Data center profile · 2950 S. Litchfield Road, Goodyear (Maricopa County), Arizona

Stream Phoenix (PHXA Campus)

Stream Data Centers' 280 MW (company says) campus in Goodyear, Arizona: two of seven buildings serve tenants today, and site plans for five more were approved in Oct. 2026

Operating, expanding. The first two buildings are serving unnamed tenants, per Stream's own campus page, and press reports site plan approval in Oct. 2026 for five more two-story buildings. No power contract, tenant lease or air permit for backup generators was found.
280 MW
critical load at full build (company says)
seven buildings, over 2 million sq ft, 157 acres
40 MW
first building, IT capacity (press)
Phoenix I, launched 2020; the second building is operating but its MW is not on record
480 MW
ultimate capacity of the on-site APS substation
utility equipment capacity, not campus load
5 buildings
added by Oct. 2026 site plan
about 400,000 sq ft each, two stories (press)
OperatorStream Data Centers (subsidiary of Stream Realty Partners)
CustomerUnnamed tenants in the first two buildings; build-to-suit offered for the rest
Planned IT capacity369 MW at full build-out (our estimate from the company or utility power figure)
First building in serviceIn service since 2026 (about 40 MW of IT capacity live)
Power

Power and the grid

480 MW energized

APS grid service via dedicated on-site substationSubstation on site
480 MW
ultimate substation capacity per Stream; campus load is stated at 280 MW; no service agreement found Company · Oct. 2026
Energized now

Getting on the grid

Who supplies what, what it costs, and what is still not public.

  1. 2020
    First building launches
    Phoenix I begins service with 40 MW of IT capacity (press). News report · Oct. 2026
  2. Aug. 2024
    Second building topped out
    Ground was broken in June 2024; the company's page now says both buildings serve tenants. News report · Oct. 2026
  3. Not set
    No service agreement found
    No APS electric service agreement is on record, so contract terms and the load schedule for the new buildings are unknown. Company · Oct. 2026
Permits

Permits checklist

1 pending · 2 granted · 3 checked, nothing on file

Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.

Risks

What could slow it down

Money

Money on record

$42M
2019 land and building purchase (press)
518,000 sq ft vacant building plus 104 acres, formerly First Solar storage News report · Oct. 2026
20 years
state sales tax exemption on tenant equipment
for tenants leasing 500 kW or more for three years or longer (company page) Company · Oct. 2026
Land assembly

1 recorded land document for the campus company in county records (Feb. 2019); 1 lists a price. Parcel counts come from the deed; acreage is not recorded.

Timeline

What happened, and what is due

SitePaper trailConstructionPowerPermitsMoneyLegalUpcoming
  1. 2019
    Site Stream buys a vacant building and 104 acres in Goodyear (press). News report · Oct. 2026
  2. Feb. 11, 2019
    Money Land purchase by SDC PHX I LLC recorded at $42M; seller not named (1 parcel) County deed records · Feb. 2019
  3. 2020
    Construction Phoenix I launches with 40 MW of IT capacity (press). News report · Oct. 2026
  4. June 28, 2023
    Permits Goodyear's planning commission hears a request to rezone 104 acres and recommends approval. Local government · June 2023
  5. June 2024
    Construction Ground broken on the second building. News report · Oct. 2026
  6. Aug. 2024
    Construction Second building topped out. News report · Oct. 2026
  7. Oct. 14, 2026
    Permits Press reports site plan approval for five more buildings of about 400,000 sq ft each. News report · Oct. 2026
Construction activity

Building activity by quarter

Since May 2019: 65 building permits (44 issued or finished, 4 pending or open, 17 withdrawn or expired); the largest lists a $50M job value; 16 FAA filings (March 2024 to April 2026): tallest permanent building 60 ft (filed Jan. 2025) and tallest crane 350 ft (Aug. 2024); and 3 OSHA inspections. Job values are not added up: trade permits often repeat the whole project's value. The chart starts in the fourth quarter of 2020; 5 earlier records are not drawn.

Building permits
FAA filings
OSHA visits
’21
’22
’23
’24
’25
’26
Dot size: records in the quarter, largest = 10. Two-digit years mark each first quarter.
The buildings

Specs

7 buildings
two complete and operating; five more planned on a 104-acre parcel
157 acres
campus site
Other data centers within 40 km (76)
This campus (footprint)
17 ac
Prime Phoenix - Lower Buckeye 2 Data C
94 ac
Phoenix Data Center
70 ac
Phoenix AZ Data Center
37 ac
Phoenix 2 Data Center
25 ac
PHX2 Phoenix Sky Harbor Data Center
21 ac
Who is involved

Owners, partners and builders

Owners
  • Stream Data Centers: developer, owner and operator
  • Stream Realty Partners: parent company
Power
  • Arizona Public Service: electric utility with a dedicated on-site substation
Decision-makers
  • City of Goodyear: zoning and site plans
  • Maricopa County Air Quality Department: air permits
Neighbors
  • Microsoft owns zoned land directly west; it is not part of this campus
Builders on site
  • Clayco, Inc.: contractor on site per OSHA inspection 347363400; 4 building permits
  • Albireo Energy LLC: contractor on site per OSHA inspection 347363392; 1 OSHA inspection
  • Data Link Technology Services LLC: contractor on site per OSHA inspection 347363418; 1 OSHA inspection
  • Holder Construction Group LLC: 11 building permits
  • Complete Fire Protection Inc: 9 building permits
  • Clune Construction Company LP: 6 building permits
  • and 6 more contractors in the permit and inspection records
Still unknown

Open questions

Where this comes from

180 records from 15 documents

Drawn from public and commercial datasets, news reports, state agency records, company statements and local government records, each kept with its date and source. The bar shows documents by type.

Dataset 4News report 4State agency 4Company 3Local government 1
Evidence

Every quote behind this page

Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.

Power (19)
  • Stated campus size: 280 MW
    “At full build, the 157-acre campus will support up to 280 MW of critical load across more than two million square feet of data center space.”
  • On-site APS substation: 350 MW in 2020 launch coverage; current operator page states ultimate power capacity of 480 MW
    “Dedicated on-site APS substation with ultimate power capacity of 480 MW.”
  • Interconnection status: energized, on-site 350 MW APS substation in service; first buildings serving tenants
    “At full build, the 157-acre campus will support up to 280 MW of critical load across more than two million square feet of data center space.”
  • County code: Maricopa County, AZ (04013)
    “At full build, the 157-acre campus will support up to 280 MW of critical load”
  • Total sq ft planned: 2000000 sq ft
    “will support up to 280 MW of critical load across more than two million square feet of data center space”
  • Stated campus size: 280 MW
    “At full build, the 157-acre campus will support up to 280 MW of critical load across more than two million square feet”
  • Utility service: 480 MW
    “Dedicated on-site APS substation with ultimate power capacity of 480 MW”
  • On-site generation: not stated
    “Dedicated on-site APS substation with ultimate power capacity of 480 MW”
  • Utility: Arizona Public Service (APS)
    “Dedicated on-site APS substation with ultimate power capacity of 480 MW”
  • Power plan: grid
    “Dedicated on-site APS substation with ultimate power capacity of 480 MW”
  • Jurisdiction: City of Goodyear (land use); Maricopa County Air Quality Department (air permits)
    “REZONE PROPERTY SOUTH OF THE SOUTHWEST CORNER OF LITCHFIELD ROAD AND LOWER BUCKEYE ROAD TO PAD OVERLAY FOR STREAM DATA CENTER CAMPUS”
  • Utility service: 350 MW
    “After all phases are complete, the Goodyear Campus will spread 2 million square feet of mission-critical capacity across five buildings all supported by a 350 MW onsite Arizona Public Service Electric Company (APS) substation”
  • Utility: Arizona Public Service (APS) via dedicated on-site substation
    “The campus has access to an on-site substation providing 350MW from the Arizona Public Service Electric Company (APS).”
  • PHX I building figure: 40 MW IT / critical capacity across 418,000 sq ft (DCD); Building-level only
    “PHX I was launched in 2020 and offers 40MW of IT capacity across 418,000 sq ft (39,000 sqm) of data center space.”
  • Statewide Arizona tracker lists Stream PHX-1, Goodyear: 157 acres, 7 buildings, 280 MW at build-out, two buildings operating and five planned; latest Aug 2024 second building topped out. Corroborates the operator page on
    “PHX-1 | Stream Data Centers | Goodyear, Maricopa Co. | 157 acres; 7 buildings; 280 MW at build-out | Two buildings operating, five planned”
  • Parent company: Stream Realty Partners
    “The company – a subsidiary of Stream Realty Partners – currently offers a total of 40MW from the first building”
  • IT capacity: 40 MW
    “PHX I was launched in 2020 and offers 40MW of IT capacity across 418,000 sq ft of data center space”
  • Original target date: 2020
    “PHX I was launched in 2020 and offers 40MW of IT capacity”
  • Cooling: air-cooled chillers (new phases)
    “The new facilities will use air-cooled chillers located on the roof, which require additional screening to comply with Goodyear building regulations”
Money and contracts (16)
  • Tenants: not stated
    “With the first two buildings actively serving tenants”
  • Tenant status: operating - unnamed tenants in first two buildings; wholesale / build-to-suit offering
    “Ample availability for build-to-suit, mega scale, or custom data center developments”
  • tax exemption: scope
    “A 20-year sales tax exemption on equipment purchases is available to all Steam tenants leasing 500 kW of capacity or more for at least three years”
  • tax exemption: term
    “A 20-year sales tax exemption on equipment purchases is available to all Steam tenants leasing 500 kW of capacity or more for at least three years”
  • tax exemption: condition
    “available to all Steam tenants leasing 500 kW of capacity or more for at least three years”
  • tax exemption: finding
    “Sales tax exemptions translate to deployment savings”
  • development agreement: finding
    “REZONE PROPERTY SOUTH OF THE SOUTHWEST CORNER OF LITCHFIELD ROAD AND LOWER BUCKEYE ROAD TO PAD OVERLAY FOR STREAM DATA CENTER CAMPUS”
  • electric service agreement: finding
    “Dedicated on-site APS substation with ultimate power capacity of 480 MW”
  • tenant lease: finding
    “With the first two buildings actively serving tenants”
  • Land purchase (recorded deed): contract value 42000000 USD
    “Recorded: Feb. 11, 2019 · Price: $42,000,000 · Grantee: SDC PHX I LLC · Parcel number: 500-07-039E · Address: 2950 S LITCHFIELD RD · City: GOODYEAR”
  • Microsoft owns land directly west of the Stream Goodyear campus, zoned for data centers, with no facility launched there per DCD
    “Microsoft owns the land directly west of the campus. It is also zoned for data centers but the company is yet to launch a facility on the land.”
  • land purchase: scope
    “Stream Data Centers acquired a 518,000-square-foot vacant industrial building at 2950 S. Litchfield Road alongside 104 undeveloped acres in 2019”
  • land purchase: value 42000000 USD
    “Real estate database Vizzda shows the company paid $42 million for the property”
  • land purchase: condition
    “The building was previously used as storage by Tempe-based First Solar Inc.”
  • Site plan approval granted for five more two-story buildings (approx. 400,000 sq ft each) on the 104-acre parcel - the build-out behind the company's seven-building plan
    “the company was recently granted site plan approval for a multi-phased development on 104 acres in Maricopa County, comprising five more two-story data center buildings, with each being approximately 400,000 square feet”
  • tax incentive program: sales tax exemption eligibility
    “The campus benefits from Arizona's data center tax exemptions.”
Permits and government (87)
  • FAA OE/AAA: Determined - No Hazard
    “Mobile Crane being used to erect steel and walls for new data center.”
    FAA · Jan. 2025 · grade A
  • FAA OE/AAA: Determined - No Hazard
    “Mobile Crane being used to erect steel and walls for new data center.”
    FAA · Jan. 2025 · grade A
  • FAA OE/AAA: Determined - No Hazard
    “Mobile Crane being used to erect steel and walls for new data center.”
    FAA · Jan. 2025 · grade A
  • FAA OE/AAA: Determined - No Hazard
    “Mobile Crane being used to erect steel and walls for new data center.”
    FAA · Jan. 2025 · grade A
  • FAA OE/AAA: Reminder
    “Two story data center”
    FAA · Jan. 2025 · grade A
  • FAA OE/AAA: Determined - No Hazard
    “ASN 2024-AWP-11035-OE: stream dunnage south side, Crane, 350 ft AGL, 1306 ft AMSL, 33.41801667,-112.36171111, Determined - No Hazard, submitted 2024-08-23”
    FAA · Aug. 2024 · grade A
  • FAA OE/AAA: Determined - No Hazard
    “ASN 2024-AWP-5400-OE: Stream point 2, Mobile crane, 200 ft AGL, 1156 ft AMSL, 33.41843889,-112.36140278, Determined - No Hazard, submitted 2024-05-03”
    FAA · May 2024 · grade A
  • FAA OE/AAA: Determined - No Hazard
    “ASN 2024-AWP-5401-OE: stream data point 3, Mobile crane, 200 ft AGL, 1156 ft AMSL, 33.41951111,-112.36161944, Determined - No Hazard, submitted 2024-05-03”
    FAA · May 2024 · grade A
  • FAA OE/AAA: Determined - No Hazard
    “ASN 2024-AWP-5402-OE: stream data point 3, Crane, 200 ft AGL, 1156 ft AMSL, 33.41986944,-112.35887222, Determined - No Hazard, submitted 2024-05-03”
    FAA · May 2024 · grade A
  • FAA OE/AAA: Determined - No Hazard
    “ASN 2024-AWP-4228-OE: stream data center, Crane, 200 ft AGL, 1156 ft AMSL, 33.41828889,-112.35937778, Determined - No Hazard, submitted 2024-03-29”
  • Zoning: I-1 (Light Industrial); I-1 with PAD Overlay (SDC II parcel)
    “request to rezone approximately 104 acres from the I-1 (Light Industrial) Zoning District to the I-1 (Light Industrial) Zoning District with a Planned Area Development (PAD) Overlay”
  • rezoning: public hearing / recommend approval
    “Recommend approval of the request to rezone approximately 104 acres from the I-1 (Light Industrial) Zoning District to the I-1 (Light Industrial) Zoning District with a Planned Area Development (PAD) Overlay”
  • City of Goodyear Planning & Zoning Commission: Case 23-200-00004 - Rezone approx. 104 acres to I-1 with PAD Overlay for the Stream Data Center Campus (draft Ordinance No. 2023-1574)
    “REZONE PROPERTY SOUTH OF THE SOUTHWEST CORNER OF LITCHFIELD ROAD AND LOWER BUCKEYE ROAD TO PAD OVERLAY FOR STREAM DATA CENTER CAMPUS”
  • air permit: not located
    “Dedicated on-site APS substation with ultimate power capacity of 480 MW”
  • building permit: Commercial construction: complete
    “Permit number: B25-01316 · Type: Commercial construction · Status: complete · Job value: $678,000 · Effective date: July 6, 2026 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: Electrical”
  • building permit: Commercial construction: complete
    “Permit number: B25-01605 · Type: Commercial construction · Status: complete · Job value: $600,000 · Effective date: July 6, 2026 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: Electrical”
  • building permit: Commercial construction: complete
    “Permit number: B25-01824 · Type: Commercial construction · Status: complete · Job value: $1,070,315 · Effective date: July 2, 2026 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: Mechanical”
  • building permit: Industrial construction: issued
    “Permit number: B26-01489 · Type: Industrial construction · Status: issued · Job value: $125,000 · Effective date: June 9, 2026 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction: withdrawn
    “Permit number: B26-01466 · Type: Commercial construction · Status: withdrawn · Job value: $125,000 · Effective date: June 4, 2026 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • FAA obstruction evaluation (7460-1): Determined - No Hazard
    “ASN 2026-AWP-6157-OE: Crane, Mobile Crane, 180 ft AGL, 1146 ft AMSL, 33.42075,-112.35769, Determined - No Hazard, submitted 2026-04-07”
  • building permit: Commercial construction: complete
    “Permit number: B25-01870 · Type: Commercial construction · Status: complete · Job value: $500,000 · Effective date: March 9, 2026 · Business: Sturgeon Electric Company INC · Address: 2950 S LITCHFIELD RD · Description: Electrical”
  • building permit: Commercial construction: complete
    “Permit number: B25-00877 · Type: Commercial construction · Status: complete · Job value: $2,498,307 · Effective date: Jan. 27, 2026 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Fire protection systems: complete
    “Permit number: B25-02003 · Type: Fire protection systems · Status: complete · Job value: $152,996 · Effective date: Jan. 22, 2026 · Business: Summit Fire Protection CO · Address: 2950 S LITCHFIELD RD · Description: Fire sprinkler”
  • Tallest structure filed with the FAA (ft): 60 ft
    “ASN 2025-AWP-18069-OE: Stream Data Center, Building, 60 ft AGL, 1007 ft AMSL, 33.41097,-112.36073, Determined - No Hazard, submitted 2025-11-26”
    FAA · Nov. 2025 · grade B
  • FAA obstruction evaluation (7460-1): Determined - No Hazard
    “ASN 2025-AWP-18069-OE: Stream Data Center, Building, 60 ft AGL, 1007 ft AMSL, 33.41097,-112.36073, Determined - No Hazard, submitted 2025-11-26”
    FAA · Nov. 2025 · grade B
  • building permit: Commercial construction / Other new construction (not listed ab: withdrawn
    “Permit number: B25-02728 · Type: Commercial construction · Status: withdrawn · Job value: $300,000 · Effective date: Nov. 26, 2025 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: New - other new construction (not listed above) - revis”
  • FAA OE/AAA records Stream Data Centers' Goodyear campus in the window: a 60-ft building filed as 'Stream Data Center' (ASN 2025-AWP-18069-OE, submitted Nov. 26, 2025) 0.99 km from the campus's 2950 S Litchfield Rd address p
    “ASN 2025-AWP-18069-OE: Stream Data Center, Building, 60 ft AGL, 1007 ft AMSL, 33.41097,-112.36073, Determined - No Hazard, submitted 2025-11-26”
    FAA · Nov. 2025 · grade B
  • building permit: Commercial construction: co or final inspection
    “Permit number: B21-05702 · Type: Commercial construction · Status: co or final inspection · Effective date: Aug. 27, 2025 · Business: Clune Construction Company LP · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction: complete
    “Permit number: B23-01827 · Type: Commercial construction · Status: complete · Effective date: Aug. 20, 2025 · Business: 2199 Innerbelt Business Center · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Fire protection systems: plancheck
    “Permit number: B25-01899 · Type: Fire protection systems · Status: plancheck · Job value: $2,500 · Effective date: Aug. 18, 2025 · Business: Summit Fire Protection CO · Address: 2950 S LITCHFIELD RD · Description: Fire sprinkler”
  • building permit: Commercial construction: issued
    “Permit number: B25-01317 · Type: Commercial construction · Status: issued · Job value: $1,875,000 · Effective date: June 2, 2025 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: Electrical - other new construction (not listed above) - n/a”
  • building permit: Commercial construction: complete
    “Permit number: B23-04017 · Type: Commercial construction · Status: complete · Job value: $8,585,643 · Effective date: May 16, 2025 · Business: 2199 Innerbelt Business Center · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Drinking water construction permit (atc/aoc): issued
    “Permit number: DWR2500237 · Type: Drinking water construction permit (atc/aoc) - pipelines · Status: issued · Effective date: May 14, 2025 · Address: 2950 S LITCHFIELD RD · Description: This project consists of an industrial development and related improvements near the swc of litchfi”
  • building permit: Drinking water construction permit (atc/aoc): issued
    “Permit number: DWR2500238 · Type: Drinking water construction permit (atc/aoc) - pipelines · Status: issued · Effective date: May 14, 2025 · Address: 2950 S LITCHFIELD RD · Description: This project consists of an industrial development and related improvements near the swc of litchfi”
  • building permit: Wastewater construction permit (atc/aoc): issued
    “Permit number: WWR2500189 · Type: Wastewater construction permit (atc/aoc) - gravity sewer · Status: issued · Effective date: May 14, 2025 · Address: 2950 S LITCHFIELD RD · Description: The stream data center phxa7 is located near the swc of litchfield road and lower buckeye road in g”
  • building permit: Commercial construction / Other new construction (not listed ab: withdrawn
    “Permit number: B25-00498 · Type: Commercial construction · Status: withdrawn · Job value: $30,000,000 · Effective date: March 3, 2025 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: New - other new construction (not listed above) - dat”
  • building permit: Drinking water construction permit (atc/aoc): issued
    “Permit number: DWR2400888 · Type: Drinking water construction permit (atc/aoc) - pipelines · Status: issued · Effective date: Dec. 23, 2024 · Address: 2950 S LITCHFIELD RD · Description: This project consists of an industrial development and related improvements near the swc of litchfi”
  • building permit: Wastewater construction permit (atc/aoc): issued
    “Permit number: WWR2400687 · Type: Wastewater construction permit (atc/aoc) - gravity sewer · Status: issued · Effective date: Dec. 23, 2024 · Address: 2950 S LITCHFIELD RD · Description: This project will develop the site to a new industrial building with associated site improvements.”
  • building permit: Fire protection systems: co or final inspection
    “Permit number: B23-04555 · Type: Fire protection systems · Status: co or final inspection · Effective date: Oct. 24, 2024 · Business: Nexus Alarm & Suppression INC · Address: 2950 S LITCHFIELD RD · Description: Fire alarm”
  • building permit: Fire protection systems: co or final inspection
    “Permit number: B24-02421 · Type: Fire protection systems · Status: co or final inspection · Effective date: Oct. 24, 2024 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Other fire protection (not listed above) - fire sprinkler relocation”
  • building permit: Commercial construction / Other new construction (not listed ab: withdrawn
    “Permit number: B24-02918 · Type: Commercial construction · Status: withdrawn · Job value: $5,000,000 · Effective date: Oct. 8, 2024 · Business: Clayco INC · Address: 2950 S LITCHFIELD RD · Description: New - other new construction (not listed above) - b23-04017”
  • building permit: Fire protection systems: co or final inspection
    “Permit number: B23-03136 · Type: Fire protection systems · Status: co or final inspection · Effective date: Sept. 9, 2024 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Fire sprinkler”
  • building permit: Commercial construction: co or final inspection
    “Permit number: B23-05086 · Type: Commercial construction · Status: co or final inspection · Effective date: Aug. 30, 2024 · Business: Clune Construction Company LP · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction: co or final inspection
    “Permit number: B23-00578 · Type: Commercial construction · Status: co or final inspection · Effective date: Aug. 29, 2024 · Business: Clune Construction Company LP · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Fire protection systems: co or final inspection
    “Permit number: B22-04702 · Type: Fire protection systems · Status: co or final inspection · Effective date: Aug. 22, 2024 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Fire sprinkler”
  • building permit: Fire protection systems: co or final inspection
    “Permit number: B22-05460 · Type: Fire protection systems · Status: co or final inspection · Effective date: Aug. 21, 2024 · Business: ORR Protection Systems INC · Address: 2950 S LITCHFIELD RD · Description: Fire alarm”
  • building permit: Fire protection systems: co or final inspection
    “Permit number: B23-03806 · Type: Fire protection systems · Status: co or final inspection · Effective date: Aug. 21, 2024 · Business: ORR Protection Systems INC · Address: 2950 S LITCHFIELD RD · Description: Fire protection systems - fire alarm”
  • building permit: Fire protection systems: co or final inspection
    “Permit number: B24-01865 · Type: Fire protection systems · Status: co or final inspection · Effective date: Aug. 21, 2024 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Fire sprinkler”
  • building permit: Commercial construction: co or final inspection
    “Permit number: B22-02883 · Type: Commercial construction · Status: co or final inspection · Job value: $4,114,850 · Effective date: Aug. 14, 2024 · Business: Clune Construction Company LP · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction: co or final inspection
    “Permit number: B23-03120 · Type: Commercial construction · Status: co or final inspection · Effective date: Aug. 14, 2024 · Business: Clune Construction Company LP · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction: co or final inspection
    “Permit number: B24-00011 · Type: Commercial construction · Status: co or final inspection · Job value: $6,000 · Effective date: July 23, 2024 · Business: Sturgeon Electric Company INC · Address: 2950 S LITCHFIELD RD · Description: Electrical”
  • building permit: Commercial construction / Other new construction (not listed ab: expired
    “Permit number: B24-02028 · Type: Commercial construction · Status: expired · Job value: $5,500,000 · Effective date: June 26, 2024 · Business: Clayco INC · Address: 2950 S LITCHFIELD RD · Description: New - revision to b23-04017”
  • building permit: Commercial construction / Other new construction (not listed ab: withdrawn
    “Permit number: B24-02009 · Type: Commercial construction · Status: withdrawn · Job value: $30,000,000 · Effective date: June 25, 2024 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: New - other new construction (not listed above) - dat”
  • building permit: Commercial construction / Other new construction (not listed ab: issued
    “Permit number: B24-01863 · Type: Commercial construction · Status: issued · Job value: $30,000,000 · Effective date: June 3, 2024 · Business: Holder Construction Group LLC · Address: 2950 S LITCHFIELD RD · Description: New - other new construction (not listed above) - data c”
  • building permit: Fire protection systems: co or final inspection
    “Permit number: B23-03604 · Type: Fire protection systems · Status: co or final inspection · Effective date: May 17, 2024 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Fire protection systems - automatic sprinkler”
  • building permit: Fire protection systems: expired
    “Permit number: B21-06171 · Type: Fire protection systems · Status: expired · Effective date: April 2, 2024 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Fire protection systems - automatic sprinkler”
  • building permit: Fire protection systems: expired
    “Permit number: B22-00110 · Type: Fire protection systems · Status: expired · Effective date: April 2, 2024 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Fire protection systems - automatic sprinkler”
  • building permit: Fire protection systems: expired
    “Permit number: B22-00245 · Type: Fire protection systems · Status: expired · Effective date: April 2, 2024 · Business: ORR Protection Systems INC · Address: 2950 S LITCHFIELD RD · Description: Fire protection systems - fire alarm”
  • building permit: Fire protection systems: expired
    “Permit number: B22-01575 · Type: Fire protection systems · Status: expired · Effective date: April 2, 2024 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Fire protection systems - automatic sprinkler”
  • building permit: Commercial construction: expired
    “Permit number: B24-00763 · Type: Commercial construction · Status: expired · Job value: $15,000,000 · Effective date: March 8, 2024 · Business: Clayco INC · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction / Other new construction (not listed ab: respond and resubmit
    “Permit number: B24-00620 · Type: Commercial construction · Status: respond and resubmit · Job value: $4,671,367 · Effective date: Feb. 26, 2024 · Address: 2950 S LITCHFIELD RD · Description: New - other new construction (not listed above) - revision”
  • building permit: Commercial construction / Other new construction (not listed ab: expired
    “Permit number: B24-00528 · Type: Commercial construction · Status: expired · Job value: $1,500,000 · Effective date: Feb. 16, 2024 · Business: Clayco INC · Address: 2950 S LITCHFIELD RD · Description: New - other new construction (not listed above) - revision”
  • building permit: Commercial construction: withdrawn
    “Permit number: B24-00399 · Type: Commercial construction · Status: withdrawn · Job value: $105,000 · Effective date: Feb. 1, 2024 · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction: withdrawn
    “Permit number: B24-00400 · Type: Commercial construction · Status: withdrawn · Job value: $105,000 · Effective date: Feb. 1, 2024 · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction: withdrawn
    “Permit number: B24-00401 · Type: Commercial construction · Status: withdrawn · Job value: $1,133,000 · Effective date: Feb. 1, 2024 · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction: withdrawn
    “Permit number: B24-00402 · Type: Commercial construction · Status: withdrawn · Job value: $209,725 · Effective date: Feb. 1, 2024 · Address: 2950 S LITCHFIELD RD · Description: Tenant improvement”
  • building permit: Commercial construction / Addition: respond and resubmit
    “Permit number: B24-00393 · Type: Commercial construction · Status: respond and resubmit · Job value: $73,664 · Effective date: Jan. 31, 2024 · Address: 2950 S LITCHFIELD RD · Description: New - addition”
  • building permit: Electrical permit / Electrical work only: issued
    “Permit number: 24-11/000 000 ELEC 00 · Type: Electrical permit · Status: issued · Job value: $300,000 · Effective date: Jan. 2, 2024 · Business: Sturgeon Electric Company INC · Address: 2950 S LITCHFIELD RD”
  • building permit: Fire protection systems: issued
    “Permit number: B23-05651 · Type: Fire protection systems · Status: issued · Effective date: Dec. 27, 2023 · Business: ADT Commercial LLC · Address: 2950 S LITCHFIELD RD · Description: Fire alarm”
  • building permit: Commercial construction: plancheck
    “Permit number: B23-03731 · Type: Commercial construction · Status: plancheck · Effective date: Aug. 29, 2023 · Address: 2950 S LITCHFIELD RD · Description: Additions & alterations - tenant improvement”
  • building permit: Commercial construction: issued
    “Permit number: B23-02408 · Type: Commercial construction · Status: issued · Effective date: June 8, 2023 · Business: 2199 Innerbelt Business Center · Address: 2950 S LITCHFIELD RD · Description: Electrical work only - electrical permit”
  • building permit: Fire protection systems: expired
    “Permit number: B23-00828 · Type: Fire protection systems · Status: expired · Effective date: March 1, 2023 · Business: Complete Fire Protection INC · Address: 2950 S LITCHFIELD RD · Description: Fire sprinkler”
  • building permit: Commercial construction: complete
    “Permit number: B22-04454 · Type: Commercial construction · Status: complete · Effective date: Aug. 31, 2022 · Business: Evergreen Innovation Group LLC · Address: 2950 S LITCHFIELD RD · Description: Photovoltaic commercial - photovoltaic/commercial”
  • building permit: Fire protection systems: issued
    “Permit number: B22-03598 · Type: Fire protection systems · Status: issued · Effective date: July 15, 2022 · Business: ORR Protection Systems INC · Address: 2950 S LITCHFIELD RD · Description: Fire protection systems - fire alarm”
  • building permit: Commercial construction / Other new construction (not listed ab: issued
    “Permit number: B22-00116 · Type: Commercial construction · Status: issued · Effective date: Jan. 7, 2022 · Business: Clune Construction Company LP · Address: 2950 S LITCHFIELD RD · Description: New - other new construction (not listed above) - exterior shel”
  • building permit: Fire alarm / Fire protection systems: complete
    “Permit number: 20-252/000 000 FALR 00 · Type: Fire alarm · Status: complete · Job value: $367,529 · Effective date: Nov. 18, 2020 · Business: Nexus Alarm & Suppression · Address: 2950 S LITCHFIELD RD”
  • building permit: Coml impr tenant permit / Additions & alterations: issued
    “Permit number: 19-4209/000 000 BCTI 00 · Type: Coml impr tenant permit · Status: issued · Job value: $24,438,127 · Effective date: Nov. 5, 2020 · Business: DPR Construction A General PRT · Address: 2950 S LITCHFIELD RD”
  • building permit: Automatic sprinkler / Fire protection systems: complete
    “Permit number: 19-5934/000 000 ASS 00 · Type: Automatic sprinkler · Status: complete · Job value: $843,701 · Effective date: Nov. 3, 2020 · Business: Summit Fire Protection CO · Address: 2950 S LITCHFIELD RD”
  • building permit: Coml impr tenant permit / Additions & alterations: complete
    “Permit number: 19-2098/000 000 BCTI 00 · Type: Coml impr tenant permit · Status: complete · Job value: $5,650,037 · Effective date: June 5, 2020 · Address: 2950 S LITCHFIELD RD”
  • building permit: Wrecking permit / Additions & alterations: complete
    “Permit number: 19-2098/000 000 BLD2 00 · Type: Wrecking permit · Status: complete · Job value: $50,000,000 · Effective date: May 4, 2020 · Address: 2950 S LITCHFIELD RD”
  • building permit: Fire protection systems: complete
    “Permit number: B20-00252 · Type: Fire protection systems · Status: complete · Effective date: Jan. 15, 2020 · Business: Nexus Alarm & Suppression · Address: 2950 S LITCHFIELD RD · Description: Fire protection systems - fire alarm”
  • building permit: Commercial construction: complete
    “Permit number: B19-04209 · Type: Commercial construction · Status: complete · Effective date: Aug. 28, 2019 · Business: DPR Construction A General PRT · Address: 2950 S LITCHFIELD RD · Description: Additions & alterations - tenant improvement - coml impr tenant permit”
  • building permit: Commercial construction: complete
    “Permit number: B19-02098 · Type: Commercial construction · Status: complete · Effective date: May 1, 2019 · Business: DPR Construction A General PRT · Address: 2950 S LITCHFIELD RD · Description: Additions & alterations - tenant improvement - wrecking permit”
  • rezoning with Planned Area Development (PAD) overlay: Passed / recommended for approval; forwarded to City Council
    “The Goodyear Planning and Zoning Commission last week passed a request by Stream to rezone approximately 104 acres on Litchfield Road and Lower Buckeye Road”
  • site plan approval (multi-phased development): Granted
    “comprising five more two-story data center buildings, with each being approximately 400,000 square feet (37,160 sqm) in size.”
  • rezoning: rezoned
    “The site was rezoned to light industrial from agricultural in 2006”
  • site plan: approved
    “the company was recently granted site plan approval for a multi-phased development on 104 acres in Maricopa County, comprising five more two-story data center buildings”
Site and other (20)
  • Operator: Stream Data Centers
    “Stream’s hyperscale data center campus in Goodyear, AZ, conveniently located in the metro Phoenix area”
  • Project status: operating (first two buildings serving tenants) with five remaining buildings in development - 7-building, 157-acre campus
    “With the first two buildings actively serving tenants, each of the five remaining buildings are being developed for separate and unique flexibility”
  • Site acres: 157 acres
    “Seven buildings planned across 157 acres”
  • Campus name: Stream Phoenix (PHXA Campus)
    “Stream's PHXA campus in Goodyear is emerging as the largest data center campus in this part of Arizona”
  • City: Goodyear
    “Stream's hyperscale data center campus in Goodyear, AZ, conveniently located in the metro Phoenix area”
  • County: Maricopa County
    “Stream's hyperscale data center campus in Goodyear, AZ”
  • Developer: Stream Data Centers
    “Stream's massive PHXA Campus in Goodyear is emerging as the largest data center campus in this part of Arizona”
  • Operator: Stream Data Centers
    “The data center operations team is comprised of 100% Stream-badged employees”
  • Site acres: 157 acres
    “Seven buildings planned across 157 acres”
  • Buildings planned: 7 buildings
    “Seven buildings planned across 157 acres”
  • Buildings operating: 2 buildings
    “With the first two buildings actively serving tenants, each of the five remaining buildings are being developed”
  • Stage: operating-partial
    “With the first two buildings actively serving tenants, each of the five remaining buildings are being developed for separate and unique flexibility”
  • Construction stage: operating-partial - 2 of 7 buildings complete and serving tenants; 5 further buildings site-plan approved / in development
    “Conveniently located in the Greater Phoenix metro area, Stream's PHXA campus is the largest in the region, with two of the seven buildings now complete”
  • Current target date: not stated
    “each of the five remaining buildings are being developed for separate and unique flexibility to ensure future development options”
  • County code: 04013
    “the company was recently granted site plan approval for a multi-phased development on 104 acres in Maricopa County”
  • Address: 2950 S Litchfield Rd, Goodyear, AZ 85338
    “Stream Data Centers acquired a 518,000-square-foot vacant industrial building at 2950 S. Litchfield Road alongside 104 undeveloped acres in 2019.”
  • Address: 2950 S Litchfield Rd, Goodyear, AZ 85338
    “Stream Data Centers acquired a 518,000-square-foot vacant industrial building at 2950 S. Litchfield Road alongside 104 undeveloped acres in 2019”
  • PHX II (second building) topped out; ground broken June 2024; expected operational by 2025. Company page (Oct 2026) confirms the first two buildings are actively serving tenants
    “Stream Data Centers has topped out a second data center facility on its Goodyear Campus in Phoenix, Arizona”
  • Source record
    “Microsoft owns the land directly west of the campus. It is also zoned for data centers but the company is yet to launch a facility on the land”
  • Announced: Feb. 18, 2019
    “Stream Data Centers has purchased an industrial facility on 157 acres in Goodyear. The company plans to establish a data center campus for hyperscale and enterprise customers in the greater Phoenix region”

Imagery and records: County deeds and building permits: ATTOM.