Permits
Permits checklist
1 contested · 1 denied · 1 withdrawn · 1 checked, nothing on file
Approvals the campus needs, and where each stands.
- !Concept plan, conditional approval ContestedHood County Commissioners Court · Jan. 29, 2026: developer says it was approved by law under the state shot clock; a motion to withdraw approval failed 3-2 News report · Jan. 2026
- ✕Permit appeal DeniedHood County Commissioners Court · Oct. 13, 2026: 4-0; the settlement offer was rejected 3-1 News report · Oct. 2026
- ↩Air permit for the dedicated Tolar gas plant WithdrawnTexas Commission on Environmental Quality · June 23, 2026: NRG withdrew after 11,000+ public comments News report · June 2026
- –Checked, nothing on file: Groundwater well permits
Risks
Why it stopped, what could revive it
- HighCounty fightThe county rejected a scaled-down settlement and denied the permit appeal; the developer warned of a $100 million lawsuit (press). News report · Oct. 2026
- HighNo power sourceNRG's withdrawal left no dedicated plant, and Sailfish has announced no replacement provider. News report · Aug. 2026
- MediumEndangered speciesOpponents are looking for golden-cheeked warblers near the site, whose presence would complicate development (press). News report · Aug. 2026
- MediumNo tenantNo tenant or hyperscale customer is named in any source checked. Company · Aug. 2026
Power
Power and the grid
Sources on record, size not disclosed
- Replacement on-site gas Proposed, no providerdeveloper says privately funded on-site gas will cut its grid draw; no new provider announced Company · Aug. 2026
Not used, not on record, or dropped
- NRG Tolar gas plant (dedicated) Withdrawn1,200 MW; air permit application withdrawn June 23, 2026 after 11,000+ public comments; one report described about 2 GW (press) News report · June 2026
Getting on the grid
- No large-load or generation queue record for the campus was found; the power plan relied on the dedicated Tolar plant. News report · Oct. 2026
- Any replacement on-site plant needs state air permits, which the governor's Sept. 21, 2026 directive suspends for data-center projects. News report · Sept. 2026
- Sailfish says the campus will meet the governor's new data-center standards as the state utility commission and ERCOT implement them. Company · Aug. 2026
Timeline
What happened, and what is due
SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
- Nov. 6, 2025Site Developer presents a 721-acre concept to a county workshop: about 1.1 GW of data capacity and a 1.2 GW gas plant News report · Nov. 2025
- Dec. 3, 2025Permits Sailfish says it submitted a complete application to the county News report · Jan. 2026
- Jan. 29, 2026Permits Motion to withdraw the conditional concept approval fails 3-2 News report · Jan. 2026
- Feb. 2026Permits County votes 3-2 against a six-month data-center moratorium News report · Feb. 2026
- June 23, 2026Power NRG withdraws the air permit application for the dedicated gas plant after 11,000+ comments News report · June 2026
- Aug. 11, 2026Site Sailfish describes 45 buildings on more than 2,100 acres Company · Aug. 2026
- Aug. 12, 2026Legal Opponents fund an endangered-species survey and plan a lawsuit (press) News report · Aug. 2026
- Sept. 21, 2026Permits Governor directs the state air regulator to suspend data-center permits News report · Sept. 2026
- Oct. 13, 2026Permits County rejects the settlement offer 3-1 and denies the permit appeal 4-0 News report · Oct. 2026
The buildings
Specs
~1,375 acres
Hood County footprint in the rejected settlement, down from about 2,523
500-foot setbacks
with closed-loop cooling and down-angled lighting, offered in the settlement
Who is involved
Owners, partners and builders
Developer
- Sailfish Investors: developer, founded in 2023
- Ryan Hughes: managing partner
Power
- NRG: former partner for the dedicated gas plant; withdrew its air permit application
Government
- Hood County Commissioners Court: county approvals
- Texas Commission on Environmental Quality: air permits
- Upper Trinity Groundwater Conservation District: well permits
Opponents
- Protect the Paluxy Valley: organized the comment campaign and species survey
Still unknown
Open questions
- A replacement power source after NRG's withdrawal.
- Whether the developer's threatened lawsuit is filed.
- Any tenant or financing.
Where this comes from
43 records from 13 documents
Drawn from news reports, company statements and local government records, each kept with its date and source. The bar shows documents by type.
News report 11Company 1Local government 1
Evidence
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (4)
- Developer design claims: 45 buildings of 300,000 sq ft each on >2,100 acres; privately funded on-site gas generation, closed-loop cooling, excess power to the grid subject to ERCOT approvals; only four residences adjacen“The project is advancing privately funded onsite natural gas generation designed to materially reduce its net draw from the ERCOT grid”Company · Aug. 2026 · grade B
- TCEQ issued a preliminary decision to approve its 1.2 GW air permit in Oct 2026; Do not confuse with the withdrawn Tolar application for this campus.“residents received letters from TCEQ evidencing TCEQ's preliminary decision to approve an air permit for NRG Prairie Energy Center LLC's 1.2 GW power plant”News report · Oct. 2026 · grade C
- After the Tolar withdrawal, Protect the Paluxy Valley states the Comanche Circle data center development itself is still moving forward; Sailfish has announced no replacement dedicated power source. Related Sailfish prop“Protect the Paluxy Valley Inc. emphasizes that the broader Comanche Circle data center development is still moving forward”News report · June 2026 · grade C
- Stated campus size: 1,100 MW“Data capacity (developer estimate): ~1.1 gigawatts; power plant: ~1.2 gigawatts on ~80 acres.”News report · Nov. 2025 · grade C
Permits and government (10)
- Project status: at risk permit appeal denied“In a decisive blow to proposed data center developments in Hood County, commissioners voted Tuesday, Oct. 13, to deny both a settlement offer and a permit appeal submitted by developer Ryan Hughes and Sailfish Investors”News report · Oct. 2026 · grade C
- Hood County Commissioners Court:“The Commissioners Court voted 3-1 to reject the settlement offer, with Precinct 1 Commissioner Kevin Andrews voting against the motion to reject it. In a separate vote, the court denied Sailfish Investors' permit appeal 4-0.”News report · Oct. 2026 · grade C
- Any replacement on-site power plan for Comanche Circle will need TCEQ air permits, whose issuance the Governor's Sep 21, 2026 directive suspends pending the ERCOT audit.“on September 21, 2026, Governor Abbott issued a letter instructing the TCEQ to suspend the issuance of all permits sought by data centers (or related to data center projects)”News report · Sept. 2026 · grade C
- NRG withdrew its TCEQ air permit application for the on-site Tolar power plant in June 2026; Sailfish has no announced replacement power provider and the concept plan approval is valid for two years“The data center plan concept as approved by Hood County is valid for two years, suggesting he may be able to proceed if he lines up a new power provider.”News report · Aug. 2026 · grade C
- Organised opposition (Protect the Paluxy Valley) mobilised 11,000+ TCEQ comments on the NRG permit and is funding an endangered-species (golden-cheeked warbler) survey and a planned lawsuit“Next up, said group co-founder Laura Crawford, is a lawsuit they are funding that will seek to stop the development for endangering the species.”News report · Aug. 2026 · grade C
- NRG withdrew its TCEQ air permit application for the 1,200 MW Tolar natural gas : air permit application withdrawn by applicant (NRG, Tolar plant)“The 1,200-megawatt natural gas-fired power plant was intended to provide dedicated power generation for Sailfish Investors' controversial 2,100-acre Comanche Circle data center project”News report · June 2026 · grade C
- air permit (prime): Withdrawn (June 23, 2026)“The 1,200-megawatt natural gas-fired power plant was intended to provide dedicated power generation for Sailfish Investors' controversial 2,100-acre Comanche Circle data center project.”News report · June 2026 · grade C
- Hood County Commissioners Court:“The commissioners ended up voting 3-2 against the six-month moratorium proposal.”News report · Feb. 2026 · grade C
- Hood County Commissioners Court (special called meeting):“the commission considered withdrawing conditional approval of Sailfish's Comanche Circle but the motion failed 3–2.”News report · Jan. 2026 · grade C
- Hood County Commissioners Court (workshop):“No regulatory outcome or formal agreement was made at the workshop; commissioners said they would continue the process with additional workshops and legal review.”News report · Nov. 2025 · grade C
Legal (3)
- Hughes warned the county that rejecting the settlement could result in a $100 million lawsuit and a larger, unmitigated development across the property“Hughes warned commissioners that failing to reach an agreement could result in a $100 million lawsuit and lead to a larger, unmitigated development being constructed across the property.”News report · Oct. 2026 · grade C
- Hughes warned rejection could produce a $100 million lawsuit and a larger, less restricted project; after the Oct 13 votes he said the parties were going to court“This is actually Sailfish coming to the county with a settlement offer to avoid unnecessary litigation.”News report · Oct. 2026 · grade C
- At the Jan 29, 2026 court, Hughes asserted Sailfish's Dec 3 application was approved by operation of law under the Texas Local Government Code ch. 232 / HB 3167 'shot clock' when the county did not act by Jan 2; a motion“He invokes the statutory 'shot clock' (Texas Local Government Code chapter 232 and HB 3167), asserts Sailfish submitted a complete application on Dec. 3”News report · Jan. 2026 · grade C
Site and other (5)
- Sailfish's rejected Oct 2026 settlement offered binding concessions incl. 500-foot setbacks, down-angled lighting and closed-loop cooling, and a reduced Hood County footprint (~1,375 acres vs ~2,523)“Hughes presented a settlement proposal offering binding concessions, including 500-foot building setbacks, down-angled lighting, and closed-loop cooling systems.”News report · Oct. 2026 · grade C
- County code: 48221“It is planned to occupy more than 2,100 acres on the line dividing Hood and Somervell counties a few miles from Dinosaur Valley State Park.”News report · Aug. 2026 · grade C
- County code: 48425“It is planned to occupy more than 2,100 acres on the line dividing Hood and Somervell counties a few miles from Dinosaur Valley State Park.”News report · Aug. 2026 · grade C
- Organised opposition (Protect the Paluxy / Protect Hood County) is documenting golden-cheeked warblers, an endangered species, near the site, which would complicate development; related Hood County projects (Project Lion“Their goal: To find golden-cheeked warblers, an endangered species whose presence would complicate efforts to develop Comanche Circle.”News report · Aug. 2026 · grade C
- Project identity: Comanche Circle - Sailfish Investors' proposed data center campus in southern Hood County, TX near the Somervell County line (Tolar / Granbury area, near the Comanche Peak nuclear plant); a 721-acre con“Developer describes Comanche Circle: 721 acres, 1.1 GW data capacity and phased build; residents press for water and noise protections”News report · Nov. 2025 · grade C