026 approves Amazon Data Services permit-to-construct for a data center at 3250 Digital Drive (Quantum Frederick campus): 99 emergency generators, 258 MW total maximum output.“The Department has made a final determination to issue the permit-to-construct, effective March 25, 2026”State agency · March 2026 · grade A
- Ordinance 26-01-001 enacted: CDI Overlay Zone mapped at 2,614.9 acres north of Adamstown (Council had expanded the Planning Commission's ~1,600-acre recommendation in Dec 2025); removed 107.45 ac (Parcel 28-E) and added“On January 20, 2026, the County Council enacted Ordinance 26-01-001, a comprehensive rezoning ordinance which established and mapped the physical boundaries of the CDI Overlay Zone.”Local government · Jan. 2026 · grade A
- Maryland Dept. of the Environment (public meeting): Amazon Data Services air permit application (99 gensets, Bauxite I / 3250 Digital Drive)“Meeting Date: December 8, 2025... The public comment period on the application expired on December 19, 2025.”State agency · Dec. 2025 · grade A
- County Council enacted Bill 25-09: comprehensive CDI regulatory revision; new CDI uses after Nov 1, 2025 must be inside the new Critical Digital Infrastructure Overlay Zone“On September 2, 2025, the Frederick County Council enacted Bill 25-09, a comprehensive revision of the regulatory structure applicable to critical digital infrastructure”Local government · Sept. 2025 · grade A
- Site plan: Approved“A Site Plan for an electric substation was approved by the Planning Commission on March 12, 2025 (SP277075).”Local government · March 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Crane for Data Center.....continuation of previous FAA permit 2023-AEA-2959-OE”FAA · Jan. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Crane for Data Center.....continuation of previous FAA permit 2023-AEA-4316-OE”FAA · Jan. 2025 · grade A
- Amazon Data Services, Inc. application for a proposed data center facility at 32: permit-to-construct application received“received a permit-to-construct application from Amazon Data Services, Inc. on October 29, 2024 for their proposed data center facility”State agency · Oct. 2024 · grade A
- Site plan: Conditional approval“Site plan is valid for a period of three (3) years from the date of Planning Commission approval (August 14, 2027).”Local government · Aug. 2024 · grade A
- Frederick County Planning Commission: Bauxite Substation site plan (Quantum Frederick Section 2, Lot 400)“Staff recommends... The Applicant shall comply with all Staff and agency comments through the completion of the plan.”Local government · Aug. 2024 · grade A
- Air quality permit to construct (application): Application received“received a permit-to-construct application from Aligned Data Centers (MD), Propco, LLC on July 1, 2024 for their proposed IAD04 data center facility”State agency · July 2024 · grade A
- CPCN exemption: Applicant rejected provisional order / withdrew“Re: ML No. 302893 - Letter Rejecting Provisional Order... The Commission's October 10th Provisional Order did not present Aligned Data Centers with sufficient relief to permit the project to proceed.”Utility regulator · Oct. 2023 · grade A
- Site plan approval date: May 10, 2023“Planning Commission May 10, 2023 - Aligned Data Centers, Quantum Frederick Lot 106, Site Plan”Local government · May 2023 · grade A
- Conditions of approval: Conditional approval; site plan valid 3 years (until May 10, 2026); lighting modification to max 1.0 foot-candle at Quantum Place South entrance; parking modification 78 spaces vs 30 required; Fin“If the Planning Commission conditionally approves the Site Plan, it is valid for three (3) years (until May 10, 2026).”Local government · May 2023 · grade A
- Site plan: Conditional approval“If the Planning Commission conditionally approves the Site Plan, it is valid for three (3) years (until May 10, 2026).”Local government · May 2023 · grade A
- Frederick County Planning Commission: Aligned Data Centers - Quantum Frederick Lot 106 site plan (SP22-04 / SP275110): 450,000 SF CDIF on 74.89 acres“If the Planning Commission conditionally approves the Site Plan, it is valid for three (3) years (until May 10, 2026).”Local government · May 2023 · grade A
- FAA OE/AAA archive case: Determined - No Hazard“ASN 2023-AEA-4316-OE: IAD04, Crane, 240 ft AGL, 574 ft AMSL, 39.33277778,-77.47777778, Determined - No Hazard, submitted 2023-04-03”FAA · April 2023 · grade A
- FAA OE/AAA archive case: Determined - No Hazard“ASN 2023-AEA-2959-OE: IAD04, Crane, 240 ft AGL, 570 ft AMSL, 39.33333334,-77.4725, Determined - No Hazard, submitted 2023-03-02”FAA · March 2023 · grade A
- FAA OE/AAA archive case: Determined - No Hazard“ASN 2023-AEA-844-OE: IAD04, Building, 87 ft AGL, 417 ft AMSL, 39.33166667,-77.4725, Determined - No Hazard, submitted 2023-01-16”FAA · Jan. 2023 · grade A
- Water use stated: Cooling water from wastewater effluent supply system (Ballenger-McKinney WWTP effluent) or added New Design WTF capacity; potable from New Design Road WTP“obtain additional water capacity of remaining (Max Day) from the New Design Water Treatment Facility (NDWTF), or study, design, permit, and construct the wastewater effluent supply system for use as cooling water... effluent from the Ballenger-McKinney WWTP to the Potomac”Local government · Dec. 2021 · grade A
- Planning Commission approved Quantum Frederick Preliminary Plan Section 1 Phases 1-3 (PP266504) and APFO LOU A266569“On December 15, 2021, the Planning Commission approved the Preliminary Plan and APFO for Quantum Frederick, Section 1, Phases 1, 2 & 3 (PP266504).”Local government · Dec. 2021 · grade A
- Stormwater construction general permit coverage: Listed (carried from T4 verification)“MDG679785 'QUANTUM FREDERICK', 5601 Manor Woods Road [V]”Dataset · Oct. 2026 · grade B
- building permit: Buildingapplication / Fire: expired“Permit number: 494586 · Type: Buildingapplication · Status: expired · Job value: $7,254,926 · Effective date: Aug. 15, 2026 · Business: Bill Charles Saunders · Address: 5601 MANOR WOODS RD · Description: Bfpe will provide core & shell fire protection as well as an additional 6 phase tenant build-out plan which i”
- building permit: Buildingapplication / Trailer: expired“Permit number: 490539 · Type: Buildingapplication · Status: expired · Job value: $600,000 · Effective date: Aug. 13, 2026 · Address: 5601 MANOR WOODS RD · Description: Turner construction trailer complex for the aligned data center project will consist of double wide trailer triple wide trailer”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510615 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510617 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510619 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510620 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510622 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510623 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510624 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510625 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510626 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510627 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510628 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 510629 · Type: Buildingapplication · Status: filed · Job value: $8,416,667 · Effective date: July 23, 2026 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Data center administrative and data hall building out”
- building permit: Buildingapplication / Grading: expired“Permit number: 494532 · Type: Buildingapplication · Status: expired · Job value: $87,846 · Effective date: July 21, 2026 · Address: 5601 MANOR WOODS RD · Description: <div>pw277278 s1179</div>grading permit associated with proposed improvements (power feed to lot 106).<div>no swm requirement.</d”
- building permit: Buildingapplication / Fire: issued“Permit number: 509344 · Type: Buildingapplication · Status: issued · Job value: $380,000 · Effective date: July 7, 2026 · Business: Ryan Fireprotection · Address: 5601 MANOR WOODS RD · Description: Bauxite III building d - core - fire sprinkler fire suppression system per nfpa 13 with fire pump. For building d”
- building permit: Buildingapplication / Trailer: expired“Permit number: 493410 · Type: Buildingapplication · Status: expired · Job value: $257,989 · Effective date: June 4, 2026 · Business: Drew Nicholas · Address: 5601 MANOR WOODS RD · Description: This submission is for a 46x60 temporary construction trailer on the quantum loop construction site.<div>”
- building permit: Buildingapplication / Fire: filed“Permit number: 507930 · Type: Buildingapplication · Status: filed · Job value: $5,700,000 · Effective date: May 27, 2026 · Business: Ryan Fireprotection · Address: 5601 MANOR WOODS RD · Description: Fire sprinkler fire suppression system per nfpa 13 with fire pump. New construction of a campus of data centers f”Local building-permit records · May 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-6392-OE: IAD07 and IAD08, Crane, 240 ft AGL, 582 ft AMSL, 39.33547,-77.47447, Determined - No Hazard, submitted 2026-05-20”FAA · May 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-6393-OE: IAD07 and IAD08, Crane, 240 ft AGL, 569 ft AMSL, 39.33600,-77.47221, Determined - No Hazard, submitted 2026-05-20”FAA · May 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-6390-OE: IAD07 and IAD08 Crane, Crane, 240 ft AGL, 574 ft AMSL, 39.33784,-77.47307, Determined - No Hazard, submitted 2026-05-20”FAA · May 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AEA-6391-OE: IAD07 and IAD08, Crane, 240 ft AGL, 588 ft AMSL, 39.33747,-77.47570, Determined - No Hazard, submitted 2026-05-20”FAA · May 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2025-AEA-10992-OE: IAD06 Mobile Crane, Mobile Crane, 240 ft AGL, 590 ft AMSL, 39.33639,-77.47417, Determined - No Hazard, submitted 2026-03-12”FAA · March 2026 · grade B
- building permit: Buildingapplication / Trailer: expired“Permit number: 491008 · Type: Buildingapplication · Status: expired · Job value: $150,000 · Effective date: March 10, 2026 · Address: 5601 MANOR WOODS RD · Description: 24 x 60 temporary construction trailer for office use. Bs site development trailer.<div>”
- building permit: Buildingapplication / Grading: issued“Permit number: 503665 · Type: Buildingapplication · Status: issued · Job value: $361,554 · Effective date: March 9, 2026 · Address: 5601 MANOR WOODS RD · Description: <div>permit to cover all phases of project (phases 1-5):</div><div>1 - pw277847 (approved)</div><div>2 - pw277848 (approved)</div”
- building permit: Buildingapplication / Tanks: expired“Permit number: 490783 · Type: Buildingapplication · Status: expired · Job value: $260,000 · Effective date: Feb. 21, 2026 · Address: 5601 MANOR WOODS RD · Description: Install one (1) above ground temporary tank to store groundwater”
- building permit: Buildingapplication / Swm: expired“Permit number: 482713 · Type: Buildingapplication · Status: expired · Job value: $200,680 · Effective date: Jan. 14, 2026 · Address: 5601 MANOR WOODS RD · Description: Pw275268 sp2204<div>mj# 482484</div><div>(1) submerged gravel wetland and grass swale”
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2025-AEA-13493-OE: CSC 5631 Manor Woods Rd, Frederick, MD, Stationary/Fixed Crane, 350 ft AGL, 682 ft AMSL, 39.33453,-77.47135, Determined - No Hazard, submitted 2025-12-08”FAA · Dec. 2025 · grade B
- FAA OE/AAA crane filings evidence vertical construction at the campus (former Eastalco site, Manor Woods Rd, Frederick MD): a 350-ft fixed crane inside the outline submitted Dec. 8, 2025, and 240-ft cranes for buildings IA“ASN 2025-AEA-13493-OE: CSC 5631 Manor Woods Rd, Frederick, MD, Stationary/Fixed Crane, 350 ft AGL, 682 ft AMSL, 39.33453,-77.47135, Determined - No Hazard, submitted 2025-12-08”FAA · Dec. 2025 · grade B
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 500278 · Type: Buildingapplication · Status: filed · Job value: $100,000 · Effective date: Oct. 16, 2025 · Address: 5601 MANOR WOODS RD · Description: Temporary (64 x 131') break tent with electric for craft and assembly area for morning stretch and flex. This deck will be inst”
- building permit: Buildingapplication / Trailer: expired“Permit number: 485609 · Type: Buildingapplication · Status: expired · Job value: $150,000 · Effective date: Sept. 13, 2025 · Business: Jennifer Bohager · Address: 5601 MANOR WOODS RD · Description: 24 x 60 temporary construction trailer ( subcontractor )”
- building permit: Buildingapplication / Elecperm: filed“Permit number: 497292 · Type: Buildingapplication · Status: filed · Job value: $88,500,000 · Effective date: July 28, 2025 · Business: JE Richards INC · Address: 5601 MANOR WOODS RD · Description: Aligned building 1 electrical permit - core work only - tenant fit out work will need to be on separate permit.<”
- building permit: Buildingapplication / Froperm: issued“Permit number: 484668 · Type: Buildingapplication · Status: issued · Job value: $100,378 · Effective date: June 23, 2025 · Address: 5601 MANOR WOODS RD · Description: Fence & signs plantings eradication<div>”
- building permit: Buildingapplication / Pi: issued“Permit number: 487071 · Type: Buildingapplication · Status: issued · Job value: $824,102 · Effective date: June 5, 2025 · Address: 5601 MANOR WOODS RD · Description: <div>pw275583 s1179</div>this involves the construction of a traffic circle on manor woods road that connects proposed new quantum pla”
- building permit: Buildingapplication / Swm: issued“Permit number: 489941 · Type: Buildingapplication · Status: issued · Job value: $348,702 · Effective date: June 5, 2025 · Business: Aligned Data Center; Davis Adl · Address: 5601 MANOR WOODS RD · Description: <div>pw275271 s1179</div><div>(1) 378 pond </div>combined swm development and improvement plan for a 45”
- building permit: Buildingapplication / Pi: issued“Permit number: 489942 · Type: Buildingapplication · Status: issued · Job value: $25,358 · Effective date: June 5, 2025 · Address: 5601 MANOR WOODS RD · Description: <div>pw275271 s1179</div><div>combined swm development and improvement plan for a 450 000 sq-ft critical digital infrastructure buildin”
- building permit: Buildingapplication / Trailer: filed“Permit number: 493624 · Type: Buildingapplication · Status: filed · Job value: $134,000 · Effective date: April 24, 2025 · Business: Suffolk Construction · Address: 5601 MANOR WOODS RD · Description: Trailer permits for suffolk construction - (1) 50 x 10 temporary construction trailer”
- building permit: Buildingapplication / Trailer: canceled“Permit number: 492730 · Type: Buildingapplication · Status: canceled · Job value: $109,646 · Effective date: April 18, 2025 · Business: Henkels & MC COY · Address: 5601 MANOR WOODS RD · Description: Up to (3) 10 x 40 temporary office trailers and up to (4) 8 x 40 material containers 10 x 40 temporary office t”
- building permit: Buildingapplication / Capacity: filed“Permit number: 493236 · Type: Buildingapplication · Status: filed · Effective date: April 15, 2025 · Address: 5601 MANOR WOODS RD · Description: Proposed 2-story data center of approximately 447637 sf (218 000 sf footprint) with construction as precast concrete panel walls and f”
- building permit: Buildingapplication / Nonresbldg: filed“Permit number: 492533 · Type: Buildingapplication · Status: filed · Job value: $400,000,000 · Effective date: April 3, 2025 · Business: HKS INC · Address: 5601 MANOR WOODS RD · Description: Proposed 2-story data center of approximately 447637 sf (218 000 sf footprint) with construction as precast concrete”
- building permit: Buildingapplication / Froperm: issued“Permit number: 479836 · Type: Buildingapplication · Status: issued · Job value: $200,120 · Effective date: March 13, 2025 · Address: 5601 MANOR WOODS RD · Description: Eradication fence & signs plantings and speciman trees<div>quantum frederick- section 2 phase 2</div><div>f276429 s1179”
- building permit: Buildingapplication / Nonresbldg: issued“Permit number: 490717 · Type: Buildingapplication · Status: issued · Job value: $1,020,500 · Effective date: March 13, 2025 · Address: 5601 MANOR WOODS RD · Description: New 1232 sf pre-fabricated metal building containing electrical control equipment for the new sage substation. The building w”
- building permit: Buildingapplication / Trailer: issued“Permit number: 491198 · Type: Buildingapplication · Status: issued · Job value: $174,000 · Effective date: March 10, 2025 · Address: 5601 MANOR WOODS RD · Description: Temporary 60 x 46 8 construction trailer <div>”
- building permit: Buildingapplication / Nonresbldg: canceled“Permit number: 491056 · Type: Buildingapplication · Status: canceled · Job value: $175,000 · Effective date: Feb. 21, 2025 · Address: 5601 MANOR WOODS RD · Description: Construction trailer 4 wide”
- building permit: Buildingapplication / Elecperm: issued“Permit number: 490568 · Type: Buildingapplication · Status: issued · Effective date: Feb. 14, 2025 · Business: David Huska · Address: 5601 MANOR WOODS RD · Description: Underground utility duct banks and conduit for electrical & telecom services.<div>bld permit # 489730”
- building permit: Buildingapplication / Nonresbldg: issued“Permit number: 489730 · Type: Buildingapplication · Status: issued · Job value: $11,800,000 · Effective date: Feb. 13, 2025 · Address: 5601 MANOR WOODS RD · Description: Foundation-only package of a new 2-story data center. Future proposed building is approximately 447 000 sf (218 000 sf footp”
- building permit: Buildingapplication / Capacity: canceled“Permit number: 490162 · Type: Buildingapplication · Status: canceled · Effective date: Feb. 13, 2025 · Address: 5601 MANOR WOODS RD · Description: Foundation-only package of a new 2-story data center. Proposed building is approximately 447, 000 sf (218, 000 sf footprint) with c”
- building permit: Buildingapplication / Nonresbldg: issued“Permit number: 489564 · Type: Buildingapplication · Status: issued · Job value: $1,773,000 · Effective date: Feb. 7, 2025 · Address: 5601 MANOR WOODS RD · Description: New 1624 sq. Ft. Pre-fabricated metal building containing electrical control equipment for the new sage substation. The build”
- building permit: Buildingapplication / Trailer: filed“Permit number: 490319 · Type: Buildingapplication · Status: filed · Job value: $413,099 · Effective date: Jan. 31, 2025 · Address: 5601 MANOR WOODS RD · Description: Trailer permits for suffolk construction - (2) 60 x 36 temporary construction trailer (1) 60 x 24 temporary construction trailer (”
- building permit: Buildingapplication / Nonresbldg: issued“Permit number: 485395 · Type: Buildingapplication · Status: issued · Job value: $556,713 · Effective date: Sept. 20, 2024 · Address: 5601 MANOR WOODS RD · Description: Foundations for a substation encompassing 330 x 430. The scope of work includes slab foundations drilled piers and pillars. Se”
- building permit: Buildingapplication / Nonresbldg: issued“Permit number: 485398 · Type: Buildingapplication · Status: issued · Job value: $374,101 · Effective date: Sept. 20, 2024 · Address: 5601 MANOR WOODS RD · Description: Foundations for a substation encompassing 330 x 430. The scope of work includes slab foundations drilled piers and pillars. Se”
- building permit: Buildingapplication / Nonresbldg: issued“Permit number: 485736 · Type: Buildingapplication · Status: issued · Job value: $1,895,422 · Effective date: Sept. 20, 2024 · Address: 5601 MANOR WOODS RD · Description: Rowan - control enclosure building associated with substation”
- building permit: Buildingapplication / Froperm: issued“Permit number: 441856 · Type: Buildingapplication · Status: issued · Job value: $319,359 · Effective date: Jan. 4, 2023 · Address: 5601 MANOR WOODS RD · Description: <div>***plan has been revised. See plan f2777817 for latest revision (10.1.2025). The clock will have to start over to meet the f”
- building permit: Buildingapplication / Pi: issued“Permit number: 436351 · Type: Buildingapplication · Status: issued · Job value: $91,270 · Effective date: Jan. 3, 2023 · Business: Rodgers Consulting INC Yellow · Address: 5601 MANOR WOODS RD · Description: <div>pw271137 s1179”
- building permit: Buildingapplication / Froperm: issued“Permit number: 429764 · Type: Buildingapplication · Status: issued · Job value: $238,982 · Effective date: Oct. 11, 2022 · Address: 5601 MANOR WOODS RD · Description: <div>***fro plans have been revised under f277298***</div><div>eradication fence & signs plantings and specimen trees”
- building permit: Buildingapplication / Froperm: canceled“Permit number: 428451 · Type: Buildingapplication · Status: canceled · Job value: $238,982 · Effective date: Sept. 29, 2022 · Address: 5601 MANOR WOODS RD · Description: <div>eradication fence & signs plantings and speciman trees”
- building permit: Buildingapplication / Demolition: complete“Permit number: 96702 · Type: Buildingapplication · Status: complete · Job value: $10,000,000 · Effective date: Oct. 23, 2015 · Address: 5601 MANOR WOODS RD · Description: Phase 2 demolition (phase 1 was under #91754) for remaining plant buildings. No buildings to remain. Highlighted areas on p”
- Gov. Moore signed Executive Order 01.01.2026.16: statewide review framework for data center campuses >= 25 MW peak demand (task force, written determinations, public dashboard) - state-level signal affecting this campus'“On September 23, Gov. Wes Moore signed Executive Order 01.01.2026.16, creating a statewide review framework for data-center facilities or campuses with projected or actual peak demand of at least 25 megawatts”News report · Sept. 2026 · grade C
- Referendum petition certified sufficient by Frederick County Board of Elections: 24,053 signatures submitted, 21,029 validated vs 15,611 required (7% of registered voters)“On April 3, the Frederick County Board of Elections certified the petition as sufficient and approved the ballot question.”News report · April 2026 · grade C
- Site plan: Approved (unanimous)“The commission approved the submitted plan unanimously on Wednesday with the following additions: a 22-foot-tall concrete wall enclosing Building 3”News report · May 2025 · grade C
- Site plan: Approved 6-0-0“Bauxite II covers 822,620 sq ft (76,400 sqm) across a 111.5-acre site and received a unanimous 6-0-0 approval.”News report · May 2025 · grade C
- Site plan: Approved 5-0-1“The vote on Bauxite III was the same as the vote on Bauxite II, except that Sepe abstained.”News report · May 2025 · grade C
- Frederick County Planning Commission: Aligned Buildings 2-4 site plan (adds 1,149,000 sq ft)“The commission approved the submitted plan unanimously on Wednesday with the following additions: a 22-foot-tall concrete wall enclosing Building 3”News report · May 2025 · grade C
- Frederick County Planning Commission: Rowan Bauxite II site plan (822,620 sq ft, 111.5 acres)“Bauxite II covers 822,620 sq ft (76,400 sqm) across a 111.5-acre site and received a unanimous 6-0-0 approval.”News report · May 2025 · grade C
- Frederick County Planning Commission: Rowan Bauxite III site plan (591,913 sq ft, 55 acres)“The vote on Bauxite III was the same as the vote on Bauxite II, except that Sepe abstained.”News report · May 2025 · grade C
- Air quality permit to construct: Permit granted“The Maryland Department of the Environment also granted a construction permit to Aligned on Jan. 30, allowing the company to build 172 emergency diesel generators.”News report · Jan. 2025 · grade C
- Site plan: Conditional approval“received unanimous approval (5-0) from the Frederick County Planning Commission to develop the 300MW facility in January... four single-story buildings totaling 777,150 sq ft (72,200 sqm) across 151 acres”News report · Jan. 2025 · grade C
- Frederick County Planning Commission: Rowan Bauxite I site plan (300 MW, 4 buildings, 777,150 sq ft, 151 acres)“received unanimous approval (5-0) from the Frederick County Planning Commission to develop the 300MW facility in January”News report · Jan. 2025 · grade C
- Maryland Dept. of the Environment (public meeting): Draft air quality permit - Aligned Data Centers (172 emergency generators)“A public comment meeting on the Maryland Department of the Environment's (MDE) draft permit for Aligned will be held on Dec. 11 at 6 p.m. at Carroll Manor Elementary School.”News report · Dec. 2024 · grade C
- Air quality permit to construct (application): Application filed“Amazon Data Services applied for the permit in October 2024 to install the emergency backup generators at a planned data center site - named Bauxite I”News report · Oct. 2024 · grade C
- CPCN exemption: Provisional order (70 MW cap)“On Oct. 10, the commission issued a provisional order granting Aligned a provisional exemption to install diesel generators with a total combined capacity of 70 megawatts”News report · Oct. 2023 · grade C
- CPCN exemption: Denied (unanimous)“The Commission treats the fleet as an aggregate 504-megawatt generating station, denies the initial request... Maryland PSC annual report - PSC Order No. 90830”News report · Aug. 2023 · grade C
- MD PSC unanimously denied Aligned's CPCN exemption for 168 gensets (treated as one 504 MW generating station)“The Commission treats the fleet as an aggregate 504-megawatt generating station, denies the initial request”News report · Aug. 2023 · grade C
- CPCN exemption application: Filed“On May 12, Aligned applied to the Public Service Commission asking to be exempt from getting a certificate of public convenience and necessity (CPCN).”News report · May 2023 · grade C
Legal (5)
- Lawsuits: Referendum: Circuit Court C-10-CV-26-000309 (Bonifant J.) ruled Jun 18, 2026 ordinance not referendable; Supreme Court of MD Case No. 0067 affirmed Jun 30, 2026, opinion Jul 24, 2026. Sugarloaf Alliance v. Fred“Sugarloaf Alliance, Inc. v. Frederick County, Maryland, No. 32, September Term, 2025... Filed: July 14, 2026”Court filing · Oct. 2026 · grade A
- Sugarloaf Alliance, Inc. v. Frederick County, SCOM No. 32 (Sept Term 2025), filed Jul 14, 2026: MPIA attorneys' fees ($25,000 award held an abuse of discretion; Gould, J., dissenting). The underlying MPIA case (C-10-CV-2“The Majority holds that the trial court abused its discretion by awarding Sugarloaf Alliance, Inc. $25,000 in attorneys' fees.”Court filing · July 2026 · grade A
- Circuit Court for Frederick County (Bonifant, J., C-10-CV-26-000309) ruled Ordinance 26-01-001 is not subject to referendum and the petition was deficient (black-and-white maps did not reproduce the ordinance's color map“the circuit court agreed, finding both that the CDI Ordinance was not a 'law' subject to referendum under the Charter and that the petition's reproduction of the ordinance was insufficient”Court filing · June 2026 · grade A
- Quantum Maryland LLC sued Fitzwater, Frederick County and the Planning Commission in Frederick County Circuit Court: alleges the pause exceeded executive authority and was election-driven; a >$500M land transaction expec“Quantum also alleges that Fitzwater overstepped her authority by suspending a council-approved zoning ordinance that governs the site.”News report · Oct. 2026 · grade C
- Supreme Court of Maryland (per curiam order, Case No. 0067, Sept 2025 Term) affirmed: zoning ordinances are not subject to referendum under the Frederick County Charter; full opinion filed Jul 24, 2026 (Fader, C.J.)“The Supreme Court of Maryland has released its full opinion explaining its decision on June 30 to not allow a voter referendum on the ordinance that created Frederick County's new data center zone.”News report · June 2026 · grade C
Site and other (10)
- Md parcel address: 5601 MANOR WOODS RD, Frederick, MD 21703“Parcel ADDRESS field is '5601 MANOR WOODS RD', the gold campus address; legal description 'S/S MANOR WOODS RD, E/NEW DESIGN RD'”State agency · Oct. 2026 · grade A
- Facility address amazon: 3250 Digital Drive, Frederick, MD 21703“The data center facility will be located at 3250 Digital Drive in Frederick, Maryland 21703 in Frederick County”State agency · March 2026 · grade A
- Address: 5601 Manor Woods Road, Frederick MD 21703“The IAD04 data center facility will be located at 5601 Manor Woods Road in Frederick, Maryland 21703 in Frederick County.”State agency · July 2024 · grade A
- Parcel IDs: Tax Map 94, Parcel 71, Lot 106 (Aligned Lot 106)“MAP/PARCEL: Tax Map 94, Parcel 71, Lot 106”Local government · May 2023 · grade A
- Acres: 74.89 acres“construct a 450,000 SF gross floor area Critical Digital Infrastructure Facility on a 74.89-acre property”Local government · May 2023 · grade A
- Sponsor form d amount sold: 25291492“<totalAmountSold>25291492</totalAmountSold> <entityName>Quantum Loophole, Inc.</entityName>”SEC filing · July 2021 · grade A
- Sponsor form d amount sold 2020: 3050000“<totalAmountSold>3050000</totalAmountSold>”SEC filing · May 2020 · grade A
- Facility address amazon 2: 3300 Radiant Way, Frederick, MD 21703 (Bauxite II, phase "Amazon 2": five buildings; Frederick County site plans SP276740 / SP278472, Lots 301/302, county acct 01607698)“This site plan application is for a Bauxite 2 campus 3300 RADIANT WAY expansion. A portion of Lot 301 will be incorporated into Lot 302”Local government · Jan. 2026 · grade B
- Water use stated: APFO Phase 1 combined cooling demand cap 1.3 MGD; Bauxite I 392,000 gpd; Bauxite II 392,000 gpd; Bauxite III 297,000 gpd (total 1.081 MGD); Aligned uses no water cooling gpd/MGD“the first phase of development on the site is limited to projects whose total combined cooling water demand does not exceed 1.3 million gallons per day... Bauxite I and Bauxite II will each require 392,000 gallons of water per day”News report · May 2025 · grade C
- Groundbreaking date: Feb. 2025 (Aligned IAD-04 groundbreaking announced Feb 3, 2025; ceremonial groundbreaking Dec 2024)“Aligned's LinkedIn post on Feb. 3 announcing the groundbreaking said the data center under construction is called IAD-04.”News report · Feb. 2025 · grade C
Imagery and records: Satellite imagery: Maxar via Esri World Imagery Wayback; Sentinel-2 (ESA Copernicus). County deeds and building permits: ATTOM.