Power and the grid
Contracted, size not disclosed
- OG&E grid Signed, approval pendingservice agreements cover this campus, Google's Council Hill campus and Stillwater; final state order pending; no MW published News report · Sept. 2026
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- April 30, 2026OG&E contracts announcedOG&E says it will power three new Google data centers in Muskogee and Stillwater. Company · April 2026
- Sept. 9, 2026Judge recommends approvalAn administrative law judge recommends approving the settlement in Case 2026-000031; a final Commission order is still needed. see Permits
- Under the settlement Google would cover all dedicated transmission and distribution needed to connect its sites and contribute toward shared grid costs, with 12-year terms and minimum payments (press). News report · Sept. 2026
- The 600 MW of solar power purchase agreements Google announced with the campuses adds supply to Oklahoma's grid; it is not the campuses' load. Local government · Nov. 2025
- Core Scientific's 100 MW data center and the Polaris facility in Muskogee are separate projects, not Google's. News report · Oct. 2026
Permits checklist
1 pending · 1 granted · 1 checked, nothing on file
Approvals on record.
- ◷OG&E-Google electric service agreements (Case 2026-000031) PendingOklahoma Corporation Commission · Sept. 9, 2026: covers this campus, the Council Hill campus and Stillwater News report · Sept. 2026
- ✓Scissortail project plan and tax incentive agreements GrantedCity of Muskogee Council · April 14, 2025: unanimous; 25-year incentive district Local government · April 2025
- –Checked, nothing on file: State air permit
What could slow it down
- WatchPower contracts not finalThe OG&E agreements still need a final state order. News report · Sept. 2026
Money on record
What happened, and what is due
- April 14, 2025Money City of Muskogee unanimously adopts the Scissortail data-center project plan and tax incentives Local government · April 2025
- Nov. 20, 2025Site Google announces two Muskogee County campuses: this one (Project Scissortail, near Summit) and one near Council Hill Local government · Nov. 2025
- April 30, 2026Power OG&E announces contracts to power the Muskogee campuses and Google's Stillwater site Company · April 2026
- May 2026Power OG&E asks state regulators to pre-approve the three service agreements News report · Aug. 2026
- July 20, 2026Money Google donates $800,000 to Muskogee County schools and nonprofits (press) News report · July 2026
- Sept. 9, 2026Power State judge recommends approving the OG&E-Google settlement; final order pending News report · Sept. 2026
- Oct. 16, 2026Site Construction timelines still not released (press tracker) News report · Oct. 2026
Building activity by quarter
Since Nov. 2025: 2 FAA filings (Nov. 2025 to Aug. 2026): tallest crane 250 ft (Nov. 2025).
Owners, partners and builders
- Google: owner and user
- Alliance Site & Grid, LLC: Google subsidiary on the power contracts
- City of Muskogee Council
- Muskogee County and Port Muskogee: announcing partners
- Oklahoma Corporation Commission
- OG&E: serving utility
- NextEra Energy Resources: solar projects in Google's statewide power purchase agreements
Open questions
- MW.
- Construction start date and first-building date.
46 records from 15 documents
Drawn from news reports, local government records, company statements, state agency records and public and commercial datasets, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (7)
- Two campuses announced Nov 20, 2025 near Summit and Council Hill, part of Google's two-year $9 billion Oklahoma investment, supporting Google Cloud, Workspace, Search and Maps demand“Part of Google's two-year $9 billion investment in Oklahoma, the new data center facilities will help meet growing demand for Google's AI-powered services”Local government · Nov. 2025 · grade B
- Google announced two long-term PPAs adding 600 MW of new clean energy to Oklahoma's grid (Rush Springs Solar, Stephens County; High Spring Solar, Muskogee County; NextEra Energy Resources)“Google announced two long-term power purchase agreements (PPAs) that will add 600 megawatts (MW) of new clean energy to Oklahoma's electricity grid”Local government · Nov. 2025 · grade B
- The 'hundreds of megawatts of renewable power' language attached to the Muskogee announcement describes Google's paired clean-energy agreements for the grid generally; do not convert the portfolio phrase into a campus fi“The company says the projects will be paired with clean energy agreements expected to add hundreds of megawatts of renewable power to Oklahoma's grid.”News report · Oct. 2026 · grade C
- Their MW figures must not be attributed to Google's Summit/Council Hill campuses.“Core Scientific has partnered with Port Muskogee to develop a 100 MW high-performance computing (HPC) data center in Muskogee at 1525 W 43rd St S”News report · Oct. 2026 · grade C
- The '$9 billion investment in Oklahoma' is Google's statewide two-year figure for ALL Oklahoma sites, not a Muskogee figure; the 600 MW of PPAs is new generation added to the grid, not campus load. No campus MW on any na“In addition to the Pryor data center, Google is planning new campuses in Stillwater, Owasso, and the Muskogee County towns of Summit and Council Hill.”News report · Sept. 2026 · grade C
- Utility: OG&E (Oklahoma Gas & Electric) for both Muskogee campuses and Stillwater - NOT GRDA; long-term service contracts under OCC Case PUD2026-000031“The case, 2026-000031, involves a landmark contract for which OG&E will power three new Google data centers in Muskogee and Stillwater.”News report · Sept. 2026 · grade C
- OG&E's May 2026 OCC pre-approval application covers three executed Electric Service Agreements with Alliance Site & Grid, LLC, including the two Muskogee campuses; ALJ recommended approval of a joint stipulation in Sep 2“When OGE filed the application for pre-approval in May 2026, it stated it had executed three Electric Service Agreements with Alliance Site & Grid, LLC, a wholly-owned subsidiary of Google”News report · Aug. 2026 · grade C
Money and contracts (7)
- Developer: Google“Google is contributing $1 million directly to the Muskogee community to support regional school districts, revitalize small businesses and fund skilled trades training”Company · Nov. 2025 · grade B
- community contribution: community betterment 1000000 USD“Google is contributing $1 million directly to the Muskogee community to support regional school districts, revitalize small businesses and fund skilled trades training”Company · Nov. 2025 · grade B
- tax incentive district: pilot and fee sharing“The City of Muskogee on April 14 adopted the Scissor Tail data center economic development project plan and related tax incentive agreements, following a public hearing and unanimous council votes”Local government · April 2025 · grade B
- Project status: Early development (announced Nov 20, 2025; construction timelines not released); Scissortail site work was reported under way for months before the public naming; OG&E service-contract settlement recommen“An administrative law judge recommended approval of the settlement following a Sept. 9 hearing, Elkins reported. A final order still requires Oklahoma Corporation Commission approval.”News report · Sept. 2026 · grade C
- electric service contract settlement: infrastructure cost coverage 100 percent“Google would cover 100% of the dedicated transmission and distribution infrastructure needed to connect its facilities and contribute toward shared grid costs.”News report · Sept. 2026 · grade C
- Google donated $800,000 to Muskogee County schools and nonprofits (Muskogee, Hilldale and Midway public schools, Indian Capital Technology Center, Main Street Muskogee, Muskogee STEAM Center, Oklahoma SBDC), reported Jul“As part of Google's construction of two data center campuses near Muskogee, the high tech company announced in recent days it was donating $800,000 to schools and nonprofit organizations across Muskogee County”News report · July 2026 · grade C
- Electric service contracts (announced): electric service purchase + infrastructure funding (announced)“New long-term contracts with OG&E, in which Google will purchase electric service and fund the infrastructure needed to support the data centers.”News report · Nov. 2025 · grade C
Permits and government (6)
- OE/AAA case for a 250-ft crawler crane filed as 'MUS2A 275 crawler' at (35.69070: Determined - No Hazard“ASN 2026-ASW-13412-OE: MUS2A 275 crawler, Mobile Crane, 250 ft AGL, 841 ft AMSL, 35.69070,-95.39865, Determined - No Hazard, submitted 2026-08-14”FAA · Aug. 2026 · grade B
- Project identity: Google Muskogee County campuses - TWO campuses in one queue row: (1) 'Project Scissortail', ~419.183 acres in the City of Muskogee (Griffin Industrial Park area, south of the city limits side), and (2)“announced plans for two new data center campuses near the towns of Summit and Council Hill”Company · Nov. 2025 · grade B
- OE/AAA case for a 250-ft crawler crane filed as 'MUS1A: Determined - No Hazard“ASN 2025-ASW-13655-OE: MUS1A - CC2200 crawler, Mobile Crane, 250 ft AGL, 833 ft AMSL, 35.69390,-95.39503, Determined - No Hazard, submitted 2025-11-20”FAA · Nov. 2025 · grade B
- City of Muskogee Council:“The City of Muskogee on April 14 adopted the Scissor Tail data center economic development project plan and related tax incentive agreements, following a public hearing and unanimous council votes”Local government · April 2025 · grade B
- Contract covers three new Google data centers (Muskogee campuses + Stillwater); : ALJ recommended approval of the OG&E-Google settlement (hearing Sep 9, 2026); final Commission order still pending“An administrative law judge recommended approval of the settlement following a Sept. 9 hearing, Elkins reported. A final order still requires Oklahoma Corporation Commission approval.”News report · Sept. 2026 · grade C
- Month precision (hearing reported Sep 2026). The two Muskogee County campuses (n: Review of OG&E Electric Service Agreements to power three Google data centers (two in Muskogee County + Stillwater); administrative law ju“The case, 2026-000031, involves a landmark contract for which OG&E will power three new Google data centers in Muskogee and Stillwater.”News report · Sept. 2026 · grade C
Site and other (5)
- County code: 40101“"We are excited to welcome Google to Muskogee County as they begin work on building two data center campuses," Muskogee County Commissioner Kenny Payne said”Local government · Nov. 2025 · grade B
- Project area acres: 419.183 acres“Project area includes, without limitation, the approximately 419.183 acres of land located in the City of Muskogee”Dataset · 2025 · grade B
- Phase building size: 300000 sq ft“Development of Data center campus with potential for a total of 4 phases approximately 419 acres of land. Each development phase will include a data center comprised of 300,000sqft”Dataset · 2025 · grade B
- Project status: announced“Construction timelines have not been released”News report · Oct. 2026 · grade C
- Site location: Project Scissortail: John T. Griffin Industrial Park, City of Muskogee, south and west of the Dal-Tile plant (3801 Dal Tile Rd); FAA cranes MUS1A/MUS2A 1.5 km SW of the plant; Summit town is 3.8 km further“One data center site will be located south and west of the Dal Tile plant.”News report · Nov. 2025 · grade C