Power and the grid
Contracted, size not disclosed
- OG&E grid Signed, approval pendingelectric service agreements signed for this and two Muskogee Google campuses; awaiting a final state order; no MW published Company · April 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Nov. 5, 2024Voters approve OG&E franchiseBecause Stillwater's city utility serves the town, voters had to approve a franchise for OG&E to serve the data-center sites. see Permits
- April 30, 2026OG&E contracts announcedOG&E announces service and capacity agreements to power three Google data centers in Stillwater and Muskogee. Company · April 2026
- Sept. 2026Judge recommends approvalAn administrative law judge recommends approving the joint stipulation in Case 2026-000031; no final Commission order yet. News report · Aug. 2026
- Google commits to pay all costs to connect the sites to the grid and all contracted costs regardless of its actual use. Company · April 2026
- Google says it will supply generation from two solar arrays under construction; their size is not stated. News report · Sept. 2026
- No campus MW appears in the city agreement, OG&E's announcement or the state case coverage. Company · Oct. 2026
Permits checklist
1 pending · 2 granted · 1 checked, nothing on file
Approvals on record.
- ◷OG&E-Google electric service agreements (Case 2026-000031) PendingOklahoma Corporation Commission · Sept. 2026: covers this and two Muskogee campuses; judge recommended approval News report · Sept. 2026
- ✓OG&E franchise GrantedStillwater voters · Nov. 5, 2024: required for OG&E to serve the sites Dataset · Nov. 2024
- ✓Economic development project plan and tax incentive agreement (Ordinance 3546) GrantedStillwater City Council · Jan. 13, 2025: with Payne County, schools and other taxing bodies Local government · Jan. 2025
- –Checked, nothing on file: State air permit
What could slow it down
- MediumWater demandA state water official estimated the campus could use 5 to 6 million gallons a day (estimate, not a permit figure). News report · Sept. 2026
- MediumRunoff lawsuitNeighbors allege construction runoff damaged their pond (allegation, undecided). see Lawsuits
- WatchPower contracts not finalThe OG&E agreements need a final state order before they take effect. see Permits
1 case on record
- Filed by Aug. 2025 Park View Estates Homeowners Association v. Kipper LLC (Google) et al.Payne County District Court News report · Aug. 2025alleges stormwater runoff from mass grading polluted a pond; also names Manhattan Construction, Olsson and Emery Sapp & Sons (allegation)
Money on record
What happened, and what is due
- July 16, 2024Permits Planning Commission recommends the project plan Local government · July 2024
- Nov. 5, 2024Power Voters approve an OG&E franchise so the utility can serve the data-center sites Dataset · Nov. 2024
- Jan. 13, 2025Money City adopts the project plan and a 25-year tax exemption with Kipper LLC Local government · Jan. 2025
- March 13, 2025Site Google is revealed as the buyer of the land at Perkins and Richmond roads Local government · March 2025
- Aug. 22, 2025Legal Homeowners sue, alleging construction runoff polluted their pond (allegation) News report · Aug. 2025
- Nov. 20, 2025Construction Port of Muskogee release describes the Stillwater facility as under construction Local government · Nov. 2025
- April 30, 2026Power OG&E announces contracts to power three Google data centers, including Stillwater Company · April 2026
- Sept. 2026Power State judge recommends approving the OG&E-Google agreements; final order pending News report · Aug. 2026
- 2027Construction Phase 1 expected to begin operating Dataset · Aug. 2026
Building activity by quarter
Since Aug. 2026: 3 FAA filings (Aug. 2026 to Oct. 2026): tallest permanent structure 70 ft (filed Oct. 2026) and tallest crane 235 ft (Oct. 2026).
Specs
5-6M gal/day water use estimated by the state water board's rights chief (estimate). News report · Sept. 2026
- Former state land: north of the former Armstrong facility, east of Perkins Road Local government · Jan. 2025
Owners, partners and builders
- Google: owner and user
- Kipper LLC and Alliance Site & Grid, LLC: Google subsidiaries
- Stillwater City Council and Planning Commission
- Oklahoma Corporation Commission: power contracts
- OG&E (Oklahoma Gas & Electric): serving utility
- Manhattan Construction Group, Olsson Inc. and Emery Sapp & Sons (named in the runoff suit)
- Park View Estates Homeowners Association
Open questions
- Campus MW and phase schedule.
- Final state order on the OG&E contracts.
- Size of the Google solar arrays.
50 records from 19 documents
Drawn from news reports, local government records, company statements, public and commercial datasets and state agency records, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (5)
- Project identity: Google Stillwater Campus - north edge of Stillwater, south of E. Richmond Road, north of E. Airport Road, east of N. Perkins Road, on former State (Commissioners of the Land Office) land north of the fo“by Ordinance No. 3546, adopted on January 13, 2025 (the "Project Plan Ordinance"), the City approved the Stillwater Data Center Economic Development Project Plan”Local government · Jan. 2025 · grade A
- Utility: Oklahoma Gas & Electric (OG&E) under the ESAs now in OCC Case 2026-000031; OG&E states the Google agreement is the model for a new large-load tariff it will submit to the Commission“This unique agreement is a model for future data center partnerships and forms the basis for a new large-load tariff that OG&E will submit in the coming weeks”Company · April 2026 · grade B
- Utility: OG&E serves the campus (a Nov 5, 2024 voter-approved OG&E franchise was required because Stillwater Electric Utility serves the city); wholesale/municipal utility is NOT the campus provider“Stillwater Electric Utility serves the city. For OG&E to serve the proposed data center sites, the city required voter approval.”Dataset · Nov. 2024 · grade B
- Google will provide generation to serve the data centers from two solar arrays currently under construction (as stated in the OCC review coverage); the arrays are Google-procured supply into the OG&E arrangement, not an“The tech company also indicated it will provide power generation to serve the data centers from two solar arrays currently under construction.”News report · Sept. 2026 · grade C
- OG&E filed for OCC pre-approval in May 2026 of three executed Electric Service Agreements with Google subsidiary Alliance Site & Grid, LLC (Stillwater plus two Muskogee sites); ALJ recommended approval of a joint stipula“When OGE filed the application for pre-approval in May 2026, it stated it had executed three Electric Service Agreements with Alliance Site & Grid, LLC, a wholly-owned subsidiary of Google”News report · Aug. 2026 · grade C
Money and contracts (9)
- County code: 40119“A RESOLUTION APPROVING AN OKLAHOMA LOCAL DEVELOPMENT ACT TAX INCENTIVE AGREEMENT BETWEEN THE CITY OF STILLWATER, THE BOARD OF COUNTY COMMISSIONERS OF PAYNE COUNTY”Local government · Jan. 2025 · grade A
- tax incentive agreement: ad valorem exemption 100 percent“The Project Plan and the Agreement provide for a one hundred percent (100%), twenty-five (25) year ad valorem tax exemption on property value attributable to qualifying new investment”Local government · Jan. 2025 · grade A
- tax incentive agreement: minimum phase investment 500000000 USD“each Phase of the Project estimated to consist of at least five hundred million dollars ($500,000,000) in private investment by the Company.”Local government · Jan. 2025 · grade A
- Tax incentive agreement scope: up to six phases (one per incentive district), each phase estimated at least $500 million in private investment, each with an approximately 300,000 sq ft data center“The Project will consist of up to six (6) Phases corresponding to the six (6) Incentive Districts, with each Phase of the Project estimated to consist of at least five hundred million dollars ($500,000,000) in private investment”Local government · Jan. 2025 · grade A
- Project status: UNDER CONSTRUCTION - Phase 1 construction started late 2025, operational 2027 expected; City has authorised Phases 1-2 of up to six; OG&E electric service agreements announced Apr 30, 2026 with OCC filing“Construction start "Late 2025 (Phase 1)"; Operational "2027 (Phase 1)"”Dataset · Aug. 2026 · grade B
- electric service agreement: service terms“Google is committing to pay 100% of the costs to connect the data center sites to the grid as well as all contracted costs regardless of the company's energy use.”Company · April 2026 · grade B
- Electric service agreements (announced terms): cost responsibility (announced terms)“Under this agreement, Google is committing to pay 100% of the costs to connect the data center sites to the grid as well as all contracted costs regardless of the company's energy use.”Company · April 2026 · grade B
- tax incentive agreement: pilot community betterment 867000 USD“Stillwater is looking to receive PILOTs (payment in lieu of taxes) for "community betterment" alongside each phase of development - phase one would see a PILOT of $867,000.”News report · Jan. 2025 · grade C
- Phase building size: 300000 sq ft“each phase will include a data center comprised of approximately 300,000 square feet (28,870 sqm).”News report · 2025 · grade C
Permits and government (14)
- City of Stillwater Council:“by Ordinance No. 3546, adopted on January 13, 2025 (the "Project Plan Ordinance"), the City approved the Stillwater Data Center Economic Development Project Plan”Local government · Jan. 2025 · grade A
- Tallest structure filed with the FAA (ft): 70 ft“ASN 2026-ASW-17257-OE: Building, Building, 70 ft AGL, 1040 ft AMSL, 36.17061,-97.03959, Studying, submitted 2026-10-19”FAA · Oct. 2026 · grade B
- OE/AAA case for 235-ft cranes filed as 'SWR1A Cranes' at (36.17061,-97.03959), 0: Studying“ASN 2026-ASW-17133-OE: SWR1A Cranes, Mobile Crane, 235 ft AGL, 1205 ft AMSL, 36.17061,-97.03959, Studying, submitted 2026-10-19”FAA · Oct. 2026 · grade B
- OE/AAA case for a 70-ft structure filed as 'Building' at (36.17061,-97.03959), t: Studying“ASN 2026-ASW-17257-OE: Building, Building, 70 ft AGL, 1040 ft AMSL, 36.17061,-97.03959, Studying, submitted 2026-10-19”FAA · Oct. 2026 · grade B
- OE/AAA case for a 226-ft mobile crane filed as 'Project Rohan SWR2A' at (36.1660: Determined - No Hazard“ASN 2026-ASW-12806-OE: Project Rohan SWR2A, Mobile Crane, 226 ft AGL, 1200 ft AMSL, 36.16609,-97.03973, Determined - No Hazard, submitted 2026-08-10”FAA · Aug. 2026 · grade B
- FAA OE/AAA records construction filings at the Stillwater campus under its code name: a 'Project Rohan SWR2A' crane (ASN 2026-ASW-12806-OE, submitted Aug. 10, 2026) and an SWR1A crane + building pair (ASNs 2026-ASW-17133-OE“ASN 2026-ASW-12806-OE: Project Rohan SWR2A, Mobile Crane, 226 ft AGL, 1200 ft AMSL, 36.16609,-97.03973, Determined - No Hazard, submitted 2026-08-10”FAA · Aug. 2026 · grade B
- OG&E announced the agreements will be filed for OCC review 'in the coming days' : Electric Service Agreements / Capacity Purchase Agreements - filing announced, OCC approval required“The Electric Service Agreements and Capacity Purchase Agreements will be filed for review with the Oklahoma Corporation Commission in the coming days.”Company · April 2026 · grade B
- City of Stillwater voters:“For OG&E to serve the proposed data center sites, the city required voter approval.”Dataset · Nov. 2024 · grade B
- Stillwater Planning Commission:“Planning Commission recommended approval 2024-07-16, Resolution PC-2024-1”Local government · July 2024 · grade B
- Oklahoma Water Resources Board Water Rights chief Chris Neel estimated the Stillwater data center's water use at 5 million to 6 million gallons per day (testimony reported Sep 2026); estimate only, not a permit figure“Google's data center in Stillwater is estimated to use 5 million to 6 million gallons per day, Neel said”News report · Sept. 2026 · grade C
- Month precision (hearing reported Sep 2026). The ESA filings are largely confide: Review of OG&E Electric Service Agreements to power three Google data centers (two in Muskogee County + Stillwater); administrative law ju“The case, 2026-000031, involves a landmark contract for which OG&E will power three new Google data centers in Muskogee and Stillwater.”News report · Sept. 2026 · grade C
- Oklahoma Water Resources Board estimate (Chris Neel, Sept 2026): the Stillwater campus is estimated to use 5-6 million gallons per day; a separate county-commissioner-attributed report cites ~3 billion gallons/year for s“Google's data center in Stillwater is estimated to use 5 million to 6 million gallons per day, Neel said.”News report · Sept. 2026 · grade C
- Source record“The materials distributed at the meeting unveiled an internal code name for the data centers, aptly named Project Rohan”News report · Sept. 2025 · grade C
- No lawsuit located; opposition is hearing testimony over Phase 2+ transmission lines and water; residents voted only on OG&E service, not on the project itself (mayoral clarification)“They thought it was school land so they thought it would always be the same, which I understand.”News report · 2025 · grade C
Legal (1)
- Park View Estates Homeowners Association sued Google/Kipper LLC, Manhattan Construction Group, Olsson Inc. and Emery Sapp & Sons in Payne County District Court, alleging construction stormwater runoff from mass grading p“A group of Stillwater homeowners is suing Google over claims that construction of the new data center created stormwater runoff that polluted its pond”News report · Aug. 2025 · grade C
Site and other (3)
- Site acreage: 387 acres“Site "387 acres total"”Dataset · Aug. 2026 · grade B
- Project status: under construction“Google has proudly called Oklahoma home for nearly two decades, with its data center campus in Pryor and new facility under construction in Stillwater”Local government · Nov. 2025 · grade B
- Developer: Google (Alphabet), acting through Kipper LLC“Google acquired the land at the intersection of Perkins and Richmond Road. The company will build a data center campus on the land.”News report · March 2025 · grade C