Data center profile · 216 Greenfield Road, Lancaster, Lancaster County, Pennsylvania

CoreWeave Lancaster Greenfield site

CoreWeave data center in a former printing plant in Lancaster, Pennsylvania: 300 MW stated (about 100 MW of IT); state-approved diesel generators are backup only.

Under construction. Turner and Wohlsen are building Phase 1 inside the existing building; the state approved its generator permit Dec. 29, 2025. A July 14, 2026 zoning amendment keeps the project permitted; Phase 2 still needs a land-development approval, not on record.
300 MW
campus power, stated
utility-side figure; about 100 MW of IT is also stated
$6B
investment commitment
CoreWeave equipment commitment, stated
$4B
Blue Owl-led joint venture funding
closed Aug. 25, 2025 (press)
78 acres
site, with 1.1M sq ft of existing building
former LSC Communications printing plant; Phase 1 is 450,000 sq ft
OperatorCoreWeave (tenant and operator); Chirisa Technology Parks (developer)
CustomerCoreWeave
Planned IT capacity240 MW at full build-out (our estimate from the company's 0.3 GW campus power figure)
First building in serviceOur estimate: 2029 or later (no dated power path yet); company says 2027.
Next deadlineOct. 26, 2026: Public comments due on a state air approval for Phase 2 generators
Power

Power and the grid

300 MW contracted

PPL Electric Utilities grid (PJM)Agreement in place
300 MW
stated campus figure; PPL requires a signed large-load agreement and the developer is paying for a new substation; no MW filing found Local government · Oct. 2026
Contracted

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. July 15, 2025
    Campus announced
    CoreWeave announces the Lancaster campus; the developer pays to replace and upgrade the site substation. Local government · Oct. 2026
  2. Aug. 25, 2025
    Funding closes
    A joint venture of Blue Owl funds, Chirisa and Machine Investment Group closes $4B of funding, with about $200M for grid improvements. News report · Oct. 2026

Backup generators on file

Emergency units only; they are not a power supply for the campus.

Permits

Permits checklist

2 pending · 5 granted

The city zones the site; state environmental regulators permit the generators.

Risks

What could slow it down

Money

Money on record

$6B
CoreWeave investment commitment
$4B
joint venture funding
Blue Owl funds with Chirisa and Machine Investment Group (press) Company · Aug. 2025
$10M
community payments to the city
phased per building, under the Nov. 2025 agreement Local government · Oct. 2026
$11.88M
2025 assessed value
before the build-out Local government · Oct. 2026
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Feb. 2025
    Site Developers buy the former LSC printing plants; the zoning officer allows data centers without a hearing Local government · Oct. 2026
  2. July 15, 2025
    Site CoreWeave announces the Lancaster campus; Turner and Wohlsen are named builders Company · Oct. 2026
  3. Aug. 25, 2025
    Money $4B Blue Owl-led funding closes Company · Aug. 2025
  4. Oct. 1, 2025
    Permits Planning Commission holds a hearing on whether the zoning determination was an error; no outcome reported News report · Oct. 2026
  5. Nov. 24, 2025
    Money Community benefits agreement signed with the city Local government · Oct. 2026
  6. Dec. 29, 2025
    Permits State issues the air approval for 176 backup generators State agency · Oct. 2026
  7. July 14, 2026
    Permits City Council adopts a data-center zoning amendment and confirms the two existing projects stay permitted News report · Oct. 2026
  8. Sept. 26, 2026
    Permits State opens comment on a Phase 2 air approval for 84 generators News report · Oct. 2026
  9. Oct. 26, 2026
    Permits Comments due on the Phase 2 air approval News report · Oct. 2026
  10. 2027
    Construction First operations targeted News report · Oct. 2026
Construction activity

Building activity by quarter

Since July 2016: 6 building permits (5 issued or finished, 1 pending or open); the largest lists a $15M job value; 1 FAA filing (April 2026): a 530 ft crane. Job values are not added up: trade permits often repeat the whole project's value. The chart starts in the third quarter of 2020; 1 earlier record is not drawn.

Building permits
FAA filings
’21
’22
’23
’24
’25
’26
Dot size: records in the quarter, largest = 2. Two-digit years mark each first quarter.
The buildings

Specs

Phase 1 and 2
Phase 1: 450,000 sq ft inside the existing footprint; Phase 2 extends beyond it
100% clean power
required by the community agreement, with a fund option for shortfalls
Who is involved

Owners, partners and builders

Developers
  • Chirisa Technology Parks: developer
  • Machine Investment Group: co-developer
  • Greenfield Road Owner, LLC: site owner and air-permit holder
Customer and money
  • CoreWeave: tenant, operator and investor
  • Blue Owl Capital funds: joint venture funding
Decision-makers
  • City of Lancaster: Zoning Officer, Planning Commission, City Council
  • PA Department of Environmental Protection: air approvals
Builders and power
  • Turner Construction and Wohlsen Construction joint venture
  • PPL Electric Utilities: serving utility
Builders on site
  • Vollers Excavating & Construction: 1 building permit
Still unknown

Open questions

Where this comes from

146 records from 20 documents

Drawn from news reports, company statements, local government records, state agency records, public and commercial datasets and securities filings, each kept with its date and source. The bar shows documents by type.

News report 7Company 7Local government 2State agency 2Dataset 1SEC filing 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (14)
  • On-site generation: 572 MW
    “As part of the project, 176 diesel fired emergency generators will be installed to support operations at the facility”
  • On-site generation: 234 MW
    “During phase one, 72 – 3,250 kW Rolls Royce model 4P9.1-2700 generators will be installed”
  • On-site generation: 338 MW
    “During phase two, 104 – 3,250 kW Rolls Royce model 4P9.1-2700 generators will be installed”
  • About $200 million intended for local power grid infrastructure improvements in partnership with PPL Electric Utilities, per the JV announcement. Grid investment dollars - signal only, not campus MW.
    “The parties also intend to fund approximately $200 million for local power grid infrastructure improvements in partnership with PPL Electric Utilities.”
  • Stated campus size: 100 MW
    “The initial 100 megawatt (MW) data center, with potential to expand to 300 MW, represents one of the first large-scale data centers of its kind in the region”
  • Expansion potential to 300 MW stated by CoreWeave (blog and announcement)
    “With room to grow up to 300 MW, our cloud facility in Lancaster will be one of the largest AI data centers in the region.”
  • IT capacity: 100 MW
    “The initial 100 megawatt (MW) data center, with potential to expand to 300 MW”
  • Stated campus size: 300 MW
    “With room to grow up to 300 MW, our cloud facility in Lancaster will be one of the largest AI data centers in the region”
  • Utility service: not stated
    “PPL Electric has signed agreements with every large load customer or data center that requests to connect to our grid”
  • Power plan: grid
    “Under Pennsylvania law, the PA Public Utility Commission (PUC) determines the rates for PPL Electric (PPL) utility customers”
  • Utility: PPL Electric Utilities
    “Chirisa Technology Parks is paying to replace and upgrade the existing substation at 216 Greenfield Road to support the increased power needed”
  • Grid operator: PJM Interconnection
    “the PJM Interconnection, which is the wholesale supplier of electricity to 13 states including Pennsylvania”
  • Cooling: Air cooling with closed-loop water system; municipal water use capped at 20,000 gallons per day under the CBA
    “Water use is capped at 20,000 gallons per day per campus, significantly less than the use for typical manufacturing”
  • Sustained resident opposition at City Planning Commission and Council meetings through 2025-2026 (noise, water, grid impacts); residents filled the Aug 2025 commission meeting and spoke for over an hour against the facil
    “residents filled the meeting room and spoke at length against the proposed facilities during public comment”
Money and contracts (43)
  • tenant lease: termination
    “In August 2025, the Company entered into additional lease agreements, primarily for data centers and storage facilities, that have not yet commenced”
  • CoreWeave's Q2 2025 10-Q reports $34.0B of executed-but-uncommenced lease payments at Jun 30, 2025 (commencing 2025-2028) and, as a subsequent event, $11.9B more from leases entered in August 2025 (commencing 2025-2027,
    “In August 2025, the Company entered into additional lease agreements, primarily for data centers and storage facilities, that have not yet commenced”
  • joint venture funding: funding for Lancaster CoreWeave developments 4000000000 USD
    “today closed on a joint venture partnership to include $4 billion of funding for the previously announced CoreWeave developments in Lancaster, Pennsylvania.”
  • lease: tenant lease of Lancaster site
    “CoreWeave has invested in the campus and will lease the site as part of its commitment to building future-ready AI infrastructure hubs in the regions that need them most”
  • Announced investment: 6000000000 USD
    “That’s why CoreWeave is committing an initial $6 billion to equip a new, state-of-the-art data center outside of Philadelphia in Lancaster, Pennsylvania, purpose-built to power the most cutting-edge AI workloads.”
  • tenant lease: capacity 100 MW
    “The initial 100 megawatt (MW) data center, with potential to expand to 300 MW, represents one of the first large-scale data centers of its kind in the region and will support US global competitiveness in AI.”
  • tenant lease: contract value 6000000000 USD commitment
    “CoreWeave (NASDAQ:CRWV), the AI Hyperscaler™, today announced its intent to commit up to $6 billion to equip a new, state-of-the-art data center in Lancaster, Pennsylvania, purpose-built to power the most cutting-edge AI use cases.”
  • tenant lease: scope
    “CoreWeave will be the tenant of the site, co-developed by Chirisa Technology Parks and Machine Investment Group.”
  • community benefits agreement: community benefits; city sustainability funds
    “The CBA was negotiated by the Sorace Administration and Chirisa Technology Parks.”
  • City of Lancaster states it offered no development incentives to the project; separately, Chirisa is paying to replace and upgrade the existing substation at 216 Greenfield Road
    “No. The City of Lancaster has not offered any development incentives (tax breaks, discounted fees, etc.) to the project.”
  • Tenants: CoreWeave, Inc.
    “CoreWeave will be the tenant of the site, co-developed by Chirisa Technology Parks and Machine Investment Group”
  • Tenant status: committed, tenant announced Jul 15, 2025; lease in place; construction underway
    “announced its intent to commit more than $6 billion to equip a new, state-of-the-art data center in Lancaster, Pennsylvania”
  • Investment commitment: 6000000000 USD
    “CoreWeave is committing an initial $6 billion to equip a new, state-of-the-art data center outside of Philadelphia in Lancaster, Pennsylvania”
  • Assessed value 2025: 11880000 USD
    “216 Greenfield Road – $11,880,000”
  • community benefits: scope
    “The City of Lancaster and Chirisa Technology Parks, the developer of the data centers at 216 Greenfield Road and 1375 Harrisburg Pike, negotiated a Community Benefits Agreement”
  • community benefits: financial contribution 10000000 USD
    “The owners will contribute $10 million each to two funds”
  • community benefits: financial contribution 10000000 USD
    “Sustainable Development and Clean Energy Fund, managed by the City of Lancaster, whose purpose is to advance environmental sustainability in the City of Lancaster”
  • community benefits: payment schedule
    “Payments in increments of 2.5 million dollars will be made into each fund at the time of construction financing and on a date within 30 days of beginning data center operations”
  • community benefits: payment schedule 250000 USD
    “Upon approval of the CBA, the Owners will make a partial payment of the first contribution in the amount of $250,000 to fund the creation of a strategic plan”
  • community benefits: condition 20000 gallons/day
    “Water use is capped at 20,000 gallons per day per campus”
  • community benefits: condition
    “All data center buildings will use 100% clean-energy electricity”
  • community benefits: condition
    “Owners may enter into long-term energy contracts that fall below 100%, only if they make significant contributions into the City's Sustainable Development and Clean Energy Fund”
  • community benefits: condition
    “Operations cannot exceed existing ambient noise levels at nearby homes and parks”
  • community benefits: condition
    “Generator testing occurs only during daytime hours, never on Sundays or federal holidays”
  • community benefits: default and remedies
    “After notice and an opportunity to cure (30-60 days), the City may pursue injunctions or orders requiring compliance with a commitment or other relief, including discontinuance of operations”
  • community benefits: assignment
    “When a property is sold, the new owner must assume all obligations under the agreement”
  • community benefits: payment security
    “the City can: Seek payment through the courts; or Draw money directly from the Letter of Credit or other financial security”
  • community benefits: condition 25000 USD per incident threshold
    “Owners must prepare emergency response plans, provide ongoing training for first responders at no cost and reimburse the City for emergency response costs above $25,000 per incident”
  • community benefits: termination
    “negotiated a Community Benefits Agreement to create a legally enforceable way to protect nearby neighborhoods, safeguard the environment, and provide meaningful community benefits”
  • utility agreement: scope
    “PPL Electric has signed agreements with every large load customer or data center that requests to connect to our grid”
  • utility agreement: condition
    “The agreement requires data center customers to pay a set amount based on their peak usage, even if they use less electricity”
  • utility agreement: scope
    “Chirisa Technology Parks is paying to replace and upgrade the existing substation at 216 Greenfield Road to support the increased power needed”
  • construction contract: scope
    “The data center will be constructed by a joint venture of Turner Construction Company and Wohlsen Construction”
  • tax treatment: scope
    “No. The City of Lancaster has not offered any development incentives (tax breaks, discounted fees, etc.) to the project”
  • Noise: Chirisa has conducted acoustic studies of the facilities' noise impact; the City is independently evaluating the findings. In LNP reporting (via U-M COHSE republication), the City had not requested a copy of the s
    “Chirisa has conducted acoustic sound studies of the potential noise impact of the proposed facilities. The City of Lancaster is independently evaluating their study findings”
  • Tenant status: announced
    “today announced its intent to commit more than $6 billion to equip a new, state-of-the-art data center in Lancaster, Pennsylvania, purpose-built to power the most cutting-edge AI use cases.”
  • Tenants: CoreWeave, Inc.
    “The initial 100 megawatt (MW) data center, with potential to expand to 300 MW, represents one of the first large-scale data centers of its kind in the region”
  • phase delivery: delivery
    “co-developers Chirisa Technology Parks and Machine Investment Group plan to have a 450,000 square-foot data center complete in summer 2027”
  • Site area acres: 78 acres
    “216 Greenfield Road, which totaled 78 acres across two contiguous parcels and 1.1 million square feet of industrial and manufacturing building spaces”
  • Existing building area sq ft: 1100000 sq ft
    “216 Greenfield Road, which totaled 78 acres across two contiguous parcels and 1.1 million square feet of industrial and manufacturing building spaces”
  • tenant lease: scope
    “CoreWeave has invested in the campus and will lease the site”
  • joint venture: scope 4000000000 USD
    “Funds managed by Blue Owl Capital, affiliates of Chirisa Technology Parks (CTP), and Machine Investment Group (MIG) this week closed on a joint venture partnership to include $4 billion of funding”
  • joint venture: scope 200000000 USD
    “the parties also intend to fund approximately $200 million for local power grid infrastructure improvements in partnership with PPL Electric Utilities”
Permits and government (31)
  • air quality plan approval: issued
    “This plan approval is for the installation of a data center and managed hosting service facility in the former LSC Communication East facility located at 216 Greenfield Road”
  • air quality plan approval: condition
    “If the construction, modification or installation is not commenced within 18 months of the issuance of this plan approval a new plan approval application shall be submitted”
  • building permit: city review described; no land development review required for Phase 1
    “Phase 1 of 216 Greenfield Road is an adaptive reuse of an existing building.”
  • Zoning: Suburban Manufacturing (SM), City Code Chapter 300; data center use deemed consistent by Feb 2025 zoning determination
    “A data center use has been deemed consistent with this zoning district”
  • air quality plan approval: municipal notification
    “The City of Lancaster is monitoring PA DEP's review process and submitted municipal comments as part of PA DEP Municipal Notification requirement on 6/12/25”
  • air quality plan approval: draft published
    “PA DEP has posted the draft permit approval in the Pennsylvania Bulletin on 11/15/2025, which serves as the official Public Notice and begins a 30-day public comment period”
  • land development: approval required pending
    “Phase 2 of 216 Greenfield Road extends beyond the building's existing footprint and involves significant site improvements; therefore, it requires land development review and approval by the Planning Commission”
  • Lancaster City Council: Council directed the City Solicitor to draft a zoning ordinance amendment to regulate data centers
    “On August 15, 2025 City Council directed the City Solicitor to draft a Zoning Ordinance amendment to regulate data centers”
  • Lancaster City Council: First reading of the proposed data center zoning ordinance amendment
    “City Council held a first reading of the ordinance on October 14, 2025”
  • Lancaster City Council: Community Benefits Agreement with Chirisa Technology Parks (CBA press conference Nov 18, 2025; executed agreement dated Nov 24, 2025)
    “The City of Lancaster and Chirisa Technology Parks, the developer of the data centers at 216 Greenfield Road and 1375 Harrisburg Pike, negotiated a Community Benefits Agreement”
  • Lancaster City Council: Hearing on the proposed data center zoning amendment; final adoption considered in July 2026
    “A hearing regarding the proposed amendment we held on June 24, 2026. City Council will consider the amendment for final adoption in July 2026”
  • building permit: Commercial: issued
    “Permit number: 260004051 · Type: Commercial · Status: issued · Job value: $920,902 · Effective date: May 13, 2026 · Address: 216 GREENFIELD RD · Description: Fire alarm per approved scope east building 1”
  • FAA obstruction evaluation (7460-1): Determined - No Hazard
    “ASN 2026-AEA-4416-OE: Crane Type - Manitowoc MLC-650, Mobile Crane, 530 ft AGL, 877 ft AMSL, 40.04802,-76.25976, Determined - No Hazard, submitted 2026-04-08”
  • building permit: Commercial: issued
    “Permit number: 250003330 · Type: Commercial · Status: issued · Job value: $9,388,638 · Effective date: Feb. 17, 2026 · Address: 216 GREENFIELD RD · Description: Sprinkler per approved plans”
  • building permit: Commercial: issued
    “Permit number: 250003254 · Type: Commercial · Status: issued · Job value: $500,000 · Effective date: Feb. 9, 2026 · Business: Vollers Excavating & Construct · Address: 216 GREENFIELD RD · Description: Sprinkler system per approved scope”
  • air quality permit: draft permit posted for public comment
    “PA DEP has posted the draft permit approval in the Pennsylvania Bulletin on 11/15/2025”
  • building permit: Commercial int&ext alter over 10 000: issued
    “Permit number: 250001690 · Type: Commercial int&ext alter over 10 000 · Status: issued · Job value: $15,000,000 · Effective date: Aug. 4, 2025 · Address: 216 GREENFIELD RD · Description: Data center building out - level III alteration per approved scope”
  • building permit: Commercial: issued
    “Permit number: 250001409 · Type: Commercial · Status: issued · Job value: $3,000,000 · Effective date: June 30, 2025 · Business: Turner Wohlsen II · Address: 216 GREENFIELD RD · Description: Demolition & alterations per approved scope”
  • zoning determination: determination issued
    “The zoning determination, issued in February and signed by Thrash, termed the centers electronic data processing warehouses, qualifying as wholesale trade and storage”
  • air quality plan approval: issuance announced
    “DEP published notice in the January 17 PA Bulletin announcing it has approved an Air Quality Plan Approval covering the installation of 176 - 3.25 MW backup diesel generators”
  • air quality plan approval phase2: intent to issue notice
    “Phase 2 involves the installation of 84 diesel generators. An Air Quality Plan Approval was already issued for Phase 1 of the project covering the installation of 72 diesel generators”
  • At the Jul 14, 2026 ordinance adoption meeting, residents said they were blindsided by the two under-construction projects and asked for them to be paused; some council members sought stronger text (vibration and low-fre
    “Residents who attended the meeting said they were blindsided by the projects that are currently under construction, would like to see them paused”
  • State context: under Gov. Shapiro's Data Center Executive Order, DEP operates a data center permit tracker and developers must obtain all permits and local approvals before DEP reviews facility permits (as summarized by
    “Visit DEP's Data Center Permit Tracker webpage for information on pending permits for A.I. data center projects established by Gov. Shapiro's Data Center Executive Order”
  • Lancaster County Planning Commission has been advising municipalities across the county about adding data center regulations since CoreWeave's announcement, the Greenfield project triggered county-wide ordinance work.
    “The Lancaster County Planning Commission has been advising municipalities in the county about adding data center regulations in the weeks since CoreWeave announced its plans”
  • An
    “The developers haven't established a timeline for the Harrisburg Pike site, or a planned second phase at Greenfield”
  • Lancaster City Planning Commission: Vote to hold an Oct 1, 2025 hearing examining the Feb 2025 zoning determination that allowed the data centers by right; Mayor Sorace and Zoning Officer Thrash invited to speak
    “Lancaster City Planning Commission members voted unanimously to hold the hearing Oct. 1”
  • Lancaster City Planning Commission: Public hearing on whether the Feb 2025 zoning determination (data centers as wholesale trade and storage) was made in error
    “commissioners voted unanimously to advertise a hearing about the city's approval of the data centers for Oct. 1”
  • Lancaster City Council: Adopted the data center zoning amendment; clarifying motion confirms the two projects approved before June 24 (216 Greenfield Road and 1375 Harrisburg Pike) remain permitted. Future data centers l
    “The Lancaster City Council voted to pass an amendment to regulate data centers in the city of Lancaster on Tuesday night”
  • land development: conditionally approved (reported)
    “Planning commission gives conditional approval to 216 Greenfield Road data center; residents press zoning and environmental concerns”
  • zoning determination: determined permitted use
    “The zoning determination, issued in February and signed by Thrash, termed the centers "electronic data processing warehouses," qualifying as wholesale trade and storage.”
  • demolition permit / demolition: demolition underway
    “Demolition is already underway at the 216 Greenfield Road site, where co-developers Chirisa Technology Parks and Machine Investment Group plan to have a 450,000 square-foot data center complete in summer 2027.”
Site and other (19)
  • Address: 216 Greenfield Road, Lancaster, PA 17601-5817
    “Name: GREENFIELD RD OWNER LLC Mailing Address: 216 GREENFIELD RD LANCASTER, PA 17601-5817”
  • City: Lancaster (City of Lancaster)
    “Location: 36 Lancaster County 36001 Lancaster City SIC Code: 7374 Services - Data Processing Services”
  • County: Lancaster County
    “Location: 36 Lancaster County 36001 Lancaster City SIC Code: 7374 Services - Data Processing Services”
  • County code: Lancaster County, PA (42071)
    “Location: 36 Lancaster County 36001 Lancaster City SIC Code: 7374 Services - Data Processing Services”
  • Operator: CoreWeave
    “CoreWeave will be the tenant of the site, co-developed by Chirisa Technology Parks and Machine Investment Group.”
  • Announced: July 15, 2025
    “Equipped with state-of-the-art infrastructure tailored for advanced AI workloads, the Lancaster data center will help position Pennsylvania, and the broader Mid-Atlantic region, as a strategic hub”
  • Campus name: CoreWeave Lancaster Greenfield site
    “The Lancaster AI Hub is what the developer, Chirisa Technology Parks, is calling the entire project”
  • Site owner: Greenfield Road Owner, LLC
    “The properties are owned by Greenfield Road Owner, LLC. (216 Greenfield Road) and Harrisburg Place Owner, LLC. (1375 Harrisburg Pike.) Both are subsidiaries of Chirisa Technology Parks”
  • Developer: Chirisa Technology Parks, co-developed with Machine Investment Group
    “CoreWeave will be the tenant of the site, co-developed by Chirisa Technology Parks and Machine Investment Group”
  • First announced: July 15, 2025
    “to announce a major step forward for CoreWeave and for the future of AI in the US”
  • Site acquisition: February 2025, purchase of the former LSC Communications printing plants by CTP-affiliated owners announced
    “The purchase and proposed use of two existing industrial sites, located at 216 Greenfield Road and 1375 Harrisburg Pike, was announced by the developers in February 2025”
  • County code: 42071
    “creating good-paying jobs as Pennsylvania workers build, maintain, and operate a new AI data center in Lancaster County”
  • Site location: 216 Greenfield Road, Lancaster, PA (City of Lancaster)
    “The properties are owned by Greenfield Road Owner, LLC. (216 Greenfield Road) and Harrisburg Place Owner, LLC. (1375 Harrisburg Pike.)”
  • Project name: Lancaster AI Hub (Greenfield site)
    “The Lancaster AI Hub is what the developer, Chirisa Technology Parks, is calling the entire project.”
  • Stage: building
    “Demolition is already underway at the 216 Greenfield Road site”
  • Original target date: 2027
    “co-developers Chirisa Technology Parks and Machine Investment Group plan to have a 450,000 square-foot data center complete in summer 2027”
  • Current target date: 2027
    “co-developers Chirisa Technology Parks and Machine Investment Group plan to have a 450,000 square-foot data center complete in summer 2027”
  • Phase 1 building area sq ft: 450000 sq ft
    “co-developers Chirisa Technology Parks and Machine Investment Group plan to have a 450,000 square-foot data center complete in summer 2027”
  • Project status: building (demolition and adaptive reuse underway at 216 Greenfield Road; not operating)
    “Demolition is already underway at the 216 Greenfield Road site, where co-developers Chirisa Technology Parks and Machine Investment Group plan to have a 450,000 square-foot data center complete in summer 2027.”

Imagery and records: Building permits: ATTOM.