Power
Power and the grid
Sources on record, size not disclosed
- Entergy Mississippi grid Utility committedEntergy agreed to provide power and meet long-term needs; no MW disclosed News report · Nov. 2025
Getting on the grid
- No state utility commission docket names the campus; Mississippi's Amazon projects run through state legislation rather than normal commission review. News report · Oct. 2026
Permits
Permits checklist
2 granted · 1 checked, nothing on file
County approvals on record.
- ✓Fee-in-lieu tax agreement GrantedWarren County Board of Supervisors · April 2026: approved before the Apr. 6, 2026 meeting; $2.5B and 100-job minimums News report · April 2026
- ✓Development permit for clearing GrantedWarren County · April 6, 2026: issued to a subcontractor; no building permits requested yet News report · April 2026
- –Checked, nothing on file: State environmental permits
Risks
What could slow it down
- WatchEarly stageAs of April 2026 no final location or general contractor had been named, so no building permits had been sought. see Permits
- WatchTraffic and neighborhood concernsResidents and parents raised traffic safety and disruption at the Sept. 2026 update (press). News report · Sept. 2026
Money
Money on record
- State aid: incentive law for Amazon's Madison County campuses extended to Vicksburg (Mississippi Major Economic Impact Authority) News report · Nov. 2025
Timeline
What happened, and what is due
SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
- Nov. 20, 2025Site AWS announces a $3B campus in Vicksburg; Entergy Mississippi agrees to provide power News report · Nov. 2025
- April 6, 2026Permits Residents question supervisors; the board says one clearing permit is issued and no building permits requested News report · April 2026
- April 6, 2026Money Board president says the fee-in-lieu deal guarantees at least $2.5B and 100 direct jobs News report · April 2026
- Sept. 17, 2026Construction AWS community update lays out a construction roadmap; residents raise traffic concerns News report · Sept. 2026
The buildings
Specs
- No rezoning: needed in unincorporated Warren County; a county development permit covers clearing, dirt work or building News report · April 2026
Who is involved
Owners, partners and builders
Owners
- Amazon Web Services: owner and operator
Decision-makers
- Warren County Board of Supervisors
- Mississippi Major Economic Impact Authority: state incentives
Power partners
- Entergy Mississippi: serving utility
Still unknown
Open questions
- MW and exact site.
- General contractor and building permits.
- Opening date.
Where this comes from
22 records from 7 documents
Drawn from news reports and company statements, each kept with its date and source. The bar shows documents by type.
News report 6Company 1
Evidence
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (2)
- Tenant is AWS itself (owner-occupied; Serving utility is Entergy Mississippi, which has agreed to provide power; No MW or power capacity has been disclosed for this campus in any source checked.“Exact details surrounding the size, power capacity, and location of the campus are sparse, but construction is slated to start this year, and Entergy Mississippi has agreed to provide power.”News report · Nov. 2025 · grade C
- Entergy Mississippi is the named supplier for Vicksburg: it has agreed to provide power, and its commitment to meeting long-term power requirements was a stated factor in AWS's decision. No MW, no PSC docket and no MDEQ“construction is slated to start this year, and Entergy Mississippi has agreed to provide power.”News report · Nov. 2025 · grade C
Money and contracts (5)
- Fee in lieu of taxes agreement: minimum financial investment 2500000000 USD“WARREN COUNTY BOARD OF SUPERVISORS APPROVED A FEE IN LIEU AGREEMENT ALLOWED UNDER STATE LAW, WHICH GUARANTEES A MINIMUM FINANCIAL INVESTMENT OF $2.5B”News report · April 2026 · grade C
- Fee in lieu of taxes agreement: minimum direct jobs 100 direct jobs once operational over the course of 5 years“A MINIMUM OF 100 DIRECT JOBS ONCE OPERATIONAL OVER COURSE OF 5 YEARS. AMAZON PUBLICLY ANNOUNCED AN ANTICIPATED 200 DIRECT JOBS”News report · April 2026 · grade C
- County code: 28149“In November 2025, Amazon Web Services announced a $3 billion data center investment in Warren County, Mississippi.”News report · Nov. 2025 · grade C
- state incentive / power framework: Mississippi Major Economic Impact Authority legislation approved for the Madison County complexes made available to the Vicksburg project; Warren County also contributing; Entergy Missi“Previous Mississippi Major Economic Impact Authority legislation approved for Amazon’s Madison County data center complexes will be made available for the Vicksburg project.”News report · Nov. 2025 · grade C
- AWS announced a $3 billion investment in the Vicksburg (Warren County) campus on Nov 20, 2025, described as the largest single capital investment in Warren County history, with at least 200 direct jobs. Figure as stated“Amazon's $3 billion expansion into Vicksburg proves once again that Mississippi delivers what tech leaders need”News report · Nov. 2025 · grade C
Permits and government (3)
- utility large-load plan / contract filing: Entergy Mississippi executed a large : Large customer supply and service agreement executed February 2025; Vicksburg Advanced Power Station announced October 2025, construction“In October 2025, Entergy Mississippi announced plans to construct, own, and operate the Vicksburg Advanced Power Station, a 754 MW combined cycle combustion turbine facility, to be located in the City of Vicksburg, Warren County, Mississippi”Company · Oct. 2025 · grade A
- As of Apr 6, 2026 one permit had been issued to a subcontractor to clear the property, but no building permits had been requested because a final location and general contractor had not been named“ONE PERMIT HAS BEEN ISSUED TO A SUB-CONTRACTOR TO CLEAR PROPERTY BUT NO BUILDING PERMITS HAVE BEEN REQUESTED”News report · April 2026 · grade C
- Warren County Board of Supervisors:“WARREN COUNTY BOARD OF SUPERVISORS APPROVED A FEE IN LIEU AGREEMENT ALLOWED UNDER STATE LAW, WHICH GUARANTEES A MINIMUM FINANCIAL INVESTMENT OF $2.5B”News report · April 2026 · grade C
Legal (1)
- No lawsuit, moratorium, denial, petition or organised opposition to the Vicksburg campus was found in this pass. Community-update coverage records resident questions on traffic safety and neighbourhood disruption, addres“With a project of this scale, residents and parents raised predictable concerns about neighborhood disruption and traffic safety.”News report · Sept. 2026 · grade C
Site and other (1)
- Project status: building - site preparation“Now, following a community update Wednesday, Sept. 17, 2026, AWS has released a detailed physical roadmap and construction timeline to bring that vision to life.”News report · Sept. 2026 · grade C