Data center profile · North of E. 76th St. N and east of N. Yale Ave., near Cherokee Industrial Park west of Owasso, unincorporated Tulsa County, Oklahoma

Project Clydesdale (Google, Tulsa County)

Beale Infrastructure's 506-acre data-center campus near Owasso in unincorporated Tulsa County, Oklahoma, under construction since Oct. 2025 and revealed in Aug. 2026 as a Google project

Approved; groundbreaking held Oct. 2025. Tulsa County approved the project plan and tax incentive district unanimously in Sept. 2025, and Beale broke ground on Oct. 30, 2025. Google confirmed in Aug. 2026 that it is the company behind the campus; no MW figure has been disclosed.
506 acres
campus, about 399 acres of it in the tax incentive districts
press; county plan
$1B
planned investment (Beale)
county plan sets at least $700M per phase; not to be summed
Up to 4
phases of about 200,000 sq ft each
at least one phase plus three possible (press, from the county plan)
$1.5M
initial yearly payment in lieu of taxes for Data Center 1
rising 1% a year
OperatorGoogle (operator); developed by Beale Infrastructure through Quartz Mountain Properties LLC
CustomerGoogle
First building in serviceOur estimate: 2029 or later (no dated power path yet); company says 2030.
Next stepNo completion date published; Beale describes a five-year build-out of the initial phase
Power

Power and the grid

Sources on record, size not disclosed

Getting on the grid

Permits

Permits checklist

1 granted · 1 checked, nothing on file

County approvals on record. A planning staff recommendation is not a decision.

Risks

What could slow it down

Money

Money on record

$1B
planned investment (Beale, Oct. 2025)
headline figure Company · Oct. 2025
$700M+
minimum private investment per phase in the county plan
a floor per phase, not a total Local government · Sept. 2025
$1.5M
initial yearly payment in lieu of taxes, Data Center 1
escalates 1% a year Local government · Sept. 2025
$500,000
yearly community betterment payment
per the county plan Local government · Sept. 2025
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. May 2025
    Permits Rezoning application first submitted to the county (press) News report · Sept. 2025
  2. July 2025
    Site A 'Stop the AI Data Center' campaign lobbies to postpone the July votes News report · July 2025
  3. Sept. 3, 2025
    Permits Planning staff recommend approval of the tax incentive district plan Local government · Sept. 2025
  4. Sept. 29, 2025
    Permits County commissioners unanimously adopt the project plan and incentive district Local government · Sept. 2025
  5. Oct. 30, 2025
    Construction Beale breaks ground on the campus News report · Aug. 2026
  6. Dec. 1, 2025
    Site Neighbors raise blasting concerns as preblast inspections begin (press) News report · Dec. 2025
  7. Aug. 19, 2026
    Site Google confirms it is the company behind the campus News report · Aug. 2026
Construction activity

Building activity by quarter

Since April 2026: 8 FAA filings (April 2026 to July 2026): tallest permanent structure 41 ft (filed May 2026) and tallest crane 286 ft (April 2026).

FAA filings
’26
Dot size: records in the quarter, largest = 7. Two-digit years mark each first quarter.
The buildings

Specs

1.5 miles
of new water lines the project funds for Washington County Rural Water District No. 3
100 jobs
up to, permanent technical roles (developer claim)
Who is involved

Owners, partners and builders

Owners
  • Google: operator
  • Beale Infrastructure: developer
  • Quartz Mountain Properties LLC: developing entity
  • Bird Creek Ranch Limited Partnership: landowner at approval
Decision-makers
  • Tulsa County Board of County Commissioners
  • Tulsa Metropolitan Area Planning Commission
Power partners
  • Public Service Company of Oklahoma (PSO)
  • Washington County Rural Water District No. 3: water lines
Opponents
  • Stop the AI Data Center campaign (Tulsa and Owasso)
  • Neighbors near the blasting area
Still unknown

Open questions

Where this comes from

51 records from 13 documents

Drawn from news reports, local government records, company statements and state agency records, each kept with its date and source. The bar shows documents by type.

News report 8Local government 2Company 2State agency 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (3)
  • Utility: Public Service Company of Oklahoma (PSO); Beale funds a new onsite substation
    “Powered by Public Service Co. of Oklahoma (PSO), the Tulsa County project includes construction of a new onsite substation funded by Beale.”
  • Power is PSO, grid-sourced; the project funds a new on-site substation and PSO transmission/distribution system upgrades. No MW load figure is stated in the plan, the Beale announcement or the Google announcement account
    “The campus will be powered by Public Service Company of Oklahoma, with Beale Infrastructure funding construction of a new on-site substation.”
  • Utility: Public Service Company of Oklahoma (PSO); Beale Infrastructure is funding construction of a new on-site substation, and the project includes PSO transmission/distribution upgrades; The queue names Beale as devel
    “The campus will be powered by Public Service Company of Oklahoma, with Beale Infrastructure funding construction of a new on-site substation.”
Money and contracts (6)
  • tax incentive district: pilot per data center 1500000 USD per year
    “The initial annual PILOT payment for Data Center 1 will total One Million, Five Hundred Thousand and No/100 Dollars ($1,500,000.00).”
  • infrastructure commitment: water line funding
    “Its Project Clydesdale is funding and installing 1.5 mi. of new water lines and infrastructure upgrades for Washington County Rural Water District #3”
  • tax incentive district: community betterment 500000 USD per year
    “The initial annual PILOT payment for Data Center 1 will total One Million, Five Hundred Thousand and No/100 Dollars ($1,500,000.00).”
  • Tenant/operator identity: Google. The campus was developed by Beale Infrastructure (with Quartz Mountain Properties on land) and reported for months without a named tenant; Google and Beale jointly announced construction
    “The Tulsa County campus will be powered by Public Service Company of Oklahoma. The project includes a new on-site substation funded by Beale”
  • Neighbors within 600 feet of blasting locations were offered free preblast inspections by Sauls Seismic (hired for Beale); some homes just outside the radius on 82nd Street North received no notice, residents mobilized i
    “According to the letter sent to those neighbors, Sauls Seismic was hired to conduct “preblast inspections” on nearby structures, including taking video and pictures inside and outside”
  • Developer: Beale Infrastructure (developer); Quartz Mountain Properties LLC (developing entity); landowner at approval: Bird Creek Ranch Limited Partnership; end user: Google (confirmed Aug 2026)
    “Beale Infrastructure is the developer behind a $1 billion data center known as Project Clydesdale.”
Permits and government (17)
  • OE/AAA case for a 250-ft mobile crane filed as 'CYL1A Data Center' at (36.26430,: Determined - No Hazard
    “ASN 2026-ASW-11179-OE: CYL1A Data Center, Mobile Crane, 250 ft AGL, 887 ft AMSL, 36.26430,-95.90889, Determined - No Hazard, submitted 2026-07-30”
    FAA · July 2026 · grade B
  • OE/AAA case for a 90-ft temporary mobile crane at (36.26781,-95.90675), at the c: Determined - No Hazard
    “ASN 2026-ASW-9230-OE: Temporary Mobile crane, Mobile Crane, 90 ft AGL, 714 ft AMSL, 36.26781,-95.90675, Determined - No Hazard, submitted 2026-06-09”
    FAA · June 2026 · grade B
  • OE/AAA case for a 72-ft pole filed as 'Substation Utility Equipment 4' at the ca: Determined - No Hazard
    “ASN 2026-ASW-9240-OE: Substation Utility Equipment 4, Utility Pole, 72 ft AGL, 695 ft AMSL, 36.26800,-95.90700, Determined - No Hazard, submitted 2026-06-09”
    FAA · June 2026 · grade B
  • OE/AAA case for a 72-ft pole filed as 'Substation Utility Equipment 3' at the ca: Determined - No Hazard
    “ASN 2026-ASW-9241-OE: Substation Utility Equipment 3, Utility Pole, 72 ft AGL, 695 ft AMSL, 36.26810,-95.90700, Determined - No Hazard, submitted 2026-06-09”
    FAA · June 2026 · grade B
  • OE/AAA case for a 72-ft pole filed as 'Substation Utility Equipment 2' at the ca: Determined - No Hazard
    “ASN 2026-ASW-9242-OE: Substation Utility Equipment 2, Utility Pole, 72 ft AGL, 696 ft AMSL, 36.26800,-95.90720, Determined - No Hazard, submitted 2026-06-09”
    FAA · June 2026 · grade B
  • OE/AAA case for a 72-ft pole filed as 'Substation Utility Equipment' at the camp: Determined - No Hazard
    “ASN 2026-ASW-9243-OE: Substation Utility Equipment, Utility Pole, 72 ft AGL, 696 ft AMSL, 36.26810,-95.90720, Determined - No Hazard, submitted 2026-06-09”
    FAA · June 2026 · grade B
  • Tallest structure filed with the FAA (ft): 41 ft
    “ASN 2026-ASW-6396-OE: Data Center 2, Building, 41 ft AGL, 703 ft AMSL, 36.27093,-95.91043, Determined - No Hazard, submitted 2026-05-12”
    FAA · May 2026 · grade B
  • OE/AAA case for a 41-ft structure filed as 'Data Center 2' at (36.27093,-95.9104: Determined - No Hazard
    “ASN 2026-ASW-6396-OE: Data Center 2, Building, 41 ft AGL, 703 ft AMSL, 36.27093,-95.91043, Determined - No Hazard, submitted 2026-05-12”
    FAA · May 2026 · grade B
  • OE/AAA case for a 286-ft mobile crane filed as 'Project Clydesdale: Determined - No Hazard
    “ASN 2026-ASW-1451-OE: Project Clydesdale - Mobile Crane, Mobile Crane, 286 ft AGL, 954 ft AMSL, 36.26423,-95.90518, Determined - No Hazard, submitted 2026-04-09”
  • FAA OE/AAA records a 'Project Clydesdale' mobile crane (ASN 2026-ASW-1451-OE, submitted April 9, 2026) and a 7-case in-block construction cluster at the documented campus block - a 'Data Center 2' building (41 ft), a 'CYL1A
    “ASN 2026-ASW-1451-OE: Project Clydesdale - Mobile Crane, Mobile Crane, 286 ft AGL, 954 ft AMSL, 36.26423,-95.90518, Determined - No Hazard, submitted 2026-04-09”
  • County code: 40143
    “After a second public hearing, the Tulsa County Board of County Commissioners voted unanimously Sept. 29 to adopt the Project Clydesdale economic development project plan and its accompanying tax-incentive district”
  • Tulsa County Board of County Commissioners:
    “After a second public hearing, the Tulsa County Board of County Commissioners voted unanimously Sept. 29 to adopt the Project Clydesdale economic development project plan and its accompanying tax-incentive district”
  • Tulsa Metropolitan Area Planning Commission:
    “The initial annual PILOT payment for Data Center 1 will total One Million, Five Hundred Thousand and No/100 Dollars ($1,500,000.00).”
  • County approval for the 506-acre campus in unincorporated Tulsa County near Cher: Project Clydesdale Economic Development Project Plan and associated tax incentives APPROVED (final approval, Sep 30, 2025)
    “Project Clydesdale received final approval from the Tulsa County Board of Commissioners on September 30, 2025”
  • Project identity: Beale Infrastructure 'Project Clydesdale' - 506-acre data center campus in UNINCORPORATED Tulsa County near Cherokee Industrial Park, just west of Owasso (north of E. 76th St N, east of N. Yale Ave, sou
    “The data center will be located north of East 76th Street North, east of North Yale Avenue, south of East 86th Street North, and west of North Sheridan Road.”
  • Tulsa County Board of Commissioners voted in September 2025 to approve and adopt the Project Clydesdale Economic Development Project Plan and associated tax incentives; the rezoning application had first been submitted i
    “On Monday, the Board voted to approve and adopt ‘The Project Clydesdale Economic Development Project Plan’ and associated tax incentives.”
  • Organised 'Stop the AI Data Center' Tulsa/Owasso campaign lobbied to postpone the July 2025 votes; hearing concerns covered electricity rates, water, environment and labour; post-groundbreaking neighbour complaints about
    “Tulsa residents are outraged and with good reason. Another large data center has been planned for 506 acres between Tulsa/Owasso area”
Site and other (5)
  • Beale claims up to 100 permanent high-paying technical roles plus thousands of local construction jobs during the five-year build-out of the initial phase - developer claims, not verified
    “creation of up to 100 permanent high-paying technical roles, in addition to thousands of local construction jobs during the five-year build-out of the initial phase”
  • Project status: UNDER CONSTRUCTION - ground broken Oct 30, 2025; Google confirmed as the end user on Aug 19, 2026
    “Google confirmed this week it is the firm behind the massive data center campus being built near Owasso in Tulsa County.”
  • Project status: under construction - ground broken Oct 30, 2025; Google confirmed as operator Aug 2026; initial phase build-out described as five years
    “Google and Beale Infrastructure announced Wednesday that construction is underway on a 506-acre data center campus in unincorporated Tulsa County near Cherokee Industrial Park.”
  • Project Clydesdale will fund and install 1.5 miles of new water lines and infrastructure upgrades for Washington County Rural Water District No. 3, the rural water district serving the site area - a utility-infrastructur
    “Project Clydesdale, the name used for the Tulsa County project, will fund and install 1.5 miles of new water lines and infrastructure upgrades for Washington County Rural Water District No. 3.”
  • Phase building size: 200000 sq ft
    “According to the development project plan, it will consist of at least one phase with three possible additional phases, with each phase covering approximately 200,000 sq ft”