The site from above
Power and the grid
Getting on the grid
Who supplies what, what it costs, and what is still not public.
- Oct. 2026Utility MW on record350 MW. News report · Oct. 2026
Permits checklist
2 granted · 4 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.
- ✓Zoning approval GrantedNesquehoning Borough: Rezoning approved by Nesquehoning Borough. Company · Aug. 2026
- ✓Air permit GrantedPennsylvania DEP: Air permit issued by Pennsylvania DEP. State agency · Oct. 2026
- –Checked, nothing on file: Site plan, Building permit, Water and wetlands permits, Utility and grid approval
Money on record
$100M Development loan (Panther Creek development financing). News report · Oct. 2026
What happened, and what is due
- Aug. 21, 2024Site Project first appears in the public record
- April 2025Money Development loan on record ($100M). News report · Oct. 2026
- June 29, 2026Site Keel ceased bitcoin mining at Panther Creek, Scrubgrass and Sharon on June 29, 2026. News report · Aug. 2026
Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026
Owners, partners and builders
- Keel Infrastructure, developer
- Stronghold Digital Mining, owner
- T5 Data Centers, design team
Open questions
- Signed electric service agreement and delivery date.
- Whether site work has started.
26 records from 10 documents
Drawn from news reports, company statements, public and commercial datasets, state agency records and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (11)
- Project status: In development. Zoning and conditional land development approvals secured (reported in Q2 2026 results); environmental permit applications in progress; bitcoin mining at the site decommissioned June 29, 2026“Secured zoning and land development approvals across Panther Creek (conditional land development) and Sharon”Company · Aug. 2026 · grade B
- Keel reports a 2.2 GW development pipeline across its portfolio (company figure, Q2 2026). Portfolio scope only; not a campus figure.“With a development pipeline of 2.2 gigawatts and established grid interconnections in place, Keel delivers scalable infrastructure solutions for institutional customers”Company · Aug. 2026 · grade B
- On-site generation: 80 MW“The Panther Creek Plant is an 80-Megawatt (MW) coal refuse reclamation-to-energy facility, located in Pennsylvania”Company · Nov. 2021 · grade B
- On-site power technology: waste coal (coal refuse) circulating fluidized bed (CFB) combustion“utilizing the same circulating fluidized bed ("CFB") technology as the Scrubgrass Plant”Company · Nov. 2021 · grade B
- Utility service: 350 MW“the site has a firm contract for 350MW of power by 2028, with potential to scale further, possibly 500MW or above”News report · Oct. 2026 · grade C
- DCD analysis reports the site could total 1 GW at full build-out; Keel has separately spoken of expansion beyond 500 MW. Neither is a committed figure; the committed campus figure is 350 MW.“The site, formerly a waste coal-fired power plant, could total 1GW at full build-out”News report · Oct. 2026 · grade C
- Stated campus size: 350 MW“Panther Creek is Keel's flagship Pennsylvania development, with a 350 MW gross campus plan and an earliest ready-for-service year of 2027”News report · Sept. 2026 · grade C
- Campus name: Keel Panther Creek“Keel said it is developing a 110MW data center in Sharon and a 350MW hyperscale campus at its Panther Creek site”News report · Aug. 2026 · grade C
- Site acreage: 336 acres“Keel has previously said the 336-acre campus could eventually be expanded beyond 500MW”News report · Aug. 2026 · grade C
- Keel ceased bitcoin mining at Panther Creek, Scrubgrass and Sharon on June 29, 2026 (Moses Lake on April 28, 2026) after completing decommissioning of all US mining operations in preparation for HPC site construction.“The company ceased mining at its 18MW Moses Lake facility in Washington on April 28, before shutting down operations at its Panther Creek, Scrubgrass, and Sharon sites in Pennsylvania on June 29”News report · Aug. 2026 · grade C
- Announced: Aug. 21, 2024“Stronghold owns over 750 acres of land and two merchant power plants, the Scrubgrass and Panther Creek Facilities in Pennsylvania.”News report · Aug. 2024 · grade C
Money and contracts (2)
- development loan: Panther Creek development financing 100000000 USD“In April, the company secured a $100m loan from Macquarie Equipment Capital to help fund the development of Panther Creek”News report · Oct. 2026 · grade C
- development partnership: Pre-construction, design, planning and development approvals“The partnership will focus on pre-construction, design, planning, and development approval processes, with T5 providing guidance and coordination throughout the planning phase”News report · Oct. 2026 · grade C
Permits and government (2)
- air permit (prime): issued“PANTHER CREEK POWER OPR LLC/NESQUEHONING”State agency · Oct. 2026 · grade A
- rezoning: approved (conditional)“Secured zoning and land development approvals across Panther Creek (conditional land development) and Sharon”Company · Aug. 2026 · grade B
Site and other (2)
- Street address: 4 Dennison Rd, Nesquehoning, PA 18240“4 Dennison Rd, Nesquehoning, PA 18240”Dataset · Oct. 2026 · grade B
- County code: 42025“The firm is developing the Panther Creek campus in Nesquehoning, Carbon County, in eastern PA”News report · Oct. 2026 · grade C
Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).