Power and the grid
Contracted, size not disclosed
- Black Hills Energy grid service under a confidential contract Contract signed, terms privateno MW figure public; customer pays energy at cost and must hold 115% capacity resources Company · June 2026
- Customer-provided backup generators and batteries Required by tariffbackup and capacity only; no MW published Utility regulator · Oct. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- July 28, 2016Large-load tariff approvedWyoming regulators approve the large-power tariff the campus is served under. Utility regulator · Aug. 2017
- June 14, 2026Substation being expandedThe developer is funding a new transformer at the Black Hills substation on site, stated at over $20M. Company · June 2026
- Under the tariff the customer must hold backup resources of at least 115% of its peak load and must obtain the air permits for its backup generators. Utility regulator · Oct. 2026
- Black Hills' Oct. 2026 deals for up to 590 MW and new gas generation in Cheyenne serve Google's campus, not this one. News report · Oct. 2026
Permits checklist
1 granted · 2 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup generators), and what we found.
- ✓Large-load electric service tariff GrantedWyoming Public Service Commission · July 28, 2016: a utility tariff, not zoning; effective in its current form since June 2024 Utility regulator · Aug. 2017
- –Checked, nothing on file: Air permit for backup generators, State sales-tax exemption
What could slow it down
- MediumOne tenant, one phaseOnly 88 MW of the 302 MW is leased, and CoreWeave's lease has no public rent, term or exit clause. SEC filing · June 2026
- MediumPower terms privateThe service contract is confidential and no utility MW figure is public; the tariff requires the customer to hold 115% backup resources. Company · Oct. 2026
- WatchAir permit not yet filedWyoming DEQ publicly notices Cheyenne generator permits when filed, and none exists for this campus. News report · Oct. 2026
- WatchLocal politicsThe council rejected a moratorium 8-1, but no campus-specific opposition has been found. Company · June 2026
Money on record
What happened, and what is due
- Oct. 7, 2025Site Groundbreaking and first announcement: a $1.2B, 302 MW campus with CoreWeave as anchor tenant. Company · Oct. 2025
- May 26, 2026Permits Cheyenne council rejects a 12-month data center moratorium 8-1. News report · May 2026
- June 11, 2026Site Governor and mayor tour the site; the first building's walls are rising and over 400 workers are on site. Company · June 2026
- June 14, 2026Site The developer says the campus will ultimately deliver up to 420 MW for CoreWeave, above the 302 MW in its release. Company · June 2026
- June 2026Money CoreWeave's quarterly filing does not identify the lease or its value. SEC filing · June 2026
- Dec. 2026Site First building due to finish; CoreWeave's lease starts after. Company · June 2026
Since March 2026: 1 FAA filing (March 2026): a 256 ft crane. FAA · March 2026
Specs
- Air-cooled: chillers plus closed-loop liquid cooling; nominal water use, company says Company · June 2026
Owners, partners and builders
- Related Digital: developer and owner
- Related Companies: parent
- CoreWeave: anchor tenant, 88 MW
- Black Hills Energy (Cheyenne Light, Fuel and Power): utility
- Clayco: construction manager
- Cheyenne LEADS: economic development partner
- Wyoming Public Service Commission: sets the utility tariff
Open questions
- How much of the 302 MW is built or leased beyond phase 1.
- The utility load and contract terms.
- Generator air permit and fuel plan.
123 records from 19 documents
Drawn from company statements, state agency records, news reports, public and commercial datasets, utility regulator dockets and securities filings, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (25)
- On-site generation: On-site backup generation and batteries are installed/required, but no capacity figure is published MW“the Customer must agree to provide backup service for the Customer's load and to maintain the reliability of the backup service”Utility regulator · Oct. 2026 · grade A
- Power plan: grid (CLFP LPCS pass-through energy) + customer-provided on-site backup capacity (backup generators and batteries)“This Rate Schedule is applicable for new or existing customer load interconnected with the Company's system with expected capacity requirements of 5,000 kW or greater”Utility regulator · Oct. 2026 · grade A
- Grid operator: none (Wyoming is not in an ISO/RTO; the CLFP system interconnects with the WAPA-LAP transmission system, WECC)“All Eligible Capacity Resources that are not located onsite must be interconnected either to the Company's system, the WAPA-LAP transmission system”Utility regulator · Oct. 2026 · grade A
- Registry status: UNDER CONSTRUCTION, NO PROJECT PERMIT IN EVIDENCE. Groundbreaking Oct 7, 2025 (Clayco; CoreWeave anchor, first building due late 2026) at Campstool Business Park / Cheyenne Business Parkway, east Cheyenn“Black Hills requested approval of the CPCN because its customer, the developer of the Switchgrass Industrial Park, requested wholesale electric service for a data center facility at the Switchgrass Industrial Park”State agency · Oct. 2026 · grade B
- Name: Related Digital Cheyenne“Related Digital Breaks Ground on 302 MW Data Center Campus in Cheyenne, Wyoming”Company · Oct. 2026 · grade B
- Aliases: Related Digital Cheyenne Data Center Campus; Cheyenne Business Parkway campus“the first phase of a 115-acre campus in the Cheyenne Business Parkway with up to 302 MWs of critical IT capacity”Company · Oct. 2026 · grade B
- Utility service: No utility-basis MW figure is published for this campus in any source reviewed“Black Hills Energy will serve as the electric service provider for the initial phase”Company · Oct. 2026 · grade B
- Interconnection status: Service arranged under CLFP Rate Schedule LPCS via a Confidential Large Power Service Agreement (terms not public); the on-site Black Hills substation is being expanded with a new transformer fund“We're investing more than $20 million to purchase a new transformer and expand the existing substation to service this data center”Company · June 2026 · grade B
- Water cooling: Air-cooled chillers plus a closed-loop direct-to-chip liquid cooling system; company states nominal water consumption (primarily domestic use) and no ongoing cooling makeup water“As long as the closed-loop system is kept tight and filled, there's essentially no ongoing makeup water required”Company · June 2026 · grade B
- Governor/mayor site tour: first building's concrete walls rising and the phase nearing completion; about 80,000 ft of chiller pipe and 40,000 ft of medium-voltage conduit installed; 21,000 linear ft of underground utilit“Related Digital broke ground in October and has since installed about 80,000 feet of chiller pipes, 40,000 feet of medium-voltage conduits to feed the data center power”Company · June 2026 · grade B
- A June 2026 tour article on the company's own site states the campus will ultimately deliver up to 420 MW of computational capacity for CoreWeave, larger than the 302 MW critical IT capacity in the formal release; unexp“Related's Cheyenne campus will ultimately deliver up to 420 megawatts of computational capacity for its client, CoreWeave”Company · June 2026 · grade B
- IT capacity: 302 MW“marks the first phase of a 115-acre campus in the Cheyenne Business Parkway with up to 302 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- Site acres: 115 acres“marks the first phase of a 115-acre campus in the Cheyenne Business Parkway with up to 302 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- IT capacity: 88 MW“CoreWeave will be the anchor tenant through a long-term lease for 88 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- Interconnection status: Under construction (ground broken Oct 7, 2025; first building due late 2026); Black Hills Energy is the named utility partner and electric service provider for the initial phase (groundbreaking re“was joined today by Wyoming Governor Mark Gordon, Cheyenne Mayor Patrick Collins, CoreWeave, Clayco, Black Hills Energy, other development partners and local officials at the groundbreaking of a new $1.2 billion state-of-the-art data center”Company · Oct. 2025 · grade B
- IT capacity: 302 MW“up to 302 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- IT capacity: 88 MW“CoreWeave will be the anchor tenant through a long-term lease for 88 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- Utility: Black Hills Energy (Cheyenne Light, Fuel and Power Company), electric service provider for the initial phase“Clayco will serve as construction manager and Black Hills Energy will serve as the electric service provider for the initial phase”Company · Oct. 2025 · grade B
- First announced: Oct. 7, 2025 (the groundbreaking release is the first public announcement located)“Related Digital Breaks Ground on 302 MW Data Center Campus in Cheyenne, Wyoming”Company · Oct. 2025 · grade B
- Groundbreaking and first public announcement: $1.2B campus on 115 acres in the Cheyenne Business Parkway, up to 302 MW critical IT at full build-out; CoreWeave anchor tenant at 88 MW; 700+ construction jobs and 40 perman“Phase I of the development is expected to generate over $250 million in tax revenue to the State of Wyoming and City of Cheyenne in its first 15 years of operations”Company · Oct. 2025 · grade B
- Developer portfolio context (NOT campus MW): Related Digital states a $45B development pipeline of more than 5 GW of near-term power across the United States and Canada“With a $45 Billion development pipeline of more than 5 gigawatts (GW) of near-term power across the United States and Canada”Company · Oct. 2025 · grade B
- Nearest power line of 345 kV or more: 5.12 kmMeasured on OpenStreetMap map data.
- Nearest gas pipeline: 7.36 km (unnamed, operator not mapped); a nearer pipeline at 2.06 km carries no substance tag and is not counted as gasMeasured on OpenStreetMap map data.
- Nearest substation of 345 kV or more: 5.36 kmMeasured on OpenStreetMap map data.
- up to 590 MW of grid service plus about 2.1 GW of managed third-party microgrid resources“Black Hills Corp. on Oct. 6 announced it has signed definitive agreements effective Sept. 30, 2026, with terms through 2048, to serve a planned Google data center to be constructed in Cheyenne, Wyoming”News report · Oct. 2026 · grade C
Money and contracts (33)
- electric service (LPCS): instrument Service is taken under a Confidential Large Power Service Agreement negotiated under Rate Schedule LPCS; the agreement itself is not public“If the parties agree through negotiations to electric service through this Rate Schedule, a Confidential Large Power Service Agreement (Agreement) will be executed”Utility regulator · Oct. 2026 · grade A
- electric service (LPCS): capacity requirement Customer must hold Eligible Capacity Resources of at least 115% of its actual peak monthly load served under the schedule; energy service is limited to the load covered by th“the Customer must have Eligible Capacity Resources, as defined in this Rate Schedule, that are greater than or equal to 115% of the Customer's actual peak monthly load served under this Rate Schedule”Utility regulator · Oct. 2026 · grade A
- electric service (LPCS): backup service Customer must provide and maintain backup service for its load through Eligible Capacity Resources (on the customer's property or delivered by firm transmission rights); all Eligib“the Customer must agree to provide backup service for the Customer's load and to maintain the reliability of the backup service”Utility regulator · Oct. 2026 · grade A
- electric service (LPCS): energy charges Capacity and energy procured or generated by the company on the customer's behalf are billed monthly at actual cost (pass-through), including transmission and ancillary charges“Capacity and Energy Charges - are the charges for the energy or capacity procured or generated by the Company on behalf of the Customer billed on a monthly basis based on actual energy or capacity costs”Utility regulator · Oct. 2026 · grade A
- electric service (LPCS): microgrid management fee Negotiated fee in $/kW-month based on the peak demand of the load served under the schedule, as defined in the service agreement; administrative costs are a formula $/kW-“Microgrid Management Fee – $/kWmo., negotiated rate based on the peak demand of the load served under this Rate Schedule for the customer as defined in the Agreement”Utility regulator · Oct. 2026 · grade A
- electric service (LPCS): air permits Customer must provide the associated air permits for backup generators owned by the customer (an Eligible Capacity Resource category)“Customers will need to provide the associated air permits for backup generators owned by the Customer”Utility regulator · Oct. 2026 · grade A
- electric service (LPCS): termination / minimum term FINDING: the public LPCS tariff sheets state no minimum term, early-termination charge or exit fee; any such terms sit in the Confidential Large Power Service Agreement“The electric service under this Rate Schedule is not applicable to temporary, standby, emergency, resale, shared, or incidental purposes”Utility regulator · Oct. 2026 · grade A
- data center lease: termination FINDING: no termination, cancellation or early-exit clause for this lease is disclosed in any public source reviewed (developer release; CoreWeave SEC filings)“As of June 30, 2026, the Company executed additional lease agreements, primarily for data centers, equipment, and office buildings, that had not yet commenced”SEC filing · June 2026 · grade A
- data center lease: value / rent FINDING: rent and lease value not disclosed; the lease is not separately identified in CoreWeave's Q2 2026 10-Q (no mention of Cheyenne or Related) and is at most inside the $35.5B aggrega“The aggregate amount of estimated future undiscounted lease payments associated with such leases is $35.5 billion”SEC filing · June 2026 · grade A
- Tenant status: Long-term lease signed for 88 MW of critical IT capacity in the first building; lease not yet commenced, building completes late 2026; CoreWeave's SEC filings do not identify the lease“CoreWeave will be the anchor tenant through a long-term lease for 88 MWs of critical IT capacity”Company · Oct. 2026 · grade B
- Incentives: Wyoming sales/use tax exemption for data-processing-center equipment (W.S. 39-15-105(a)(viii); W.S. 39-16-105(a)(viii)) is available by statute: equipment tier requires over $2M of qualifying purchases in a y“This exemption is located within the economic incentive group of sales and use tax exemptions in the Wyoming statutes”State agency · Oct. 2026 · grade B
- sales/use tax exemption (statutory): campus status (finding) FINDING: no Wyoming Business Council jobs certification, Dept. of Revenue exemption record, local tax abatement or development agreement naming Related Digital“the data processing services center must have received certification from the Wyoming Business Council that the business has created or will create a number of jobs in Wyoming”State agency · Oct. 2026 · grade B
- community commitment: affordable housing 3500000 USD“They've also made a $3.5 million commitment for affordable housing in Cheyenne”Company · June 2026 · grade B
- community commitment: interconnection investment 20000000 USD“We're investing more than $20 million to purchase a new transformer and expand the existing substation to service this data center”Company · June 2026 · grade B
- Related states a $3.5M commitment for affordable housing in Cheyenne, alongside food-bank and Cheyenne Frontier Days support; the housing pledge was also referenced by the mayor at the Nov 25, 2025 council meeting (aggre“They've also made a $3.5 million commitment for affordable housing in Cheyenne, something Blau said he's particularly proud of doing”Company · June 2026 · grade B
- Tenant status: CoreWeave - anchor tenant under a long-term lease for 88 MW of critical IT capacity in the first building; remainder of the 302 MW campus unleased in the sources checked“CoreWeave will be the anchor tenant through a long-term lease for 88 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- Project status: under construction“was joined today by Wyoming Governor Mark Gordon, Cheyenne Mayor Patrick Collins, CoreWeave, Clayco, Black Hills Energy, other development partners and local officials at the groundbreaking of a new $1.2 billion state-of-the-art data center”Company · Oct. 2025 · grade B
- Tenants: CoreWeave, Inc.“Initial 184,000-square-foot building, anchored by CoreWeave as first tenant, will provide 88 MWs of critical IT capacity.”Company · Oct. 2025 · grade B
- Tenant status: signed“Initial 184,000-square-foot building, anchored by CoreWeave as first tenant, will provide 88 MWs of critical IT capacity.”Company · Oct. 2025 · grade B
- Tenants: CoreWeave (anchor tenant, Phase 1)“CoreWeave will be the anchor tenant through a long-term lease for 88 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- Groundbreaking date: Oct. 7, 2025“other development partners and local officials at the groundbreaking of a new $1.2 billion state-of-the-art data center”Company · Oct. 2025 · grade B
- Stated capital cost: 1200000000 USD“groundbreaking of a new $1.2 billion state-of-the-art data center that marks the first phase of a 115-acre campus”Company · Oct. 2025 · grade B
- Tenant lease: execution“the groundbreaking of a new $1.2 billion state-of-the-art data center that marks the first phase of a 115-acre campus in the Cheyenne Business Parkway with up to 302 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- Tenant lease: capacity 88 MW critical IT“CoreWeave will be the anchor tenant through a long-term lease for 88 MWs of critical IT capacity.”Company · Oct. 2025 · grade B
- Tenant lease: delivery“The first data center building will occupy 184,000 SF on 36 acres and is expected to be completed late 2026.”Company · Oct. 2025 · grade B
- data center lease: scope 88 MW“CoreWeave will be the anchor tenant through a long-term lease for 88 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- data center lease: term Long-term lease; term in years not disclosed“CoreWeave will be the anchor tenant through a long-term lease for 88 MWs of critical IT capacity”Company · Oct. 2025 · grade B
- electric service (LPCS): cost allocation (company statement) Black Hills states its regulated large power contract service tariff enables it to serve large-load data center customers in Wyoming with no cost impact to loc“Black Hills' regulated large power contract service tariff enables us to serve large-load data center customers in Wyoming with no cost impact to our local retail customers”Company · Oct. 2025 · grade B
- Phase I expected to create over 700 construction jobs and 40 permanent jobs; $250M+ tax revenue projected over the first 15 years“create over 700 construction jobs and 40 well-paying, permanent jobs”Company · Oct. 2025 · grade B
- sales/use tax exemption (statutory): exemption scope Sales and use tax exempt, per tier, when aggregate qualifying purchases exceed $2M in a calendar year: (I) computer software, computer equipment, servers, storage, per“The sales price paid for the purchase or rental of qualifying uninterruptable power supplies, back-up power generators, specialized heating and air conditioning equipment”State agency · Nov. 2020 · grade B
- sales/use tax exemption (statutory): investment threshold Initial total capital asset investment in a Wyoming physical location: not less than $5,000,000 (tier I) / not less than $50,000,000 (tier II)“an initial capital investment of not less than fifty million dollars ($50,000,000)”State agency · Nov. 2020 · grade B
- sales/use tax exemption (statutory): jobs condition Purchaser must have received certification from the Wyoming Business Council that it has created or will create a number of jobs in Wyoming appropriate to the size and“the data processing services center must have received certification from the Wyoming Business Council that the business has created or will create a number of jobs in Wyoming”State agency · Nov. 2020 · grade B
- sales/use tax exemption (statutory): clawback Per the statutory text (W.S. 39-15-105(a)(viii)): if the annual $2M threshold is not met, or the subparagraph's requirements are not met, the excise tax on otherwise qualifyi“when the aggregate purchase of the qualifying equipment exceeds two million dollars ($2,000,000.00) in any calendar year”State agency · Nov. 2020 · grade B
Permits and government (11)
- tariff revision: revised tariff effective“This Rate Schedule is applicable for new or existing customer load interconnected with the Company's system with expected capacity requirements of 5,000 kW or greater”Utility regulator · Oct. 2026 · grade A
- FAA status: Screened at Cheyenne city point: 40 cases in the 5-NM circle (all statuses, 2021-2026 window). 40 cases are airport works, retail cranes and one 'Microsoft CYS' 300-ft mobile crane (Microsoft's campus, a guar“FAA OE/AAA circle pull at 41.1400,-104.8197 (5 NM, 2021-2026): 40 cases; 40 cases are airport works, retail cranes and one 'Microsoft CYS' 300-ft mobile crane (Microsoft's campus, a guard)”FAA · Oct. 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-ANM-1858-OE: Leibherr LR1700-1.0 /Clayco Jobsite, Mobile Crane, 256 ft AGL, 6256 ft AMSL, 41.14617,-104.69444, Determined - No Hazard, submitted 2026-03-31”FAA · March 2026 · grade B
- FAA OE/AAA records a 256-ft mobile crane filed as 'Leibherr LR1700-1.0 /Clayco Jobsite' (ASN 2026-ANM-1858-OE, submitted March 31, 2026) 1.27 km east of this folder's park-core anchor in the Cheyenne Business Parkway - Clayc“ASN 2026-ANM-1858-OE: Leibherr LR1700-1.0 /Clayco Jobsite, Mobile Crane, 256 ft AGL, 6256 ft AMSL, 41.14617,-104.69444, Determined - No Hazard, submitted 2026-03-31”FAA · March 2026 · grade B
- tariff application: application filed“On October 1, 2015, CLF&P filed its application for approval of a new Large Power Contract Service (LPCS) tariff”Utility regulator · Aug. 2017 · grade B
- tariff approval: approved“The Commission approved the proposed tariff with minor revisions and clarifications, as recommended by Dyno and Holy Frontier”Utility regulator · Aug. 2017 · grade B
- Wyoming Public Service Commission: Approval of Cheyenne Light, Fuel & Power Large Power Contract Service (LPCS) tariff, Docket No. 20003-146-ET-15“After a contested hearing the Commission determined the arguments advanced by Dyno and Frontier were without merit and that the proposed tariff is in the public interest and should be approved”Utility regulator · Aug. 2017 · grade B
- air permit: no filing located“The Wyoming Department of Environmental Quality (DEQ) announced its preliminary decision to approve the permit in April”News report · Oct. 2026 · grade C
- No WY DEQ air permit for the campus's backup generators located as of this date, although DEQ publicly processes Cheyenne data-center genset permits (Microsoft, 128 units, preliminary approval April 2026). Under the LPCS“A proposal from Microsoft to install 128 diesel generation units across its data center portfolio in Cheyenne, Wyoming, is set for approval”News report · Oct. 2026 · grade C
- Cheyenne City Council rejected a 12-month moratorium on new data center development 8-1 after hours of debate; the measure was citywide and this campus, already under construction, was not its subject“The proposal followed heated public comment from both residents concerned about impacts and industry supporters warning of economic harm”News report · May 2026 · grade C
- Cheyenne City Council: Proposed 12-month moratorium on new data center development (citywide; this campus already under construction and not the subject)“The Cheyenne City Council has overwhelmingly rejected a 12-month moratorium on new data center development, voting 8–1 after hours of debate”News report · May 2026 · grade C
Legal (1)
- Announced: Oct. 7, 2025“Related Digital, a vertically integrated data center development and investment platform, was joined on Oct. 7, 2025, by Wyoming Gov. Mark Gordon, Cheyenne Mayor Patrick Collins, CoreWeave, Clayco, Black Hills Energy”News report · Oct. 2025 · grade C
Site and other (13)
- County: Laramie County, WY“The fringe territory is further defined as the area between the city limits and areas within the Sixth Principal Meridian in Laramie County, Wyoming”Utility regulator · Oct. 2026 · grade A
- County code: 56021“FCC census block find for latitude 41.141 longitude -104.708 returned County FIPS 56021, name Laramie County, block 560210020023071”Dataset · Oct. 2026 · grade B
- Construction stage: building, first 184,000 SF building nearing completion as of June 2026; later campus phases not started“Work is nearing completion on the first 184,000-square-foot phase of the campus, which is expected to be finished in late 2026”Company · June 2026 · grade B
- Stage: building“Work is nearing completion on the first 184,000-square-foot phase of the campus, which is expected to be finished in late 2026”Company · June 2026 · grade B
- Current target date: late 2026 (first building), reaffirmed June 2026; no slip announced“Work is nearing completion on the first 184,000-square-foot phase of the campus, which is expected to be finished in late 2026”Company · June 2026 · grade B
- Opposition: No campus-specific opposition, litigation or referendum located in sources reviewed; state and city officials publicly supportive at the groundbreaking and at the June 2026 site tour“What Related has done here is absolutely astounding”Company · June 2026 · grade B
- Construction stage: under construction - groundbreaking Oct 7, 2025 with Clayco as construction manager; the first building (184,000 sq ft on a 36-acre parcel) is expected to be completed late 2026“The first data center building will occupy 184,000 SF on 36 acres and is expected to be completed late 2026”Company · Oct. 2025 · grade B
- Developer: Related Digital (data center development and investment platform of Related Companies)“Related Digital, a vertically integrated data center development and investment platform”Company · Oct. 2025 · grade B
- City: Cheyenne, WY“We're delighted Related Digital has chosen Cheyenne as the location for their new data center”Company · Oct. 2025 · grade B
- Acres: 115 acres“the first phase of a 115-acre campus in the Cheyenne Business Parkway”Company · Oct. 2025 · grade B
- Phase 1 building: First data center building: 184,000 SF on 36 acres; completion expected late 2026“The first data center building will occupy 184,000 SF on 36 acres and is expected to be completed late 2026”Company · Oct. 2025 · grade B
- Original target date: late 2026 (first building)“The first data center building will occupy 184,000 SF on 36 acres and is expected to be completed late 2026”Company · Oct. 2025 · grade B
- First data center building (184,000 SF on 36 acres) expected to be completed late 2026“The first data center building will occupy 184,000 SF on 36 acres and is expected to be completed late 2026”Company · Oct. 2025 · grade B