Data center profile · 28803 NW Livestock Road, Hermiston, Umatilla County, Oregon

Amazon Hermiston campus (Livestock Road)

Amazon Web Services' four-building campus on 117 acres off NW Livestock Road in Hermiston, Oregon, in service, backup generators state-permitted, no MW figure published.

Operating. A data-center directory lists four buildings on the site, built in 2022 and 2023 and all operational, and the state air permit for the facility runs to June 2029. Amazon has published no MW figure, and no utility agreement for the campus is public.
4 buildings
all operational
one of 217,900 sq ft and three of 250,000 sq ft (directory)
117 acres
campus site
directory listing
Not published
campus power in MW
neither the state air permit nor enterprise-zone reports state one
OperatorAmazon Data Services, Inc. (permit holder)
CustomerNone named beyond Amazon Web Services
First building in serviceIn service since 2022
Next deadlineJune 1, 2029: State air permit for the facility expires
Power

Power and the grid

Energized, size not disclosed

Sources on record, size not disclosed

Getting on the grid

Permits

Permits checklist

1 granted · 1 checked, nothing on file

Approvals on record for the campus.

Risks

What could slow it down

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. 2017
    Site Amazon first announces plans for a Hermiston data-center site, on 120 acres next to the local power plant (press) News report · Oct. 2026
  2. 2022
    Construction First building completed on the Livestock Road site (directory) Dataset · Oct. 2026
  3. 2023
    Construction Remaining buildings completed; directory lists all four as operational Dataset · Oct. 2026
  4. June 1, 2029
    Permits State air permit expires State agency · Oct. 2026
The buildings

Specs

217,900 + 3 x 250,000 sq ft
four buildings, built 2022 to 2023 (directory)
PDX80
Amazon's facility name in the state air permit
Who is involved

Owners, partners and builders

Owner
  • Amazon Data Services, Inc.: operator and permit holder
Utility
  • Umatilla Electric Cooperative: serves Hermiston (press)
Government
  • Oregon Department of Environmental Quality: air permit
  • City of Hermiston and Umatilla County: enterprise-zone sponsors
Still unknown

Open questions

Where this comes from

53 records from 11 documents

Drawn from news reports, state agency records, local government records, public and commercial datasets and company statements, each kept with its date and source. The bar shows documents by type.

News report 7State agency 1Local government 1Dataset 1Company 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (11)
  • Size status: no live MW on any basis - no mw it, mw utility or mw campus stated figure exists for this campus in Umatilla Electric Cooperative, Oregon DOE, Umatilla County or Oregon DEQ records found through Oct 20, 2026
    “A total of 105 emergency generators and two (2) fire pumps were permitted at the facility in 2018.”
  • Project identity: Amazon Data Services campus at 28803 NW Livestock Rd, Hermiston OR (hence 'Livestock Campus'); Oregon DEQ air-permit records designate the facility 'AWS Environmental - PDX80'. The Greater Hermiston Ent
    “Amazon Data Services, Inc., AWS Environmental - PDX80”
  • Regional (not campus-instrument) context: Amazon-UEC agreement lets Amazon select the energy supply powering its data center operations in UEC territory while UEC provides utility service
    “The agreement allows Amazon to take on the responsibility of selecting the energy supply that powers its data center operations, including from renewable energy resources.”
  • Campus buildings: 4 buildings: one 217,900 sq ft and three 250,000 sq ft each; site built on 117 acres with 9 acres for dedicated electrical substations
    “Amazon's Hermiston Campus is located at 28803 NW Livestock Rd. The site was built on 117 acres.”
  • Amazon began building in Boardman (Morrow County) around 2011 and expanded into Hermiston (Umatilla County) from around 2017; a 2017-era plan covered a five-building Hermiston data center of ~$2.75B under the state Strat
    “Amazon plans to build a five-building data center near Hermiston”
  • Hermiston is served by the Umatilla Electric Cooperative (UEC), a consumer-owned cooperative - not PacifiCorp or PGE. Per AWS county filings reported by DCD, UEC builds the on-site substations for Amazon's developments i
    “According to the filings, the Umatilla Electric Cooperative will build an on-site substation for the development”
  • Regional context only: in Morrow County filings for a different AWS development, Umatilla Electric Cooperative will build an on-site substation. No fetched source states a substation size, load or MW for the Livestock/PD
    “According to the filings, the Umatilla Electric Cooperative will build an on-site substation for the development”
  • Copia's proposed Charlestown Data Center and Battery Energy Storage System on 106 acres of BLM land in Umatilla County (draft plan filed May 8, 2026) is a separate, non-Amazon project in the same county - not this campus
    “the California-based energy company Copia, submitted an application to site the Charlestown Data Center and Battery Energy Storage System in Umatilla County on 106 acres of BLM land.”
  • Hermiston is Umatilla Electric Cooperative territory and no fetched source names a Hermiston campus in the complaint
    “One AWS campus, the complaint states, has "insufficient power," a second has no power at all”
  • SIGNAL ONLY - off-site generation, never campus MW: Amazon PPA with Avangrid (Feb 2024) for Oregon wind farm output (Leaning Juniper IIA, said to be 98.4MW from 40 turbines). No source ties this PPA capacity to the Lives
    “was said to have a capacity of 98.4MW generated by 40 turbines.”
  • Amazon's November 2025 complaint to the Oregon PUC against PacifiCorp (four campuses left with insufficient or no power, contracting refused for two more) concerns PacifiCorp service territory
    “One AWS campus, the complaint states, has “insufficient power,” a second has no power at all”
Money and contracts (3)
  • PDX138 is tracked separately from PDX80/Livestock
    “This investment officially broke ground in 2023, and received it's first Certificate of Occupancy in July, 2024.”
  • application submitted 10/9/2019, approved 4/13/2020; Annual Improvement Payment no less than $2M/yr rising to $4M/yr once the fourth building is occupied; CY2025 payments in lieu of taxes $2,658,314.07 - is a DIFFERENT A
    “This investment broke ground in 2023, and received it's first Certificate of Occupancy in July, 2024, which is a trigger point for the beginning of the 15 year exemption to begin in 2025.”
  • Under the 2022 Greater Hermiston Enterprise Zone abatement framework, Amazon's two new campuses were expected at full build-out to generate around $5 million in payments in lieu of property taxes and about 120 permanent
    “At full build-out, the two sites will generate around $5 million in payments in lieu of property taxes and generate 120 permanent jobs each.”
Permits and government (12)
  • Amazon Data Services, Inc., AWS Environmental: Standard Air Contaminant Discharge Permit (Synthetic Minor SM-80)
    “Amazon Data Services, Inc., AWS Environmental - PDX80”
  • Emergency generator fleet: 112 emergency generators
    “This permit regulates the operations and emissions from one hundred twelve (112)emergency generators and two (2) fire pump engines”
  • Facility use: Data center housing computer systems and associated components, with diesel-fueled emergency backup generators
    “The permittee operates a data center which houses computer systems and associated”
  • Standard Air Contaminant Discharge Permit (Synthetic Minor SM-80): renewal review report - proposed permit
    “The proposed permit is a renewal of an existing Standard Air Contaminant Discharge”
  • Standard Air Contaminant Discharge Permit: original permit issued
    “Permit (ACDP) that was issued on 01/26/2018 and was scheduled to expire on 1/3/2023”
  • Water Pollution Control Facilities General Permit: issued (as recorded in DEQ air permit review report)
    “PDX80 has been issued a Water Pollution Control Facilities General Permit 2501”
  • Notice of intent to construct approval: generator addition approved
    “Caterpillar 3512 C, rated at 1500 kWe and 2206 hp, NC# 34086, letter of approval issued on 10/14/2022.”
  • Standard Air Contaminant Discharge Permit: compliance inspection - in compliance
    “The facility was inspected on 12/30/2020 and found to be in compliance with the permit”
  • Oregon DEQ permit 30-0054-ST-01 regulates 112 emergency generators and 2 fire pump engines at the PDX80 Livestock campus: 105 generators permitted in 2018 plus 7 more approved since via notices of intent to construct; ra
    “This permit regulates the operations and emissions from one hundred twelve (112) emergency generators and two (2) fire pump engines”
  • Oregon DEQ recently fined an Amazon data center in Hermiston for violating its air quality permit by running an emergency diesel generator about 50 hours beyond the permitted limit (Sightline Institute analysis of DEQ da
    “the Oregon environmental quality department recently fined an Amazon data center in Hermiston for violating its air quality permit by running an emergency diesel generator for 50 hours more than allowed.”
  • Hermiston City Council:
    “the Hermiston City Council at its September 26 meeting, approved Amazon Data Services' application for long-term tax abatement to build the new additional campuses within the Greater Hermiston Enterprise Zone.”
  • Announced: Aug. 2017
    “For Amazon's proposed site near Hermiston, Umatilla County held a public hearing in August 2017.”
Site and other (6)
  • PDX146 had not broken ground in 2025; Both are separate GHEZ campuses from PDX80/Livestock.
    “This investment broke ground in 2024 but had not received a Certificate of Occupancy”
  • Project identity: Amazon Data Services, Inc. campus designated 'AWS Environmental - PDX80' at 28803 NW Livestock Rd, Hermiston, OR 97838 (queue name: Amazon Hermiston Livestock Campus)
    “Amazon Data Services, Inc. (ADS), PDX80 campus, located at 28803 NW Livestock”
  • County code: 41059
    “Amazon Data Services, Inc. (ADS), PDX80 campus, located at 28803 NW Livestock”
  • Generator nameplate ceiling: 266475 kWe
    “One hundred four (104) diesel-fired emergency generator engine sets, CAT 3516C HD, rated at 2500 kWe and 3,634 hp, each (Type B)”
  • Project status: operating
    “The campus consists of four buildings: one measuring 217,900 sq ft, and three measuring 250,000 sq ft each.”
  • Project status: operating four buildings first built 2022
    “The campus consists of four buildings: one measuring 217,900 sq ft, and three measuring 250,000 sq ft each.”