Data center profile · 3441 Railport Parkway, Midlothian (Ellis County), Texas

Google Midlothian (Sharka Data Center)

Google's Railport campus in Midlothian, Texas: four buildings complete, fifth under construction, city approved two more phases and an on-site generating plant (Oct. 2026).

Operating, expanding. Buildings 1 to 4 are complete; federal air operating permit held since July 2021. Building 5 began construction in Jan. 2026. On Oct. 13, 2026 the city approved zoning for phases 5 and 6 and an on-site generating plant.
288,000 sq ft
Building 5 (filing, press)
Google gives no MW figure
4 of 5
buildings complete, fifth under construction
Building 5 filed completion date is Feb. 24, 2027
$880M
filed cost of Building 5
press
~540 acres
land bought across 2019 and 2020
375 acres in 2019 plus 165 acres in 2020
OperatorGoogle, through Sharka LLC (site owner and permit holder)
CustomerGoogle (self-use)
Planned IT capacity103 MW at full build-out (company IT figure)
First building in serviceIn service since 2021 (about 103 MW of IT capacity live, estimated)
Next deadlineFeb. 24, 2027: Building 5 filed completion date
Power

Power and the grid

Energized, size not disclosed

Sources on record, size not disclosed
Backup generators (emergency use, not a power supply)

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. May 26, 2020
    Water contract
    The city authorizes a 20-year retail water supply contract with Sharka LLC, passed 6-0. Local government · May 2020
  2. Nov. 14, 2025
    Google commits to more Texas capacity
    At an event on the campus, Google announces a $40B Texas program and continued investment in Midlothian; its 6,200 MW of Texas power contracts are a portfolio figure, not this site (press). News report · Nov. 2025
  3. Oct. 13, 2026
    On-site generating plant zoned
    Council approves a zoning amendment adding phases 5 and 6 and an on-site generating plant, with a 20-foot sound wall. see Permits
  4. Not set
    Utility service agreement: not public
    No Oncor contract, delivered MW or generator capacity is on record.

Backup generators on file

Emergency units only; they are not a power supply for the campus.

Permits

Permits checklist

4 granted · 1 checked, nothing on file

Approvals a campus like this normally needs (including an air permit for backup generators), and what we found.

Risks

What could slow it down

Money

Money on record

$600M
investment Google cited at the 2019 reveal (press)
$350M
filed cost of Building 4
state construction filing, 2024 State agency · April 2024
$880M
filed cost of Building 5 (press)
started Jan. 2026 News report · Jan. 2026
100% / 85%
personal property and improvement tax abatement, 10 years (press)
agreement text is not public News report · June 2019
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. Oct. 15, 2018
    Permits First state air authorization for the Sharka Data Center, before Google's name was public State agency · Oct. 2018
  2. May 31, 2019
    Permits City council approves tax abatements for Sharka LLC while the operator's identity is hidden under a nondisclosure agreement News report · May 2019
  3. June 2019
    Site Google confirms it bought the 375-acre site and announces a $600M data center, its first in Texas (press) News report · June 2019
  4. May 26, 2020
    Permits City authorizes a 20-year water supply contract for the campus Local government · May 2020
  5. July 21, 2021
    Permits Federal air operating permit issued for the campus State agency · July 2021
  6. April 1, 2024
    Site Building 4 construction starts (170,600 sq ft, $350M filed) State agency · April 2024
  7. 2025
    Site Building 4 completed and its state construction file closed State agency · Dec. 2025
  8. Jan. 2026
    Site Building 5 construction begins (288,000 sq ft, $880M filed) News report · Jan. 2026
  9. Oct. 13, 2026
    Permits Council approves zoning for phases 5 and 6 and an on-site generating plant News report · Oct. 2026
  10. Feb. 24, 2027
    Site Building 5 filed completion date News report · Oct. 2026
The buildings

Specs

170,600 sq ft
Building 4, finished Dec. 2025
288,000 sq ft
Building 5, one story (press)
20 years
retail water supply contract with the city, extendable by mutual consent
Who is involved

Owners, partners and builders

Owners
  • Google: developer and operator
  • Sharka LLC: site owner and permit holder (Delaware)
Power and water
  • Oncor Electric Delivery: utility
  • City of Midlothian: water provider and abating authority
Decision-makers
  • Midlothian City Council: zoning, abatements, water
  • Texas Commission on Environmental Quality: air permits
Others
  • Trinity Consultants: environmental consultant
Still unknown

Open questions

Where this comes from

122 records from 21 documents

Drawn from news reports, state agency records, company statements, local government records, public and commercial datasets and our own analysis, each kept with its date and source. The bar shows documents by type.

News report 14State agency 4Company 2Local government 1Dataset 1Analysis 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (5)
  • On-site generation: not stated
    “Equipment authorized at the site includes: Diesel-fired engine-driven emergency generators; Diesel-fired engine-driven emergency firewater pump; Diesel storage tanks; Mechanical draft cooling towers”
  • Power plan: grid
    “allow for a power supply to protect critical data center functions if the primary power from the grid is unavailable”
  • Utility: Oncor Electric Delivery Company LLC
    “Oncor is the TDSP for eligible Midlothian addresses. It maintains the poles, wires, and meter and handles outages.”
  • Project status: operating, expanding (Building 4 TDLR project closed; Building 5 filed, due Feb 24, 2027; council approved phases 5-6 Oct 13, 2026)
    “The Midlothian City Council unanimously approved amendments to PD 106 allowing Google’s Railport campus to add phases 5 and 6 and an on-site generation (OSG) plant”
  • Google states it has contracted more than 6,200 MW of net new energy generation and capacity for the Texas grid through PPAs (AES, Enel, Clearway, ENGIE, Intersect, SB Energy, Orsted, X-Elio). PORTFOLIO figure for all Te
    “Google has contracted to add more than 6,200 megawatts (MW) of net new energy generation and capacity to the Texas electricity grid through power purchase agreements”
Money and contracts (34)
  • County code: 48139
    “Location Address: 3441 Railport Parkway Midlothian, TX 76065, Location County: Ellis, Start Date: 4/1/2024, Completion Date: 12/31/2025, Estimated Cost: $350,000,000”
  • Building4 cost filed: 350000000 USD
    “Project Name: Sharka Data Center - Building 4 Project Number: TABS2024013301 Location Address: 3441 Railport Parkway Start Date: 4/1/2024, Completion Date: 12/31/2025, Estimated Cost: $350,000,000”
  • Building 4 construction starts (TDLR TABS2024013301: 170,600 sq ft, filed cost $350M).
    “Start Date: 4/1/2024, Completion Date: 12/31/2025, Estimated Cost: $350,000,000”
  • Water supply: City of Midlothian retail water supply contract (20-year; authorized May 26, 2020)
    “CONSIDER AND ACT UPON AUTHORIZING THE CITY MANAGER TO EXECUTE A RETAIL WATER SUPPLY CONTRACT WITH SHARKA LLC”
  • City Council authorizes a 20-year retail water supply contract with Sharka LLC (Item 2020-168, passed 6-0), folding in the earlier water/wastewater MOU.
    “IT IS A 20 YEAR AGREEMENT. IT HAS THE ABILITY TO BE EXTENDED ON MUTUALLY CONSENT.”
  • Investment: 600000000 USD
    “We’re investing $600 million to develop the Midlothian site, which will create a number of full-time jobs, as well as hundreds of construction jobs”
  • Tenants: Google LLC (owner-occupied)
    “TENANT Not Assigned”
  • Tenant status: owner-occupied
    “TENANT Not Assigned”
  • retail water supply contract: scope Retail water supply to the campus within the City's CCN; incorporates water and wastewater terms from the original MOU
    “THIS MATTER IS FOR SUPPLYING WATER, WE ARE THE RETAIL PROVIDER FOR THE CITY WITHIN OUR CCN SO THIS CONTRACT REALLY HAS FALLEN IN LINE WITH WHAT WE ARE TYPICALLY DOING WITH OUR INDUSTRY OUT AT RAIL PORT”
  • retail water supply contract: term 20 years
    “IT IS A 20 YEAR AGREEMENT. IT HAS THE ABILITY TO BE EXTENDED ON MUTUALLY CONSENT.”
  • retail water supply contract: extension Extendable by mutual consent of the parties
    “IT IS A 20 YEAR AGREEMENT. IT HAS THE ABILITY TO BE EXTENDED ON MUTUALLY CONSENT.”
  • retail water supply contract: termination FINDING: no termination clause is stated in the public council record for this contract; the executed contract text was not opened
    “CONSIDER AND ACT UPON AUTHORIZING THE CITY MANAGER TO EXECUTE A RETAIL WATER SUPPLY CONTRACT WITH SHARKA LLC”
  • memorandum of understanding (water/wastewater): lineage Original MOU with water and wastewater terms predates and is folded into the 2020 retail water supply contract
    “THERE ARE SOME ITEMS THAT WERE COVERED IN THE ORIGINAL MEMORANDUM OF UNDERSTANDING, ALONG WITH THE WATER AND WASTE WATER AGREEMENT THAT'S INCLUDED WITHIN THIS AGREEMENT”
  • TDLR filing for Sharka Data Center Building 5: one-story, 288,000 sq ft, $880M, construction began late January 2026, expected completion February 24, 2027.
    “Dubbed Sharka Data Center - Building 5, the construction project began in late January this year and is expected to be completed by February 24, 2027.”
    News report · grade C
  • Buildings completed: 4
    “Google added a fourth building in 2024, revealing plans for a $100 million, 170,600 sq ft data center at the site in March of that year”
  • Building5 cost filed: 880000000 USD
    “An estimated $880 million will be invested in the development, which will be a one-story data center spanning 288,000 sq ft”
  • Building 5 construction begins (288,000 sq ft, filed cost $880M, filed completion Feb 24, 2027).
    “the construction project began in late January this year and is expected to be completed by February 24, 2027”
  • At an event held at the Midlothian campus, Google announces a $40B Texas investment through 2027 (new Armstrong and Haskell County campuses) and confirms continued investment in the existing Midlothian campus.
    “It would also continue investing in the existing 400-acre Midlothian site and its Dallas Cloud region”
  • Google November 2025 $40B Texas investment through 2027 includes expansion of its Ellis County presence; statewide program figure, not a Midlothian campus figure.
    “In November 2025, Google revealed it would spend $40bn to expand its cloud and AI infrastructure in Texas through 2027. This included the expansion of its presence in Ellis County”
  • Google buys an additional 165 acres in Ellis County for expansion of the Midlothian campus (375 + 165 = 540 acres total).
    “In 2020, the internet giant bought an additional 165 acres for a second facility”
  • First announced: June 2019
    “Google has acquired 375 acres in Midlothian for a new data center, promising $500 million in capital investment in return for significant tax breaks”
  • Investment initial announced: 600000000 USD
    “Google has invested $600 million to develop the site”
  • tax abatement (TX Ch. 312): scope 100% abatement of personal property taxes
    “June saw the council approve a 100 percent personal property tax abatement and an 85 percent improvement tax abatement over a 10-year period for the facility at RailPort Business Park”
  • tax abatement (TX Ch. 312): scope 85% abatement of real property (improvement) taxes
    “June saw the council approve a 100 percent personal property tax abatement and an 85 percent improvement tax abatement over a 10-year period for the facility at RailPort Business Park”
  • tax abatement (TX Ch. 312): term 10 years
    “an 85 percent improvement tax abatement over a 10-year period”
  • tax abatement (TX Ch. 312): consideration 500000000 USD
    “promising $500 million in capital investment in return for significant tax breaks”
  • tax abatement (TX Ch. 312): jobs up to 40 jobs
    “Council documents suggest that the data center could create up to 40 jobs”
  • Google publicly confirms it bought the Midlothian property; $600M data center announced at a groundbreaking event - Google's first Texas data center.
    “Google has invested $600 million to develop the site”
  • tax abatement (TX Ch. 312): nondisclosure Google's identity withheld from the public under a nondisclosure agreement during negotiation and approval
    “The developer, which incorporated with the state four months earlier, went by the name Sharka LLC. City officials declined at the time to say who was behind Sharka”
  • Midlothian City Council approves the Sharka tax abatement package (100% personal property / 85% improvements, 10 years) while the developer's identity is still secret under an NDA.
    “June saw the council approve a 100 percent personal property tax abatement and an 85 percent improvement tax abatement over a 10-year period”
  • tax abatement: property tax abatement, 10 years 100% personal property / 85% improvements percent abated
    “June saw the council approve a 100 percent personal property tax abatement and an 85 percent improvement tax abatement over a 10-year period for the facility at RailPort Business Park.”
  • Tax abatement agreement: PILOT schedule 100% personal property tax abatement; 85% abatement on improvements; 10-year period percent / years
    “negotiated a deal that was passed by the Midlothian City Council to receive a 100 percent property tax abatement and an 85 percent abatement on improvements over a 10-year period”
  • Tax abatement agreement: investment commitment 500000000 USD over five years
    “the company has made commitments to the city, Ellis County, and the State of Texas to bring at least 40 jobs and $500 million in investment over the next five years”
  • Tax abatement agreement: job commitments 40 jobs
    “the company has made commitments to the city, Ellis County, and the State of Texas to bring at least 40 jobs and $500 million in investment over the next five years”
Permits and government (23)
  • Air: update submittal received
    “Sharka is requesting an update to hourly emissions rates for emergency generators in Emergency Generator Group 4”
  • Sharka files a PBR 153622 update for Emergency Generator Group 4 emission rates (manufacturer data); no annual cap change - filed five months before the state permit pause.
    “Sharka is requesting an update to hourly emissions rates for emergency generators in Emergency Generator Group 4”
  • construction project registration: project closed
    “Project Name: Sharka Data Center - Building 4 Project Number: TABS2024013301 Facility Name: Sharka Data Center”
  • Construction registration (architectural barriers): registered; project closed
    “Start Date: 4/1/2024, Completion Date: 12/31/2025, Estimated Cost: $350,000,000 Current Status: Project Closed”
  • Air: draft statement of basis prepared; public notice
    “Permit Number: O4262 Project Type: Minor Revision Prepared on: November 7, 2025”
  • Air: revisions approved
    “Effective Date: 10/15/2018, Rev. 11/27/2018, Rev. 2/22/2019, Rev. 9/17/2020, Rev. 9/24/2020, Rev. 6/6/2022, Rev. 7/27/2022, Rev. 12/20/2024, Rev. 10/17/2025”
  • Air: revised
    “Title V Permit O4262, which was issued for the site in July 2021 and revised in July 2024”
  • Title V Federal Operating Permit: issued
    “A FEDERAL OPERATING PERMIT IS HEREBY ISSUED TO Sharka LLC AUTHORIZING THE OPERATION OF Sharka Data Center”
  • Air: issued
    “Permit No: O4262 Issuance Date: July 21, 2021”
  • Title V Federal Operating Permit O4262 issued to Sharka LLC - the operating campus's site-wide air permit.
    “Permit No: O4262 Issuance Date: July 21, 2021”
  • Midlothian City Council: Item 2020-168 - authorize City Manager to execute a retail water supply contract with Sharka LLC
    “CONSIDER AND ACT UPON AUTHORIZING THE CITY MANAGER TO EXECUTE A RETAIL WATER SUPPLY CONTRACT WITH SHARKA LLC”
  • Air: initial authorization
    “The Sharka Data Center was originally authorized under PBR registration 153622 in October 2018”
  • TCEQ PBR Registration 153622 first authorizes the Sharka Data Center (emergency generators and support equipment) - the campus's first primary-document footprint, predating Google's public reveal.
    “The Sharka Data Center was originally authorized under PBR registration 153622 in October 2018”
  • Permit by Rule registration: update requested
    “The Sharka Data Center was originally authorized under PBR registration 153622 in October 2018.”
  • Original target date: not stated
    “No original campus completion/operation date was published by Google or the City in any opened source; the facility held a Title V operating permit from July 21, 2021”
    grade C
  • planned development amendment: approved
    “The Midlothian City Council voted unanimously to approve an amendment to Plan Development District (PD) 106 that authorizes Google’s Railport campus to build phases 5 and 6”
  • Zoning: approved
    “The Midlothian City Council approved an amendment to Plan Development District 106 on Oct. 13, 2026, allowing Google's Railport campus to add phases 5 and 6 and an on-site generating (OSG) plant”
  • Oct 13, 2026 council approval includes a temporary on-site generating (OSG) plant to support phases 5 and 6
    “to install a temporary on-site generating (OSG) plant to support those phases. Council members asked detailed questions about tax abatements, water use and noise before approving”
  • City Council approves the PD-106 amendment adding phases 5 and 6 and an on-site generating plant to the campus entitlement (aggregator summary
    “allowing Google's Railport campus to add phases 5 and 6 and an on-site generating (OSG) plant to support new data center buildings”
  • Midlothian City Council: Amendment to Planned Development District 106 - campus phases 5 and 6 plus an on-site generating (OSG) plant
    “Midlothian council unanimously approved amendments to PD 106 allowing phases 5 and 6 of the Google Railport campus and an on-site generating (OSG) plant”
  • Governor Abbott directs TCEQ to pause issuance of all data-center-related permits until ERCOT completes its data-center audit (report expected ~Dec 10, 2026). All of this campus's issued permits (2018-2025) predate the p
    “directs TCEQ to pause the issuance of all permits related to data center projects until ERCOT completes its review”
  • Midlothian City Council: Tax abatement package for the Sharka LLC data center project (developer's identity not disclosed)
    “Last May, officials in Midlothian, Tex., a city near Dallas, approved more than $10 million in tax breaks for a huge, mysterious new development”
  • IRB/abatement ordinance: passed
    “negotiated a deal that was passed by the Midlothian City Council to receive a 100 percent property tax abatement and an 85 percent abatement on improvements over a 10-year period”
Site and other (18)
  • Name: Google Midlothian (Sharka Data Center)
    “Site Name: Sharka Data Center Physical Location: 3441 Railport Pkwy”
  • Aliases: Sharka Data Center; Project Sharka
    “Site Name: Sharka Data Center Physical Location: 3441 Railport Pkwy”
  • Address: 3441 Railport Parkway, Midlothian, TX 76065
    “Site Name: Sharka Data Center Physical Location: 3441 Railport Pkwy”
  • City: Midlothian
    “Nearest City: Midlothian”
  • County: Ellis County
    “County: Ellis”
  • County code: Ellis County, TX (48139)
    “Site Name: Sharka Data Center Physical Location: 3441 Railport Pkwy Nearest City: Midlothian County: Ellis”
  • Developer: Google LLC
    “Company Official Contact Information Name: Zia Khan Title: Data Center Facilities Manager Email Address: ziakhan@google.com”
  • Owner entity: Sharka LLC
    “Owner Name: Sharka LLC c/o Corporation Services Co.”
  • Building 4 completed; TDLR project status closed.
    “Completion Date: 12/31/2025 Current Status: Project Closed”
  • Site address: 3441 Railport Parkway, Midlothian, TX 76065
    “The location of the project is listed as 3441 Railport Parkway in Ellis County, the same address as Google’s Midlothian data center campus.”
  • Operator: Google
    “we’re extending our commitment to the state with a new data center in Midlothian”
  • Stage: operating
    “The Sharka Data Center was originally authorized under PBR registration 153622 in October 2018”
  • Construction stage: Buildings 1-4 complete; Building 5 under construction (started Jan 2026, filed completion Feb 24, 2027)
    “the construction project began in late January this year and is expected to be completed by February 24, 2027”
  • Current target date: Feb. 24, 2027
    “expected to be completed by February 24, 2027”
  • Land acres total: 540 acres
    “That 375-acre project was one of the largest in the country when it was built in 2019. In 2020, the internet giant bought an additional 165 acres for a second facility”
  • Google launches its Dallas cloud region (us-south) in June 2022, anchored by its DFW campuses including Midlothian.
    “Google launched a Texas cloud region in Dallas in June 2022”
  • Land acres initial: 375 acres
    “Google has acquired 375 acres in Midlothian for a new data center”
  • Announced: May 2018
    “That day was the first time officials had spoken publicly about an enigmatic developer's plans to build a sprawling data center.”