Power and the grid
216 MW contracted
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Aug. 10, 2023Power agreement and substation startEdgeCore announces an NV Energy agreement and a substation already under way, with power due in the second half of 2025. see Permits
- Jan. 26, 2026Backup engine air permit proposedNevada proposes to issue a Class II air permit covering the campus's stationary engines (backup generators, not supply). State agency · Jan. 2026
- Not setCampus service agreement not publicNo agreement for the campus appears in a public utility commission record; the commission's large-load framework came later and is pending. News report · Oct. 2026
- The campus is grid-only. On-site engines are backup power and are permitted under an air permit that keeps each pollutant under 100 tons a year. State agency · Jan. 2026
- The 2023 design was two buildings and 1.5 million sq ft; the Jan. 2026 company release shows three 72 MW buildings. Total IT capacity is unchanged at 216 MW. News report · Oct. 2026
Evidence from space
NO2 over the site, net of the rural background, was about the same in July–September 2026 (9 µmol/m²) as a year earlier (8), and the rural background rose 14% (15 to 17). The satellite sees no new combustion large enough to stand out here. This campus shares its satellite box with a neighboring campus at the same site.
What else could explain it
- Cities, highways, oil and gas fields and power plants in or near the box also emit NO2. Comparing the same months a year apart removes steady sources; a new source nearby would not cancel.
- Weather moves NO2 from day to day (wind, sunlight, cloud), and it builds up in winter. Subtracting the background box and comparing the same season a year apart removes most of that.
How this works: the Sentinel-5P satellite measures NO2 in the air over every point on Earth once a day, around 1:30 p.m. local time, in pixels about 5.5 by 3.5 km. NO2 comes from burning fuel (turbines, engines, traffic, power plants), so a rise over a site that open country does not share points to new combustion there. It shows combustion activity, not megawatts. The site box is about 15 km across; the background box is open country about 62 km away. We use only high-quality readings and drop days or weeks when cloud hides more than half of either box. Data: Copernicus Sentinel-5P (ESA), processed with the Copernicus Data Space Ecosystem Sentinel Hub statistics service.
Permits checklist
1 pending · 2 granted · 1 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ◷Class II air operating permit PendingNevada Division of Environmental Protection · Jan. 26, 2026: intent to issue; comments closed Feb. 25, 2026; no final permit located State agency · Oct. 2026
- ✓State tax abatement GrantedNevada Governor's Office of Economic Development · March 15, 2018: for the original 2018 plan; terms not public News report · March 2018
- ✓Utility service agreement GrantedNV Energy · Aug. 10, 2023: company says executed; not a public document Company · Aug. 2023
- –Checked, nothing on file: Local zoning and building permits
What could slow it down
- HighSchedule slipPower and delivery were slated for H2 2025; trade press now says 2026 and no building is announced as delivered. News report · Oct. 2026
- MediumNo tenantA speculative single-tenant build with no customer announced. News report · Oct. 2026
- MediumPower terms unseenThe NV Energy agreement and its minimum-bill or exit terms are not public. News report · Oct. 2026
- WatchAir permit not finalOnly a proposed permit is on record; it covers backup engines. State agency · Jan. 2026
Money on record
3 recorded land documents for the campus company in county records (March 2018 to Sept. 2026); 1 lists a price. 1 sale or conveyance by the campus company or to public bodies is not listed. Parcel counts come from the deed; acreage is not recorded.
- March 2018 MECP1 Reno 1 LLC (seller not named) · $3.9M · 1 parcel County deed records · March 2018
- Sept. 2026 MECP1 Reno 1 LLC (seller not named) · price not recorded · 1 parcel County deed records · Sept. 2026
- Sept. 2026 MECP1 Reno 1 LLC (seller not named) · price not recorded · 1 parcel County deed records · Sept. 2026
What happened, and what is due
- Construction First building delivery: no date announced News report · Oct. 2026
- March 15, 2018Money State approves tax abatements for a 225 MW Reno data center plan News report · March 2018
- Nov. 2022Paper trail Partners Group acquires EdgeCore and starts funding the Reno build Company · Oct. 2026
- Aug. 10, 2023Construction EdgeCore announces construction start, a 216 MW design and an NV Energy agreement News report · Oct. 2026
- Sept. 20, 2024Site EdgeCore donates $48,000 to Storey County Local government · Oct. 2026
- Aug. 21, 2025Site County records show a land lease from EdgeCore's Reno 1 entity to CoreWeave Inc.; price not recorded County deed records · Aug. 2025
- Jan. 13, 2026Construction EdgeCore reports active construction on the first of three 72 MW buildings News report · Jan. 2026
- Jan. 26, 2026Permits Nevada proposes to issue the Class II air permit; comments due Feb. 25 State agency · Jan. 2026
- Sept. 17, 2026Legal Governor's order sets new conditions for data-center tax breaks; the 2018 approval is outside its scope as reported News report · Oct. 2026
Building activity by quarter
Since Sept. 2024: 2 FAA filings (Sept. 2024 to Jan. 2025): tallest crane 365 ft (Sept. 2024).
Specs
- Air-cooled: closed-loop chilled water; water use below 0.01 L/kWh (company) Company · Oct. 2026
Owners, partners and builders
- EdgeCore Digital Infrastructure: developer and operator
- Partners Group: owner of EdgeCore since Nov. 2022
- MECP1 Reno 1, LLC: project entity
- Nevada Division of Environmental Protection: air permit
- Nevada Governor's Office of Economic Development: tax abatement
- Public Utilities Commission of Nevada: large-load framework
- NV Energy (Sierra Pacific Power): utility and substation developer
Open questions
- Tenant and lease terms.
- Delivery date of the first building.
- Size and terms of the NV Energy agreement.
- Whether the final air permit was issued.
- Scope and terms of the land lease to CoreWeave recorded Aug. 2025, and whether CoreWeave is the campus tenant.
104 records from 20 documents
Drawn from news reports, company statements, state agency records, local government records and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (28)
- Owner companies: MECP1 Reno 1, LLC“MECP1 Reno 1, LLC (RNO1) submitted an application for a new Class II Air Quality Operating Permit, AP7374-4772, FIN A2652, for the RNO1 facility in Storey County, Nevada”State agency · Oct. 2026 · grade A
- County code: Storey County, NV (32029)“MECP1 Reno 1, LLC (RNO1) submitted an application for a new Class II Air Quality Operating Permit, AP7374-4772, FIN A2652, for the RNO1 facility in Storey County, Nevada”State agency · Oct. 2026 · grade A
- On-site generation: not stated“RNO1 will be subject to 40 CFR Part 60 Subpart IIII and 40 CFR Part 63 Subpart ZZZZ”State agency · Oct. 2026 · grade A
- County code: 32029“MECP1 Reno 1, LLC (RNO1) submitted an application for a new Class II Air Quality Operating Permit, AP7374-4772, FIN A2652, for the RNO1 facility in Storey County, Nevada.”State agency · Jan. 2026 · grade A
- IT capacity: 216 MW“EdgeCore is currently constructing an on-site substation and three data centers in Reno. This project sits on a 56-acre campus, offering 1 million square feet (92,532 sqm) of space, capable of supporting 216 MW of critical IT load.”Company · Oct. 2026 · grade B
- Site area: 56 acres“This project sits on a 56-acre campus, offering 1 million square feet (92,532 sqm) of space, capable of supporting 216 MW of critical IT load.”Company · Oct. 2026 · grade B
- Land (acres): 56 acres“56, Acres, 3, Data Centers, 216 MW, Critical IT Load, 1M Total Building Sq. Ft.”Company · Oct. 2026 · grade B
- Buildings: 3 buildings“56, Acres, 3, Data Centers, 216 MW, Critical IT Load, 1M Total Building Sq. Ft.”Company · Oct. 2026 · grade B
- Building sq ft total: 1000000 sq ft“56, Acres, 3, Data Centers, 216 MW, Critical IT Load, 1M Total Building Sq. Ft.”Company · Oct. 2026 · grade B
- IT capacity: 216 MW“56, Acres, 3, Data Centers, 216 MW, Critical IT Load, 1M Total Building Sq. Ft.”Company · Oct. 2026 · grade B
- Stated campus size: 216 MW“56, Acres, 3, Data Centers, 216 MW, Critical IT Load, 1M Total Building Sq. Ft.”Company · Oct. 2026 · grade B
- Power plan: grid-only with diesel backup (NV Energy)“RNO1 will be subject to 40 CFR Part 60 Subpart IIII and 40 CFR Part 63 Subpart ZZZZ”State agency · Oct. 2026 · grade B
- Cooling: air-cooled design; closed-loop chilled water; WUE below 0.01 L/kWh“we implemented an air-cooled design at our Reno data center campus which utilizes very little water to cool our facilities”Company · Oct. 2026 · grade B
- Project status: active construction - first of three data centers“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada.”Company · Jan. 2026 · grade B
- Buildings count: 3 buildings“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada.”Company · Jan. 2026 · grade B
- First building was still in active construction in Jan 2026, after the Aug 2023 expectation of completion as early as late 2025 - delivery has slipped into 2026 with no delivery/opening announced in sources checked“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada.”Company · Jan. 2026 · grade B
- Utility: NV Energy“EdgeCore has completed an agreement with NV Energy for its campus near Reno with utility power being delivered to the site by H2 2025.”Company · Aug. 2023 · grade B
- Utility service: not stated“EdgeCore has completed an agreement with NV Energy for its campus near Reno with utility power being delivered to the site by H2 2025”News report · Oct. 2026 · grade C
- Stage: building“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada”News report · Oct. 2026 · grade C
- Utility: NV Energy (Sierra Pacific Power Company)“EdgeCore has completed an agreement with NV Energy for its campus near Reno with utility power being delivered to the site by H2 2025”News report · Oct. 2026 · grade C
- Groundbreaking of the redesigned TRIC campus under Partners Group ownership: two buildings, 1.5 million sq ft, 216 MW of critical IT capacity, an on-site substation and an executed NV Energy agreement with power delivery sla“two data centers totaling 1.5 million square feet of space and capable of supporting 216 MW of critical IT load”News report · Oct. 2026 · grade C
- EdgeCore's January 2026 platform release restates the Reno campus as THREE 72 MW buildings (the 2023 design had two buildings) and reports active construction under way on the first, total campus capacity unchanged at 2“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada”News report · Oct. 2026 · grade C
- NV Energy agreement executed for the campus before groundbreaking, with utility power delivery and substation completion slated for H2 2025. No MW figure for the agreement has ever been published, and no campus service a“EdgeCore has completed an agreement with NV Energy for its campus near Reno with utility power being delivered to the site by H2 2025”News report · Oct. 2026 · grade C
- Delivery has slipped from late 2025 (2023 company guidance) to an unannounced date in 2026 per trade press, with no delivery announced as of Oct 2026. The visible long pole is permitting and power: the Class II air-permi“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada”News report · Oct. 2026 · grade C
- Buildings operational: 0 buildings“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada”News report · Jan. 2026 · grade C
- IT capacity: 72 MW“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada”News report · Jan. 2026 · grade C
- Construction stage: building, active construction on first of three 72 MW data centers“Active construction is under way on the first of three 72MW data centers at the EdgeCore Digital Infrastructure campus in Greater Reno, Nevada”News report · Jan. 2026 · grade C
- Announced: March 2018“Reno, Nevada: 56 acres in Tahoe-Reno Industrial Corridor; six buildings; 1.06 million sq. ft. (98,474 sq. m.) to support 225 MW of critical load; phase one to deliver in Q1 2019”News report · March 2018 · grade C
Money and contracts (25)
- land purchase: scope 56 acres“56, Acres, 3, Data Centers, 216 MW, Critical IT Load, 1M Total Building Sq. Ft.”Company · Oct. 2026 · grade B
- land purchase: consideration“56, Acres, 3, Data Centers, 216 MW, Critical IT Load, 1M Total Building Sq. Ft.”Company · Oct. 2026 · grade B
- Community engagement: EdgeCore donated $48,000 to Storey County, $24,000 to the Sheriff's Office for portable radios and $24,000 to Health & Community Services (veterans' employment services, food and nutritional care).“Storey County is pleased to announce a generous donation from EdgeCore Digital Infrastructure totaling $48,000 to support critical county services”Local government · Oct. 2026 · grade B
- EdgeCore's 2025 community contributions in Storey County included $30,000 for a Search & Rescue pickup truck for the Sheriff's Office, per the county's 2025 Year in Review.“EdgeCore Digital Infrastructure contributed to both the Sheriff's Office and Health & Community Services, including $30,000 for a Search & Rescue pickup truck”Local government · Oct. 2026 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Sept. 1, 2026 · Grantee: MECP1 RENO 1 LLC · Parcel number: 005-071-46 · Address: 3000 USA PKWY · City: SPARKS”County deed records · Sept. 2026 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Sept. 1, 2026 · Grantee: MECP1 RENO 1 LLC · Parcel number: 005-071-46 · Address: 3000 USA PKWY · City: SPARKS”County deed records · Sept. 2026 · grade B
- Land lease (recorded document): contract value USD“Recorded: Aug. 21, 2025 · Grantor: MECP1 RENO 1 LLC · Grantee: COREWEAVE INC · Parcel number: 005-071-46 · Address: 3000 USA PKWY · City: SPARKS”County deed records · Aug. 2025 · grade B
- utility power agreement: utility power delivery“EdgeCore has completed an agreement with NV Energy for its campus near Reno with utility power being delivered to the site by H2 2025.”Company · Aug. 2023 · grade B
- Land purchase (recorded deed): contract value 3921500 USD“Recorded: March 19, 2018 · Price: $3,921,500 · Grantee: MECP1 RENO 1 LLC · Parcel number: 005-071-46 · Address: 3000 USA PKWY · City: SPARKS”County deed records · March 2018 · grade B
- Tenants: not stated“build high-density, scalable, single tenant data centers with an absolute certainty of execution”News report · Oct. 2026 · grade C
- Tenant status: no tenant announced; speculative single-tenant build“build high-density, scalable, single tenant data centers with an absolute certainty of execution”News report · Oct. 2026 · grade C
- electric service agreement: termination“EdgeCore has completed an agreement with NV Energy for its campus near Reno with utility power being delivered to the site by H2 2025”News report · Oct. 2026 · grade C
- electric service agreement: minimum billing“EdgeCore has completed an agreement with NV Energy for its campus near Reno with utility power being delivered to the site by H2 2025”News report · Oct. 2026 · grade C
- tax abatement: clawback“MECP1 Reno 1, LLC, Storey County, 50 jobs, $221,418,850 in capital investment”News report · Oct. 2026 · grade C
- GOED Board approved MECP1 Reno 1, LLC's abatement application for the ORIGINAL campus plan: a 1.1 million sq ft, 225 MW, multi-tenant campus at TRIC with $221,418,850 of capital investment and 50 jobs. The project then s“MECP1 Reno 1, LLC, Storey County, 50 jobs, $221,418,850 in capital investment”News report · Oct. 2026 · grade C
- Portfolio financing context (NOT campus financing): Partners Group's initial $1.2B commitment funded Reno's development start in 2023, and EdgeCore raised a further $1.9B of equity in 2024“The ABS issuance is backed by EdgeCore's stabilized PH01 data center in the Mesa area of Phoenix, Arizona”News report · Oct. 2026 · grade C
- electric service agreement: scope“EdgeCore has completed an agreement with NV Energy for its campus near Reno with utility power being delivered to the site by H2 2025”News report · Aug. 2023 · grade C
- electric service agreement: delivery deadline utility power delivery and on-site substation completion slated H2 2025“Development of the substation has already begun and is also slated for completion in the second half of 2025”News report · Aug. 2023 · grade C
- tax abatement approval: state-approved abatement application; capital investment 221418850 USD“MECP1 Reno 1, LLC, Storey County, 50 jobs, $221,418,850 in capital investment: MECP1 Reno 1, LLC is an EdgeCore Data Centers project.”News report · March 2018 · grade C
- Capital cost announced: 221418850 USD“MECP1 Reno 1, LLC, Storey County, 50 jobs, $221,418,850 in capital investment”News report · March 2018 · grade C
- Jobs committed: 50 jobs“MECP1 Reno 1, LLC, Storey County, 50 jobs, $221,418,850 in capital investment”News report · March 2018 · grade C
- Incentives: GOED partial tax abatements approved March 15, 2018 (terms not public in sources opened)“On March 15, board members for the Nevada Governor's Office of Economic Development approved applications for 12 businesses throughout the state”News report · March 2018 · grade C
- tax abatement: scope 221418850 USD capital investment“which involves the construction of a 1.1 million-square-foot facility and 225 MW of data center capacity”News report · March 2018 · grade C
- tax abatement: jobs floor 50 jobs“MECP1 Reno 1, LLC, Storey County, 50 jobs, $221,418,850 in capital investment”News report · March 2018 · grade C
- tax abatement: tax terms“MECP1 Reno 1, LLC, Storey County, 50 jobs, $221,418,850 in capital investment”News report · March 2018 · grade C
Permits and government (10)
- NDEP BAPC made a preliminary determination to issue Class II air permit AP7374-4772 for RNO1, the campus's first air-permit action, roughly 29 months after groundbreaking; the comment period closed Feb 25, 2026 and no f“Current emissions estimates indicate RNO1 is a Class II source, because the facilitywide PTE for any individual regulated pollutant is less than 100 tons per year”State agency · Oct. 2026 · grade A
- Class II Air Quality Operating Permit: Application received; Director intent to issue proposed permit“MECP1 Reno 1, LLC (RNO1) submitted an application for a new Class II Air Quality Operating Permit, AP7374-4772, FIN A2652, for the RNO1 facility in Storey County, Nevada.”State agency · Jan. 2026 · grade A
- Class II Air Quality Operating Permit: Notice of Proposed Action published“RNO1 is requesting a Class II Air Quality Operating Permit for their new facility. RNO1 is a data center.”State agency · Jan. 2026 · grade A
- air quality permit: application reviewed, preliminary determination to issue“Current emissions estimates indicate RNO1 is a Class II source, because the facilitywide PTE for any individual regulated pollutant is less than 100 tons per year”State agency · Jan. 2026 · grade A
- air quality permit: notice of proposed action, public comment opened“the Director is hereby announcing his intent to issue the proposed Class II Air Quality Operating Permit”State agency · Jan. 2026 · grade A
- A Class II air quality OPERATING permit for RNO1 was only at proposed-action stage in Jan-Feb 2026 (comments until Feb 25 2026), i.e. the operating permit process was still open while construction was under way“Written comments or objections will be received at the Nevada Division of Environmental Protection, above address, until February 25, 2026”State agency · Jan. 2026 · grade A
- FAA OE/AAA: Determined - No Hazard“Crane to assist with construction of new data center.”FAA · Jan. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AWP-11751-OE: Manitowoc 16000 with luffer, Mobile crane, 365 ft AGL, 5057 ft AMSL, 39.524167,-119.482167, Determined - No Hazard, submitted 2024-09-05”FAA · Sept. 2024 · grade A
- Governor Lombardo's Executive Order 2026-005 (the Nevada Standard for Responsible Data Center Development) imposes new conditions, school-support tax paid in full, a Community Support Commitment, full incremental power“Data center applications seeking tax breaks cannot be brought to the state's economic development board for approval unless the developer agrees to pay the school tax in full”News report · Oct. 2026 · grade C
- Nevada Governor's Office of Economic Development (GOED) Board of Directors: Partial tax abatement applications of 12 businesses approved, including MECP1 Reno 1, LLC (EdgeCore) for a Storey County data center at the Taho“MECP1 Reno 1, LLC, Storey County, 50 jobs, $221,418,850 in capital investment”News report · March 2018 · grade C
Site and other (10)
- Aliases: EdgeCore Reno campus; RN01; RNO1“MECP1 Reno 1, LLC, 3000 USA Parkway, McCarran, Nevada 89437”State agency · Oct. 2026 · grade A
- Address: 3000 USA Parkway, McCarran, NV 89437“MECP1 Reno 1, LLC, 3000 USA Parkway, McCarran, Nevada 89437”State agency · Oct. 2026 · grade A
- Site address: 3000 USA Parkway, McCarran, Nevada 89437“MECP1 Reno 1, LLC 3000 USA Parkway McCarran, Nevada 89437”State agency · Jan. 2026 · grade A
- Name: EdgeCore Reno (TRIC)“Storey County, which is home to EdgeCore's metro Reno data center campus”Company · Oct. 2026 · grade B
- Developer: EdgeCore Digital Infrastructure“the expansion and development of data center campuses in Santa Clara, California (January 2023); Ashburn, Virginia (March 2023); Mesa, Arizona (April 2023) and Reno, Nevada (August 2023)”Company · Oct. 2026 · grade B
- Construction stage: building, first building topped out; no delivery announced“Topping Off Ceremony for EdgeCore Digital Infrastructure”Local government · Oct. 2026 · grade B
- Developer: EdgeCore Digital Infrastructure“EdgeCore Digital Infrastructure, a wholesale data center developer, owner, and operator, announced it has begun construction of its initial data center campus in metro Reno, Nevada.”Company · Aug. 2023 · grade B
- Current target date: 2026“Its facility in Reno, Nevada, is set to be delivered in 2026”News report · Oct. 2026 · grade C
- Original target date: 2025“Completion is expected as early as late 2025”News report · Aug. 2023 · grade C
- Groundbreaking date: Aug. 2023“announced it has begun construction of its initial data center campus in metro Reno, Nevada”News report · Aug. 2023 · grade C
Imagery and records: County deeds: ATTOM.