Data center profile · North San Jose, Santa Clara County, California (2001 Fortune Drive and nearby)

STACK SVY01 Silicon Valley Campus

STACK's 100 MW (company says) North San Jose campus: two buildings in service since before 2024, a roughly 60 MW expansion under construction.

Operating, expanding. Buildings SVY01A and SVY01B operate, and the expansion (SVY01C and SVY01D, plus a manufacturing building) broke ground Mar. 26, 2024. No tenant or lease is public, and no PG&E service agreement is on record.
100 MW
campus size, company says
stated total; the expansion is about 60 MW of IT (press)
91 MW
backup diesel generators permitted
39 emergency units; not a power supply
522,194 sq ft
expansion approved by the city
two data centers on 9.78 acres
Mar. 26, 2024
expansion groundbreaking
SVY01C and SVY01D
OperatorSTACK Infrastructure (owned by IPI Partners)
CustomerNone named (wholesale; expansion buildings to be sold to customers)
Planned IT capacity100 MW at full build-out (company IT figure)
First building in serviceIn service since 2001 (about 41 MW of IT capacity live)
Next deadlineNov. 18, 2026: San Jose Planning Commission reviews new data-center standards; the council is expected to act in Dec. 2026. They would govern future phases, not SVY01's existing approvals
Power

Power and the grid

None energized or contracted yet

PG&E grid service and a new on-site substationUnder construction
100 MW
substation sized 100 MVA; STACK says power is 100% renewable from PG&E News report · May 2023
Under construction

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. May 9, 2023
    Substation approved
    The city approves an electrical substation as part of the expansion; PG&E builds it with STACK. News report · May 2023
  2. As of Oct. 2026
    No service agreement public
    No executed electric service or interconnection agreement is in the public record. see Permits
Permits

Permits checklist

3 granted · 1 checked, nothing on file

The city zones the site, the air district permits the generators, and the Energy Commission handled the backup plant exemption.

Risks

What could slow it down

Money

Money on record

$326,275 tree in-lieu fees (plus $40,000 to a district tree fund; the only city money conditions found). News report · May 2023

Not on record: leases, incentives, abatements: none public, no tenant, lease or city incentive is on record Local government · May 2023

Land assembly

5 recorded land documents for the campus company in county records (Jan. 2024); none lists a price. 1 related-party transfer is shown greyed. Parcel counts come from the deed; acreage is not recorded.

+3 more
Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. 2015
    Paper trail STACK takes ownership of the existing 2001 Fortune Drive facility State agency · Nov. 2024
  2. Dec. 10, 2021
    Permits STACK files for the Energy Commission exemption for backup generators, the first public filing of the expansion State agency · May 2022
  3. April 12, 2023
    Permits Energy Commission certifies the environmental report and grants the exemption State agency · April 2023
  4. April 26, 2023
    Permits San Jose Planning Commission recommends approval unanimously News report · May 2023
  5. May 9, 2023
    Permits San Jose City Council approves the rezoning and permits unanimously News report · May 2023
  6. Jan. 3, 2024
    Money Land purchase recorded (no price on the deed): SI Svy01c LLC and SI Svy01f LLC to SI Svyoif LLC County deed records · Jan. 2024
  7. March 26, 2024
    Construction Groundbreaking for the SVY01C and SVY01D expansion Company · March 2024
  8. Jan. 16, 2025
    Permits Air district issues the authority to construct for 39 backup diesel generators State agency · Jan. 2025
  9. Nov. 18, 2026
    Permits Planning Commission reviews new city data-center standards News report · Oct. 2026
Construction activity

Since Feb. 2026: 1 FAA filing (Feb. 2026): a recreational use structure 123 ft. FAA · Feb. 2026

The buildings

Specs

4 data centers
SVY01A and B operating; C and D under construction
380,000 sq ft
existing buildings
~700 / ~200
union construction jobs / permanent jobs (press)
Other data centers within 40 km (213)
This campus (footprint)
9 ac
SV11 Silicon Valley IBX Data Center
23 ac
MOD SV1 Data Center
23 ac
SJC9 San Jose Data Center
23 ac
SV10 San Jose Data Center
23 ac
SV1 San Jose Data Center
23 ac
Who is involved

Owners, partners and builders

Owners
  • STACK Infrastructure: developer, owner and operator
  • IPI Partners: owner and sponsor of STACK
Decision-makers
  • San Jose City Council and Planning Commission: zoning
  • California Energy Commission: backup-plant exemption
  • Bay Area Air Quality Management District: generator permits
Power
  • Pacific Gas and Electric: serving utility and substation partner
Still unknown

Open questions

Where this comes from

115 records from 19 documents

Drawn from state agency records, news reports, company statements, public and commercial datasets, local government records and securities filings, each kept with its date and source. The bar shows documents by type.

State agency 7News report 6Company 2Dataset 2Local government 1SEC filing 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (29)
  • On-site generation: 91 MW
    “The maximum collective generating capacity of the proposed STACK project will not exceed 91 MW, although the collective nameplate capacity of the generators would exceed 91 MW”
  • Backup generators: 39 units
    “Permits to Operate 39 standby diesel emergency generators for two new data centers and one office building in San Jose, CA”
  • Backup generators count existing: 30 units
    “STACK currently has a total of thirty existing emergency standby diesel generators and associated abatement equipment”
  • On-site power technology: Diesel reciprocating emergency standby generator sets (Caterpillar C175-16, Caterpillar C32, John Deere 6068HFG85A) with DPF/DOC and SCR abatement
    “Make: Caterpillar; Model: C175-16, Model Year: 2023 EPA Engine Family: PCPXL106.NZS 4,423 bhp, 28.962 MMBTU/hr”
  • Series 2023-1 and 2023-2, by May 2023; Series 2023-3, $290M, Oct 2023; cumulative $2.59B per trade coverage); Collateral is the sponsor's stabilized operating portfolio under a master trust; per-property schedules are no
    “We have performed the procedures described below, related to certain information with respect to a portfolio of tenant leases in connection with the proposed offering of Stack Infrastructure Issuer, LLC, Secured Data Center Revenue Term Notes, Series 2023-3, Class A-2.”
  • Utility: Pacific Gas and Electric Company (PG&E)
    “to provide up to 91 MW to the data center buildings and the AMB in case of a loss of electrical power from Pacific Gas and Electric Company (PG&E)”
  • Power plan: grid
    “The generating facility would consist of 36 3-MW and 3 1-MW diesel-fired emergency backup generators to provide up to 91 MW to the data center buildings and the AMB”
  • Backup facility design evolved during CEC review: the application as first described had 38 gensets (36 x 3 MW + 2 x 1 MW) at up to 90 MW; the final permitted design is 39 gensets at a 91 MW collective cap (the added uni
    “The SVYBGF would be a diesel-fired emergency backup generating facility with a generation capacity of up to 90 megawatts (MW)”
  • Utility: Pacific Gas and Electric (PG&E)
    “Site: Stack: SVY01A, Short Code: SVY01D, Year Built: 2026, Utility Provider: PG&E, Floors: 4”
  • Utility service: not stated
    “STACK is also actively collaborating with PG&E to develop new power infrastructure in the area, promoting a more reliable, safe, and scalable grid”
  • Construction stage: Operating (SVY01A, SVY01B) with expansion under construction (SVY01C, SVY01D, advanced manufacturing building, parking structure)
    “today announced a groundbreaking and expansion of its 100MW campus in San Jose, SVY01”
  • Stage: operating + building (expansion)
    “The 60MW data center expansion will provide critical capacity and scale to one of the largest and most desired data center markets in the world”
  • IT capacity: 100 MW
    “today announced a groundbreaking and expansion of its 100MW campus in San Jose, SVY01. The 60MW data center expansion will provide critical capacity”
  • Name: STACK SVY01 Silicon Valley Campus
    “today announced a groundbreaking and expansion of its 100MW campus in San Jose, SVY01”
  • Buildings: 4 data center buildings (SVY01A, SVY01B operating; SVY01C, SVY01D under construction) plus 1 advanced manufacturing building (SVY01F)
    “The expansion includes two data centers, an advanced manufacturing facility, and a parking structure, bringing the total campus to 100MW across 19 acres”
  • IT capacity: 60 MW
    “The expansion brings an additional 60MW of critical capacity and hundreds of mixed-use jobs to the epicenter of technology and innovation”
  • Stated campus size: 100 MW
    “The expansion includes two data centers, an advanced manufacturing facility, and a parking structure, bringing the total campus to 100MW across 19 acres”
  • Groundbreaking date: March 26, 2024
    “today announced a groundbreaking and expansion of its 100MW campus in San Jose, SVY01”
  • Groundbreaking for the SVY01C/SVY01D expansion, announced by STACK with the San Jose mayor and District 4 councilmember in attendance.
    “today announced a groundbreaking and expansion of its 100MW campus in San Jose, SVY01”
  • STACK portfolio figures (4.0+ GW built or under development
    “STACK's comprehensive portfolio of data center solutions now includes 4.0+GW built or under development, with an additional 2.5+GW of planned and potential development”
  • Grid operator: CAISO
    “in case of a loss of electrical power from Pacific Gas and Electric Company (PG&E)”
  • Existing buildings: SVY01A: 9 MW, 140,000 sq ft; SVY01B: 32 MW, 240,000 sq ft (press-reported components, not summed)
    “The first data center, SVY01A, has a total capacity of 9MW and spans 140,000 sq ft (13,000 sqm). SVY01B offers 32MW capacity over 240,000 sq ft (22,300 sqm).”
  • STACK SVY02A (48 MW, ~560,000 sq ft, former Memorex site in Santa Clara, less than six miles away) is a separate STACK campus
    “The company also has a third facility located less than six miles away, Stack SVY02A, that has a capacity of 48MW over 560,000 sq ft (52,000 sqm).”
  • Sq ft existing: 380000 sq ft
    “The first data center, SVY01A, has a total capacity of 9MW and spans 140,000 sq ft (13,000 sqm). SVY01B offers 32MW capacity over 240,000 sq ft (22,300 sqm).”
  • IT capacity: 41 MW
    “The first data center, SVY01A, has a total capacity of 9MW and spans 140,000 sq ft (13,000 sqm). SVY01B offers 32MW capacity over 240,000 sq ft (22,300 sqm).”
  • STACK's SVY02A facility (48 MW, 560,000 sq ft, Santa Clara, under six miles away, Silicon Valley Power territory) is a SEPARATE campus and is excluded from this folder; likewise the 32 MW building at 2001 Fortune Drive w
    “The company also has a third facility located less than six miles away, Stack SVY02A, that has a capacity of 48MW over 560,000 sq ft (52,000 sqm)”
  • Substation capacity: 100 MVA
    “The project also includes the buildout of a 100 mega-volt ampere electrical substation, and a 150,000 square-foot parking garage with about 300 spaces”
  • The expansion includes a new PG&E electrical substation described as 100 MW in the filing coverage and as 100 mega-volt ampere by San Jose Spotlight; Recorded as a signal only
    “The project also includes the buildout of a 100 mega-volt ampere electrical substation, and a 150,000 square-foot parking garage with about 300 spaces.”
  • The expansion filing includes 39 diesel-fired backup generators (36 at 3 MW and three at 1 MW) as stated in the filing coverage. Backup diesel is never generation; unit counts/sizes are quoted as stated and were not summ
    “The site would include 39 backup generators - 36 3MW and three 1MW diesel-fired backup generators.”
Money and contracts (17)
  • Tenants: not stated
    “STACK will construct, operate and own the three buildings under a condominium plan where each entity will be sold to specific customers when operational”
  • Tenant status: No tenant named in any opened source; wholesale colocation campus; expansion buildings to be sold to specific customers when operational (condominium plan)
    “Each data center and the office building will have separate, distinct physical addresses and will operate as separate legal entities”
  • Tenant leases / building sale agreements: scope, FINDING: no lease, tenant identity, term, termination or cancellation clause is public for any SVY01 building
    “STACK will construct, operate and own the three buildings under a condominium plan where each entity will be sold to specific customers when operational”
  • CEC Small Power Plant Exemption (Order No. 23-0412-09): scope, exemption granted
    “The SPPE application is GRANTED exempting the STACK Trade Zone Park from the Application for Certification provisions of the CEC's power plant licensing process”
  • CEC Small Power Plant Exemption (Order No. 23-0412-09): condition, capacity cap 100 MW
    “The generating capacity of the project will not exceed 100 megawatts”
  • CEC Small Power Plant Exemption (Order No. 23-0412-09): condition, mitigation monitoring (MMRP)
    “The Mitigation Monitoring and Reporting Program (MMRP) set forth in Section 7 Mitigation Monitoring and Reporting Program of the FEIR, and the agreement by the City of San José to serve as the enforcement agency for the MMRP”
  • CEC Small Power Plant Exemption (Order No. 23-0412-09): termination / cancellation, FINDING: no termination, expiry or revocation clause is stated in the Order
    “This Order is adopted, issued, effective, and final on April 12, 2023”
  • Electric service / interconnection (PG&E): scope, FINDING: no executed ESA or interconnection agreement in the public record opened; no term, minimum-bill, collateral or termination clause is public
    “STACK is also actively collaborating with PG&E to develop new power infrastructure in the area, promoting a more reliable, safe, and scalable grid”
  • Land purchase (recorded deed): contract value USD
    “Recorded: March 26, 2024 · Grantor: SI SVY01C LLC · Grantee: SI SVY01C LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”
  • Land purchase (recorded deed): contract value USD
    “Recorded: Jan. 3, 2024 · Grantor: SI SVY01C LLC · Grantee: SI SVYOIF LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”
  • Land purchase (recorded deed): contract value USD
    “Recorded: Jan. 3, 2024 · Grantor: SI SVY01C LLC · Grantee: SI SVY 01 PG&E LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”
  • Land purchase (recorded deed): contract value USD
    “Recorded: Jan. 3, 2024 · Grantor: SI SVY01C LLC · Grantee: SI SVYOIS1 LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”
  • Land purchase (recorded deed): contract value USD
    “Recorded: Jan. 3, 2024 · Grantor: SI SVY01C LLC · Grantee: SI SVYC LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”
  • Land purchase (recorded deed): contract value USD
    “Recorded: Jan. 3, 2024 · Grantor: SI SVY01C LLC · Grantee: 2000 TRADE ZONE BOULEVARD OWNERS AS · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”
  • Development agreement / incentives: FINDING: no development agreement, abatement or incentive instrument appears in the City project record opened; the only monetary conditions found are tree-removal in-lieu fees in the
    “PT22-002: Vesting Tentative Map to combine two lots into one lot and allow up to 15 commercial condominiums on an approximately 9.78-gross acre site”
  • Sq ft expansion: 522194 sq ft
    “for the construction of two data centers totaling approximately 522,194 square feet, an approximately 136,573-square foot manufacturing building, an approximately 150,000-square foot parking structure”
  • utility substation buildout (planned): substation
    “The company also aims to install a 100 MW electrical substation from Pacific Gas and Electric (PG&E).”
Permits and government (21)
  • Air permit, Authority to Construct: authority to construct issued (NOD filed)
    “STACK Trade Zone Park - Issuance of Authority to Construct for Emergency Backup Diesel Generators, sources S-35 through S-73”
  • Developer: STACK Infrastructure
    “STACK Infrastructure (STACK) is submitting this application for Authorities to Construct and/or Permits to Operate 39 standby diesel emergency generators”
  • Air permit, draft engineering evaluation: draft evaluation and public notice
    “In this application, STACK is applying for Authorities to Construct and Permits to Operate for the thirty-nine (39) diesel-fired engines powering the 39 backup generators”
  • Air permits, existing facility history: permit history 2008-2021 (existing SVY01A/B facility)
    “The application history of the facility's current sources is provided below”
  • Permitting jurisdiction: CEC held exclusive Warren-Alquist jurisdiction over the 91 MW backup generating facility (thermal powerplant >= 50 MW); SPPE granted April 12, 2023 returned permitting to the City of San Jose (land u
    “the California Energy Commission (CEC) has the exclusive jurisdiction to approve or deny applications for the construction and operation of thermal powerplants that have the capacity to generate 50 megawatts (MW) or more of electricity”
  • Small Power Plant Exemption / FEIR certification: SPPE granted; FEIR certified
    “The SPPE application is GRANTED exempting the STACK Trade Zone Park from the Application for Certification provisions of the CEC's power plant licensing process. This Order is adopted, issued, effective, and final on April 12, 2023”
  • CEQA Draft EIR: draft EIR released for public review
    “STACK Infrastructure (STACK or applicant) filed an application with the CEC seeking an exemption from the CEC's jurisdiction for the Trade Zone Park (21-SPPE-02)”
  • Small Power Plant Exemption application: application filed
    “STACK Infrastructure filed an application with the California Energy Commission seeking an exemption from the CEC's jurisdiction (Small Power Plant Exemption) for the Trade Zone Boulevard Technology Park”
  • STACK filed the CEC Small Power Plant Exemption application (Docket 21-SPPE-02) for the Trade Zone Park backup generating facility, the first public filing of the SVY01 expansion.
    “In a series of filings dated December 10, 2021, March 8, 2022, March 30, 2022, April 4, 2022, and April 11, 2022; STACK Infrastructure filed an application”
  • Tallest structure filed with the FAA (ft): 123 ft
    “ASN 2026-AWP-3064-OE: Stack SVY-01C, Recreational Use Structure, 123 ft AGL, 170 ft AMSL, 37.40172,-121.89524, Determined - No Hazard, submitted 2026-02-13”
    FAA · Feb. 2026 · grade B
  • FAA obstruction evaluation (7460-1): Determined - No Hazard
    “ASN 2026-AWP-3064-OE: Stack SVY-01C, Recreational Use Structure, 123 ft AGL, 170 ft AMSL, 37.40172,-121.89524, Determined - No Hazard, submitted 2026-02-13”
    FAA · Feb. 2026 · grade B
  • FAA OE/AAA filings evidence vertical construction at STACK Infrastructure's SVY01 campus (North San Jose CA): the SVY01C expansion building filed under the campus's own designation ('Stack SVY-01C', 123 ft, submitted 202
    “ASN 2026-AWP-3064-OE: Stack SVY-01C, Recreational Use Structure, 123 ft AGL, 170 ft AMSL, 37.40172,-121.89524, Determined - No Hazard, submitted 2026-02-13”
    FAA · Feb. 2026 · grade B
  • expansion groundbreaking: groundbreaking announced; construction started on the 60 MW expansion
    “today announced a groundbreaking and expansion of its 100MW campus in San Jose, SVY01.”
  • Site acres expansion: 9.78 acres
    “PD22-001: Planned Development Permit to allow the demolition of two existing buildings and the removal of 156 trees (101 ordinance-size, 55 non-ordinance-size) for the construction of two data centers”
  • City of San Jose (PBCE community meeting): Proposed Planned Development Zoning, Planned Development Permit and Vesting Tentative Map at 1849 Fortune Drive & 2400 Ringwood Avenue, Project Nos. PDC22-001, PD22-001 & PT22-0
    “Meeting Purpose: To discuss the applicant's proposed project, the City's project and environmental review processes, and to obtain community input relative to the Planned Development Zoning, Planned Development Permit, and Vesting Tentative Map”
  • The City of San Jose is drafting new data-center standards (carbon-free power, water, generator testing limits, impact fees) with Planning Commission review Nov 18, 2026 and Council action expected Dec 2026. The standard
    “The proposals are expected to reach the City Council on Dec. 8, with a second and final vote set for Dec. 15”
  • Planned Development zoning + permit + vesting tentative map: approved by City Council (unanimous)
    “The San Jose City Council unanimously approved plans this week for an advanced manufacturing facility and data centers”
  • San Jose City Council: PDC22-001 / PD22-001 / PT22-002, STACK Trade Zone Park rezoning, planned development permit and vesting tentative map
    “The San Jose City Council unanimously approved plans this week for an advanced manufacturing facility and data centers, adding to the growing hub of tech facilities and workplaces in North San Jose”
  • San Jose Planning Commission: STACK Trade Zone Park: demolition of two industrial buildings; two data centers, advanced manufacturing building, parking garage and substation at 2400 Ringwood Ave & 1849 Fortune Dr
    “The San Jose Planning Commission unanimously approved STACK Infrastructure's proposal last week to demolish two older industrial buildings and put up an advanced manufacturing facility, two data centers, a parking garage and a power substation”
  • planned development rezoning / project approval: approved (unanimous)
    “The San Jose City Council unanimously approved plans this week for an advanced manufacturing facility and data centers, adding to the growing hub of tech facilities and workplaces in North San Jose.”
  • planned development rezoning (IP Industrial Park to TEC(PD)): considered; city staff recommended approval
    “The company is requesting to rezone the approximately 9.78-gross-acre site from the IP Industrial Park Zoning District to a TEC(PD) Planned Development Zoning District.”
Site and other (16)
  • County code: Santa Clara County, CA (06085)
    “2400 Ringwood Avenue, 1849 Fortune Drive, and 2000 Trade Zone Boulevard, San Jose, Santa Clara County, CA 95131”
  • Address: 2001 Fortune Drive, San Jose, CA 95131 (existing SVY01A/SVY01B); expansion: 2400 Ringwood Avenue and 1849 Fortune Drive; manufacturing building: 2000 Trade Zone Boulevard
    “2400 Ringwood Avenue, 1849 Fortune Drive, and 2000 Trade Zone Boulevard, San Jose, Santa Clara County, CA 95131”
  • Operator: STACK Infrastructure
    “STACK will construct, operate and own the three buildings under a condominium plan where each entity will be sold to specific customers when operational”
  • Generators nonemergency limit: 24 hours/year per engine
    “for all 39 proposed engines, the facility has accepted a non-emergency operation limit of 24 hours per year, per engine”
  • Ownership since: 2015
    “The facility (Legacy Site ID B8734) has been operating under Facility ID 22974 since STACK Infrastructure began ownership in 2015. Prior to STACK Infrastructure, the facility was owned by Fortune Data Centers”
  • STACK took ownership of the pre-existing 2001 Fortune Drive data center facility (formerly Fortune Data Centers) in 2015; the site carries BAAQMD Facility ID 22974 with 30 existing standby gensets.
    “The facility (Legacy Site ID B8734) has been operating under Facility ID 22974 since STACK Infrastructure began ownership in 2015”
  • Announced: Dec. 10, 2021
    “In a series of filings dated December 10, 2021, March 8, 2022, March 30, 2022, April 4, 2022, and April 11, 2022; STACK Infrastructure filed an application with the California Energy Commission”
  • County code: 06085
    “Stack is expanding its data center campus in San Jose, California to build two data centers on a plot at 2400 Ringwood Avenue and 1849 Fortune Drive in Santa Clara County.”
  • Project status: operating (SVY01A/SVY01B) with expansion SVY01C/D listed as built 2026 by tracker; no company completion announcement found
    “Site: Stack: SVY01A, Short Code: SVY01D, Year Built: 2026, Utility Provider: PG&E, Floors: 4”
  • Site location: 2001 Fortune Drive, North San Jose, CA (SVY01A/SVY01B)
    “Former Seagate fab at 2001 Fortune Drive in North San Jose, rebuilt by Fortune Data Centers with seismic upgrades to FEMA essential-facility standards and later run by Infomart and STACK.”
  • Expansion site: 2400 Ringwood Avenue and 1849 Fortune Drive, San Jose, CA (SVY01C/SVY01D)
    “Stack is expanding its data center campus in San Jose, California to build two data centers on a plot at 2400 Ringwood Avenue and 1849 Fortune Drive in Santa Clara County.”
  • Operator: STACK Infrastructure, Inc.
    “the digital infrastructure partner to the world's most innovative companies and a leading global developer and operator of data centers”
  • Campus size: 38-acre SVY01 campus; expansion spanning 19 acres
    “The expansion is taking place on Stack's 38-acre SVY01 campus, joining the two existing data centers on the site.”
  • Original target date: not stated
    “Other details of the expansion, including when operations are expected to begin, have not been shared”
  • Current target date: June 2026
    “The first data center could be finished by the end of 2025, with a final project completion target of June 2026”
  • Workforce estimate: ~700 union construction jobs; ~200 permanent employees (128 manufacturing, ~70 data centers)
    “The project would generate roughly 700 union construction jobs, Kersten said. When complete, the facilities will support nearly 200 new permanent jobs”

Imagery and records: County deeds: ATTOM.