Power and the grid
Contracted, size not disclosed · 365 MW permitted
- Black Hills Energy grid service (large-load tariff) Contracted under tariffservice is under a confidential contract; the campus MW is not public Company · Oct. 2026
- Customer-owned backup capacity (behind the meter) Required by tariffthe tariff requires the customer to provide its own backup; size not stated and not a power supply Utility regulator · Oct. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- June 1, 2024Large-load tariff in forceBlack Hills Energy's tariff for customers above 13 MW takes effect, with a confidential service agreement negotiated case by case. Utility regulator · Oct. 2026
- July 2, 2024Meta says it will add grid resourcesAt announcement Meta says it will work with Black Hills Energy to add new resources to the grid, including renewables. Company · Oct. 2026
- May 19, 2026Dedicated solar and battery announcedEnbridge announces 365 MW of solar and a 200 MW battery for Meta, the first project procured through the utility's large-load tariff. Company · Oct. 2026
- Not setContract terms: not publicNo power purchase price, term or termination clause has been disclosed. Company · Oct. 2026
- Wyoming has no regional grid operator, and the campus is served by the local utility rather than a market. Utility regulator · Oct. 2026
- Enbridge says its partnership with Meta now totals about 1.6 GW (company). Company · Oct. 2026
Permits checklist
2 revoked · 1 contested · 2 granted
- ✕Temporary wastewater discharge authorization RevokedCheyenne Board of Public Utilities · March 27, 2026: ended after the bacterium Cupriavidus gilardii was traced to the site's fill-and-flush discharge Local government · Oct. 2026
- ✕Industrial user discharge privileges RevokedCheyenne Board of Public Utilities · June 26, 2026: city says permanently terminated (press) News report · Oct. 2026
- !Notice of significant noncompliance ContestedCheyenne Board of Public Utilities · July 2, 2026: $10,000 fine paid under protest; developer appealed July 13 and seeks a contested case hearing Local government · Oct. 2026
- ✓Development agreement and rezoning terms GrantedCheyenne City Council · Nov. 13, 2023: approved after a Feb. 2023 memorandum of understanding; the agreement itself grants no entitlements News report · Oct. 2026
- ✓Industrial siting permit for Cowboy Solar I and II GrantedWyoming Industrial Siting Council · May 21, 2024: up to 771 MW in two phases; Meta's contracted supply State agency · Oct. 2026
What could slow it down
- HighNo wastewater outletThe city's utility board permanently terminated the industrial user's wastewater discharge privileges in June 2026, after a bacterium was traced to the site (press). see Permits
- MediumOpening date unannouncedMeta has not announced the campus operational, and the Epoch AI tracker estimate puts capacity built so far at about 152 MW of 249 MW planned.
- MediumContested fine and cost recoveryA surcharge to recover the city's costs is still to come, and the appeal is unresolved. Local government · Oct. 2026
- WatchDedicated supply arrives lateThe Enbridge solar and battery project is due only by the end of 2027, so the dedicated supply is not yet in place. Company · Oct. 2026
1 case on record
- Filed July 13, 2026; contested case pending Goat Systems appeal of the noncompliance noticeCheyenne Board of Public Utilities (administrative) Local government · Oct. 2026developer says the contractor holding the discharge authorization was the proper respondent
Money on record
- Fees only: city development agreement (developer pays park, public safety and building permit fees) Local government · Oct. 2026
3 recorded land documents for the campus company in county records (Aug. 2022 to Sept. 2022); none lists a price. Parcel counts come from the deed; acreage is not recorded.
- Aug. 2022 Sara to Goat Systems LLC · price not recorded County deed records · Aug. 2022
- Aug. 2022 Schroth and Schroth to Goat Systems LLC · price not recorded County deed records · Aug. 2022
- Sept. 2022 Sara and Sara to Goat Systems LLC · price not recorded County deed records · Sept. 2022
What happened, and what is due
- April 28, 2022Paper trail Goat Systems LLC registered in Wyoming
- Aug. 26, 2022Money Land purchase recorded (no price on the deed): Sara to Goat Systems LLC County deed records · Aug. 2022
- Feb. 27, 2023Permits City council approves a memorandum of understanding with Goat Systems for Project Cosmo. Local government · Oct. 2026
- Nov. 13, 2023Permits Council approves the development agreement for a 945-acre campus. News report · Oct. 2026
- May 21, 2024Power State issues the siting permit for the Cowboy solar project that later supplies Meta. State agency · Oct. 2026
- July 2, 2024Site Meta announces its Cheyenne data center, its 21st in the U.S. Company · Oct. 2026
- March 27, 2026Legal City revokes the site's temporary wastewater discharge authorization after a bacterium is traced to it. Local government · Oct. 2026
- May 19, 2026Power Enbridge announces 365 MW of solar and a 200 MW battery for Meta's Wyoming load. Company · Oct. 2026
- July 2, 2026Legal City issues a significant noncompliance notice and $10,000 fine to Goat Systems (press). Local government · Oct. 2026
- July 2, 2026Permits The city utility board adopts a policy barring wastewater discharges from data centers using closed-loop or fill-and-flush cooling (press). News report · Oct. 2026
- July 13, 2026Legal Goat Systems pays the fine under protest and appeals, arguing the construction contractor was the proper respondent. Local government · Oct. 2026
- 2027Construction Opening targeted for 2027 in a third-party listing; Meta has published no opening date.
- End of 2027Power Enbridge's Cowboy Phase 1 due in service. Company · Oct. 2026
Specs
- Closed-loop cooling: city water and sewer; discharge now barred by city policy Local government · Oct. 2026
- Fortis Construction: general contractor Company · Oct. 2026
Owners, partners and builders
- Meta Platforms: owner and operator
- Goat Systems LLC: shell developer and city counterparty; Pamela Gregorski, president
- Cheyenne Light, Fuel and Power (Black Hills Energy): utility
- Enbridge: builds the Cowboy solar and battery project
- Fortis Construction: general contractor
- Cheyenne City Council
- Cheyenne Board of Public Utilities: wastewater enforcement
- Wyoming Industrial Siting Council: solar permit
Open questions
- Whether and when Meta opens the campus.
- Campus IT capacity in MW, which Meta has not stated.
- How the wastewater dispute and discharge policy are resolved.
- Terms of the power contract.
126 records from 16 documents
Drawn from news reports, local government records, company statements, business registries, public and commercial datasets, utility regulator dockets, state agency records and court filings, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (13)
- Grid operator: none (WECC; Wyoming has no ISO/RTO)“The territory served by the Company is the City of Cheyenne and the Fringe and Rural areas adjacent thereto”Utility regulator · Oct. 2026 · grade A
- Utility service: not stated“If the parties agree through negotiations to electric service through this Rate Schedule, a Confidential Large Power Service Agreement (Agreement) will be executed”Utility regulator · Oct. 2026 · grade A
- On-site generation: not stated“In order to receive service under this Rate Schedule, the Customer must agree to provide backup service for the Customer's load”Utility regulator · Oct. 2026 · grade A
- Wyoming Industrial Siting Council permit issued for Cowboy Solar I & II (up to 771 MW, all Laramie County), the permitted project behind Meta's contracted renewable supply; county land-use approvals for the solar projec“The Project is planned to be up to 771 megawatts in size and all panels and associated infrastructure will be located in Laramie County”State agency · Oct. 2026 · grade A
- Utility: Cheyenne Light, Fuel and Power Company d/b/a Black Hills Energy“Cheyenne Light, Fuel and Power (CLFP) will deliver the project's power to Meta under Wyoming's Large Power Contract Service (LPCS) tariff”Company · Oct. 2026 · grade B
- Utility designation: Cheyenne Data Center CHY 1-2 (BOPU industrial-user designation)“Notice of Significant Noncompliance – Meta Cheyenne Datacenter CHY1-2 (CHY1-2), In the Matter of Noncompliance with Cheyenne City Code Chapter 13.20”Local government · Oct. 2026 · grade B
- Power plan: grid (CLFP LPCS tariff) with customer-owned behind-the-meter backup capacity; contracted off-site renewables (Cowboy Solar + BESS) delivered under the same tariff“Cheyenne Light, Fuel and Power (CLFP) will deliver the project's power to Meta under Wyoming's Large Power Contract Service (LPCS) tariff”Company · Oct. 2026 · grade B
- Enbridge Cowboy Project Phase 1 announced for Meta's Wyoming load: 365 MW solar + 200 MW/1,600 MWh BESS, $1.2B, delivered via CLFP under the LPCS tariff, targeted in service end of 2027, first project procured by Meta t“Cheyenne Light, Fuel and Power (CLFP) will deliver the project's power to Meta under Wyoming's Large Power Contract Service (LPCS) tariff”Company · Oct. 2026 · grade B
- Utility: Black Hills Energy (Cheyenne Light, Fuel & Power)“Meta will work with Black Hills Energy to add new resources to the grid, including renewables.”Company · July 2024 · grade B
- Buildings: 2“Renderings suggest at least two buildings and on-site substations are planned”News report · Oct. 2026 · grade C
- BOPU drained and disinfected the entire reuse water system and Prairie View Pond; final samples confirmed no Cupriavidus gilardii present and the reuse irrigation system was restarted June 27, 2026 (irrigation resumed Ju“That same day, BOPU received final sample results confirming that no Cupriavidus gilardii were present in the reuse system. The next day, the reuse system was restarted”News report · Oct. 2026 · grade C
- BOPU drained and disinfected the reuse water system and Prairie View Pond over roughly two months and temporarily switched affected irrigation systems to potable water - the scale of the municipal response to the fill-an“Over the past two months, BOPU drained and disinfected the reuse water system and Prairie View Pond and temporarily switched affected irrigation systems to potable water supplies”News report · July 2026 · grade C
- Enbridge's Cowboy Project (365 MW solar + 200 MW/1,600 MWh Tesla-supplied storage, ~$1.2B, in service expected end-2027) will deliver power to Meta through Cheyenne Light, Fuel and Power under the LPCS tariff - a supply-“The project will deliver power to Meta “through Cheyenne Light, Fuel and Power under a large-load tariff designed to serve data centers without affecting retail electricity rates,””News report · May 2026 · grade C
Money and contracts (32)
- City: Cheyenne, WY“A development agreement between the City of Cheyenne, Cheyenne, Wyoming, a municipal corporation and Goat Systems, LLC”Local government · Oct. 2026 · grade A
- Memorandum of Understanding: scope/approval“was preceded by a memorandum of understanding (MOU) which was approved by the Governing Body on February 27, 2023”Local government · Oct. 2026 · grade A
- Development Agreement: scope“The developer, Goat Systems, LLC, proposes an approximate 945-acre data center campus development”Local government · Oct. 2026 · grade A
- Development Agreement: fees and infrastructure obligations“The developer will be required to pay park fees, public safety fees, and building permit revenue and will aid in construction of onsite and offsite infrastructure (sewer, water, and roadways)”Local government · Oct. 2026 · grade A
- Development Agreement: condition/limitation, no approvals granted“The City's intent of the DA is to provide assurances of anticipated fees and costs to the developer - not to prematurely grant the developer any specific approvals or exceptions to City requirements”Local government · Oct. 2026 · grade A
- Development Agreement: termination/cancellation, FINDING: the council packet copy of the DA was a placeholder, so no termination, cancellation or clawback clause of the executed DA could be reviewed from the public pack“This shall serve as a place holder for the Development Agreement between the City of Cheyenne, Cheyenne, Wyoming, a municipal corporation and Goat Systems, LLC, a Delaware limited liability company”Local government · Oct. 2026 · grade A
- Electric service, LPCS tariff (Rate Schedule LPCS, Wyo. P.S.C. Tariff No. 14): scope/applicability“This Rate Schedule is applicable for new or existing customer load interconnected with the Company's system with expected capacity requirements of 5,000 kW or greater”Utility regulator · Oct. 2026 · grade A
- Electric service, LPCS tariff: condition, customer backup capacity obligation“In order to receive service under this Rate Schedule, the Customer must agree to provide backup service for the Customer's load and to maintain the reliability of the backup service”Utility regulator · Oct. 2026 · grade A
- Electric service, LPCS tariff: cost responsibility“The costs of the Eligible Capacity Resources, any associated transmission costs and any ancillary service or other costs will be the responsibility of the Customer”Utility regulator · Oct. 2026 · grade A
- Electric service, LPCS tariff: confidentiality of service agreement“If the parties agree through negotiations to electric service through this Rate Schedule, a Confidential Large Power Service Agreement (Agreement) will be executed”Utility regulator · Oct. 2026 · grade A
- Electric service, LPCS tariff: termination/exit, FINDING: no exit clause in tariff sheets; terms would sit in the confidential LPCS Agreement“The electric service under this Rate Schedule is not applicable to temporary, standby, emergency, resale, shared, or incidental purposes”Utility regulator · Oct. 2026 · grade A
- Tenants: Meta (owner-occupied own campus)“Cheyenne, Wyoming, will be home to our newest Meta data center”Company · Oct. 2026 · grade B
- Tenant status: owner-occupied; no third-party tenants“This 715,000-square-foot campus will be part of our global infrastructure that helps bring our technologies and services to life”Company · Oct. 2026 · grade B
- Capital cost announced: more than 800 USD million“Once completed, the Cheyenne Data Center will represent an investment of more than $800 million”Company · Oct. 2026 · grade B
- Jobs permanent: approximately 100 jobs“will represent an investment of more than $800 million and support approximately 100 jobs”Company · Oct. 2026 · grade B
- General contractor: Fortis Construction, Inc.“For construction information, please check the Fortis Construction website”Company · Oct. 2026 · grade B
- Renewable supply, Cowboy Project Phase 1: scope 365 MW solar“Located near Cheyenne, Wyoming, the project will combine 365 megawatts (MW) of solar generation and a 200MW/1600MWhr battery energy storage system (BESS)”Company · Oct. 2026 · grade B
- Renewable supply, Cowboy Project Phase 1: delivery mechanism 200 MW / 1600 MWh BESS“Cheyenne Light, Fuel and Power (CLFP) will deliver the project's power to Meta under Wyoming's Large Power Contract Service (LPCS) tariff”Company · Oct. 2026 · grade B
- Battery tolling agreement: scope 200 MW“The BESS capacity is contracted under a long-term, battery tolling agreement with CLFP under the same LPCS tariff. Tesla will supply and service the batteries”Company · Oct. 2026 · grade B
- Renewable supply, Cowboy Project Phase 1: value and in-service date 1.2 USD billion“Enbridge expects to invest US$1.2 billion to construct this project, which is expected to enter service by the end of 2027”Company · Oct. 2026 · grade B
- Renewable supply, Cowboy Project Phase 1: term/termination, FINDING: neither the PPA term length, price nor any termination provision is stated in Enbridge's release or in the coverage opened; only the BESS tolling agr“this phase of the project is the first project procured by Meta through CLFP's large-load tariff”Company · Oct. 2026 · grade B
- Temporary Authorization to Discharge: scope“Fortis was the permit holder for the Temporary Authorization to Discharge Boiler Condensate and Fill/Flush Drainage for the CHY1-2 Project (Oct. 2, 2025)”Local government · Oct. 2026 · grade B
- Temporary Authorization to Discharge: termination, revocation“BOPU's Revocation of the Temporary Authorization to Discharge letter of March 27, 2026 was addressed to Fortis, not Goat Systems, and terminated Fortis's Temporary Authorization to Discharge”Local government · Oct. 2026 · grade B
- Water restoration partnership: scope“we are partnering with Laramie County Conservation District to help restore Crow Creek, which serves Laramie County and recharges Wyoming's Ogallala Aquifer”Company · Oct. 2026 · grade B
- Grid resource commitment: scope“Meta will work with Black Hills Energy to add new resources to the grid, including renewables”Company · Oct. 2026 · grade B
- Investment: 800 USD millions“Once completed, the Cheyenne Data Center will represent an investment of more than $800 million and support approximately 100 jobs.”Company · July 2024 · grade B
- development agreement: fees and infrastructure park fees, public safety fees and building permit revenue; developer aids construction of onsite/offsite sewer, water and road infrastructure“The developer will be required to pay park fees, public safety fees, and building permit revenue and will aid in construction of onsite and offsite infrastructure”Local government · Oct. 2023 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Sept. 22, 2022 · Grantor: SARA · Grantee: GOAT SYSTEMS LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Sept. 2022 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Aug. 26, 2022 · Grantor: SARA · Grantee: GOAT SYSTEMS LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Aug. 2022 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Aug. 26, 2022 · Grantor: SCHROTH · Grantee: GOAT SYSTEMS LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Aug. 2022 · grade B
- Mayor Patrick Collins described the $800M Meta campus as nearing completion (AP), no Meta opening announcement followed; opening target remains 2027“An $800 million data center announced last year by Facebook parent company Meta Platforms is nearing completion, Collins said”News report · Oct. 2026 · grade C
- energy supply / PPA: generation supply 365 MW solar + 200 MW / 1,600 MWh battery storage (Cowboy Project, phase 1)“Enbridge and Meta are expanding their clean energy partnership with a solar and storage project in Wyoming, which will supply Meta data centers with 365 MW of solar”News report · May 2026 · grade C
Permits and government (19)
- Industrial Siting Permit (dedicated supply project): permit issued“The Industrial Siting Council has issued an Industrial Siting Permit to Enbridge Inc. to construct and operate the Cowboy Solar Project I & II (Project)”State agency · Oct. 2026 · grade A
- Cheyenne City Council (Governing Body): Memorandum of Understanding with Goat Systems, LLC for the Project Cosmo development“was preceded by a memorandum of understanding (MOU) which was approved by the Governing Body on February 27, 2023”Local government · Oct. 2026 · grade A
- Cheyenne City Council: Development Agreement with Goat Systems, LLC, introduction and referral“Introduction and Referral: October 23, 2023 • Public Service Committee: November 7, 2023 • Final Consideration: November 13, 2023”Local government · Oct. 2026 · grade A
- Wyoming Industrial Siting Council: Contested case hearing on Enbridge's Industrial Siting Permit application for Cowboy Solar Project I & II (Docket DEQ/ISC 23-03)“the Wyoming Industrial Siting Council conducted a public hearing on the Application for Permit. The hearing began at 8 A.M on March 25, 2024”State agency · Oct. 2026 · grade A
- Notice of Significant Noncompliance (pretreatment): SNC notice issued to Goat Systems, LLC; Goat Systems filed a Notice of Appeal on Jul 13, 2026“The notice concerns the release of Cupriavidus gilardii into the City's wastewater treatment processes resulting in pass through and interference violations”Local government · July 2026 · grade A
- Water service: City of Cheyenne Board of Public Utilities (municipal water/sewer); closed-loop cooling design“Fortis was the permit holder for the Temporary Authorization to Discharge Boiler Condensate and Fill/Flush Drainage for the CHY1-2 Project (Oct. 2, 2025)”Local government · Oct. 2026 · grade B
- Industrial wastewater discharge authorization: issued“Fortis was the permit holder for the Temporary Authorization to Discharge Boiler Condensate and Fill/Flush Drainage for the CHY1-2 Project (Oct. 2, 2025)”Local government · Oct. 2026 · grade B
- Industrial wastewater discharge authorization: revoked“BOPU contacted Fortis—not Goat Systems—with a verbal order to cease all discharge from the facility on March 24, 2026”Local government · Oct. 2026 · grade B
- Pretreatment enforcement, Notice of Significant Noncompliance: issued; $10,000 administrative fine assessed; cost-recovery surcharge to follow“The Order section of the Notice assesses an administrative fine of $10,000.00”Local government · Oct. 2026 · grade B
- Cheyenne Board of Public Utilities: Notice of Significant Noncompliance issued to Goat Systems, LLC (Meta Cheyenne Datacenter CHY1-2)“states that BOPU will later issue a surcharge under Cheyenne City Code Section 13.20.640 to recover costs allegedly associated with the presence of the bacteria”Local government · Oct. 2026 · grade B
- industrial wastewater discharge authorization: verbal cease-discharge order Mar 24, 2026; revocation letter Mar 27, 2026 terminating Fortis's Temporary Authorization“BOPU contacted Fortis—not Goat Systems—with a verbal order to cease all discharge from the facility on March 24, 2026.”Court filing · March 2026 · grade B
- Temporary Authorization to Discharge Boiler Condensate and Fill/Flush Drainage (: temporary discharge authorization held by Fortis (per Goat Systems' appeal)“Fortis was the permit holder for the Temporary Authorization to Discharge Boiler Condensate and Fill/Flush Drainage for the CHY1-2 Project (Oct. 2, 2025), not Goat Systems.”Court filing · Oct. 2025 · grade B
- County code: 56021“Meta is proud to work alongside Governor Mark Gordon, the Laramie County, the City of Cheyenne, Wyoming, the Cheyenne LEADS, the Wyoming Business Council”Company · July 2024 · grade B
- Industrial user discharge privileges: permanently terminated“BOPU temporarily suspended Cheyenne's reclaimed water irrigation program, permanently terminated Meta's discharge privileges”News report · Oct. 2026 · grade C
- BOPU publicly named Goat Systems LLC as the industrial user in significant noncompliance, four months after the March 24, 2026 privilege revocation, and adopted a citywide policy prohibiting wastewater discharges from“On July 2, BOPU issued a Notice of Significant Noncompliance to Goat Systems LLC, as well as a second media release titled Public Notice of Industrial User in Significant NonCompliance”News report · Oct. 2026 · grade C
- Cheyenne City Council: Development Agreement with Goat Systems, LLC, final consideration (Project Cosmo approvals)“A data center development on the site, dubbed 'Project Cosmo', was approved by Cheyenne City Council last November”News report · Oct. 2026 · grade C
- Cheyenne Board of Public Utilities: New policy prohibiting wastewater discharges from data centers using closed-loop cooling systems and fill-and-flush systems“adopted a new policy prohibiting wastewater discharges from data centers using closed-loop cooling systems and fill-and-flush systems”News report · Oct. 2026 · grade C
- Site location: High Plains Business Park, Cheyenne, WY“The Cheyenne Board of Public Utilities identified Goat Systems LLC, the corporate entity Meta uses for construction of its sprawling data center campus in the High Plains Business Park”News report · July 2026 · grade C
- data center wastewater discharge policy: new policy prohibiting wastewater discharges from data centers using closed-loop cooling and fill-and-flush systems; Meta's discharge privileges permanently terminated“BOPU temporarily suspended Cheyenne's reclaimed water irrigation program, permanently terminated Meta's discharge privileges and adopted a new policy prohibiting wastewater discharges from data centers”News report · July 2026 · grade C
Legal (2)
- Stage: building (commissioning)“Petitioner appeals the Notice, which was issued by BOPU to Goat Systems on July 2, 2026”Local government · Oct. 2026 · grade B
- Goat Systems appealed the Notice of Significant Noncompliance, paid the $10,000 fine under protest and petitioned for a contested case hearing, arguing Fortis Construction (the discharge-authorization holder) was the pro“Accept this filing as Petitioner's timely written request for reconsideration of the $10,000.00 administrative fine pursuant to Cheyenne City Code Section 13.20.710(C)”Local government · Oct. 2026 · grade B
Site and other (23)
- Name: Meta Cheyenne Data Center (Project Cosmo)“This DA is related to a project, commonly known as Project Cosmo, within the business park”Local government · Oct. 2026 · grade A
- County: Laramie County, WY“The Project will be constructed on private land leases in two phases in Laramie County”State agency · Oct. 2026 · grade A
- County code: Laramie County, WY (56021)“all panels and associated infrastructure will be located in Laramie County”State agency · Oct. 2026 · grade A
- Site: High Plains Business Park, south Cheyenne“The High Plains Business Park final plat was recorded on January 24, 2023”Local government · Oct. 2026 · grade A
- Site acres: 945 acres“The developer, Goat Systems, LLC, proposes an approximate 945-acre data center campus development”Local government · Oct. 2026 · grade A
- Developer: Meta Platforms, Inc. (via Goat Systems LLC during entitlement)“Cheyenne, Wyoming, will be home to our newest Meta data center — our 21st data center in the U.S. and 25th in the world”Company · Oct. 2026 · grade B
- Operator: Meta Platforms, Inc.“Once operational, the Cheyenne Data Center will be optimized for our AI workloads”Company · Oct. 2026 · grade B
- Building sq ft: 715000 sq ft“This 715,000-square-foot campus will be part of our global infrastructure”Company · Oct. 2026 · grade B
- Jobs construction peak: more than 1000 workers“We anticipate that more than 1,000 construction workers will be onsite at the peak of construction”Company · Oct. 2026 · grade B
- Construction stage: shell/commissioning, buildings erected; cooling-system fill-and-flush (pre-commissioning) under way in early 2026; not yet announced operational by Meta“at the discharge point associated with the CHY1-2 site, which at the time of the sampling was under construction by Fortis Construction, Inc.”Local government · Oct. 2026 · grade B
- First announced: July 2, 2024“Cheyenne, Wyoming, will be home to our newest Meta data center”Company · Oct. 2026 · grade B
- Meta partners with Laramie County Conservation District to restore Crow Creek (which recharges the Ogallala Aquifer) under its global goal to restore more water than it consumes in 2030“Meta also has a global goal to restore more water than we consume in 2030, and we are partnering with Laramie County Conservation District to help restore Crow Creek”Company · Oct. 2026 · grade B
- Operator: Meta“Cheyenne, Wyoming, will be home to our newest Meta data center — our 21st data center in the U.S. and 25th in the world.”Company · July 2024 · grade B
- Campus sq ft: 715000 sq ft“This 715,000-square-foot campus will be part of our global infrastructure that helps bring our technologies and services to life.”Company · July 2024 · grade B
- Project code name: Project Cosmo“This DA is related to a project, commonly known as “Project Cosmo,” within the business park.”Local government · Oct. 2023 · grade B
- Site acres: 945 acres“The developer, Goat Systems, LLC, proposes an approximate 945-acre data center campus development.”Local government · Oct. 2023 · grade B
- Announced: Oct. 23, 2023“This DA is related to a project, commonly known as “Project Cosmo,” within the business park.”Local government · Oct. 2023 · grade B
- Facility profile has the first building scheduled to open by 2027; trade reporting (May 2026) puts the final building's operations start in 2029.“Construction on the first building started in early 2024 and the facility is scheduled to open by 2027.”News report · Oct. 2026 · grade C
- Original target date: 2027“2027 (opening targeted 2027 per Baxtel; no COD in Meta's own announcement)”grade C
- Current target date: 2027“2027 (no revised date published)”grade C
- Meta publicly named as the company behind Project Cosmo; through entitlement the project ran under the Goat Systems LLC shell (City approvals Nov 2023; Meta's own announcement followed July 2, 2024)“At the time, Meta was using the shell company Goat Systems LLC to conduct business. The social media firm was named as the company behind the project in May”News report · Oct. 2026 · grade C
- Cupriavidus gilardii chronology per BOPU's released timeline: bacterium first observed in BOPU wastewater sampling Jan 15, 2026; Wyoming Public Health Laboratory identified it Feb 23, 2026; BOPU notified Wyoming DEQ Feb“a total of 801,475 gallons of wastewater was discharged from the Meta facility during January, February and March”News report · Oct. 2026 · grade C
- Project status: under construction / pre-commissioning - building construction began early 2024; still under construction as of Jul 2026; cooling-system fill-and-flush (pre-commissioning) documented Feb-Mar 2026“Meta's new AI data center in Cheyenne, Wyoming is still under construction.”News report · July 2026 · grade C