Power and the grid
- SRP grid service with an on-site substation Not on recordno service agreement or MW on record; the project includes an on-site substation Dataset · Oct. 2026
Getting on the grid
- SRP sets its prices through its elected board rather than the state commission, and new large accounts of 20 MW or more go through its large-customer process. Company · Feb. 2025
Permits checklist
1 granted · 1 checked, nothing on file
Approvals a campus like this normally needs, and what we found.
- ✓Site plan and zoning GrantedCity of Mesa: city design review case DRB17-00310 is listed as approved; no date found Utility regulator · Oct. 2026
- –Checked, nothing on file: State power plant siting certificate
What could slow it down
- MediumCapacity unverifiedThe 115 MW figure traces to a tracker citing a 2024 datasheet; no city or utility document states it. News report · Sept. 2026
- MediumWhich phase is built is unknownReports say the campus is under construction in four phases but do not say which phase or how much capacity is near energization. News report · July 2026
- WatchLarge-load rules at SRPNew accounts of 20 MW or more must go through SRP's large-customer integration process under the 2025 price plan. Company · Feb. 2025
Money on record
$10.2M land purchase in 2017 (press) (93 acres). News report · July 2026
3 recorded land documents for the campus company in county records (Aug. 2017 to Dec. 2025); 1 lists a price. 2 related-party transfers are shown greyed. Parcel counts come from the deed; acreage is not recorded.
- Aug. 2017 Loop 202 & Elliot Road LLC (seller not named) · $10.2M County deed records · Aug. 2017
- Aug. 2023 Loop 202 & Elliot Road Parcel 2 LLC to Loop 202 & Elliot Road LLC · price not recorded · related-party transfer County deed records · Aug. 2023
- Dec. 2023 Loop 202 & Elliot Road LLC to Loop 202 & Elliot Road LLC · price not recorded · related-party transfer County deed records · Dec. 2023
+2 more
- Dec. 2025 Edgeconnex PHX11 Operations LLC leases from Loop 202 & Elliot Road LLC · lease recorded · price not recorded County deed records · Dec. 2025
- Dec. 2025 Edgeconnex PHX12 Operations LLC leases from Loop 202 & Elliot Road LLC · lease recorded · price not recorded County deed records · Dec. 2025
What happened, and what is due
- 2017Site EdgeConneX, through Loop 202 & Elliot Road LLC, buys the 93-acre site for $10.2M (press) News report · July 2026
- 2023Permits EdgeConneX files its project paperwork with the City of Mesa (press) News report · July 2026
- Feb. 27, 2025Power SRP's board approves its updated large-customer price plan and a large-customer integration process, which apply to new accounts of 20 MW or more Company · Feb. 2025
- Dec. 30, 2025Site Land lease to EdgeConneX PHX11 Operations LLC recorded by the county; price not recorded County deed records · Dec. 2025
- Dec. 30, 2025Site A second land lease, to EdgeConneX PHX12 Operations LLC, recorded the same day; price not recorded County deed records · Dec. 2025
- July 20, 2026Construction Arizona Republic reports the campus under construction, in four phases, with completion timing unclear (press) News report · July 2026
- Sept. 2026Site An Arizona tracker lists PHX11 at 115 MW planned and reports no groundbreaking (tracker) News report · Sept. 2026
Building activity by quarter
Since Dec. 2024: 5 FAA filings (Dec. 2024 to April 2026): tallest crane 360 ft (March 2025).
Owners, partners and builders
- EdgeConneX: developer
- Loop 202 & Elliot Road LLC: land-holding entity since 2017
- City of Mesa: site plan and zoning
- Salt River Project: serving utility, governed by an elected board
Open questions
- Which phase is under construction and its opening date.
- A primary source for the planned MW.
- Terms of SRP service for this campus.
- 1 unconfirmed county land record near the site: the buyer or location could not be tied to this campus.
61 records from 15 documents
Drawn from news reports, state agency records, company statements, public and commercial datasets, utility regulator dockets and securities filings, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (11)
- Collateral is EdgeConneX's operating portfolio; per-property schedules are not public, and no collateral property is address/APN-matched to this campus (Mesa, under development); Portfolio context only; no campus MW or v“Re: EdgeConneX Data Centers Issuer, LLC, Secured Data Center Revenue Notes, Series 2024-1 – Data File Procedures”SEC filing · July 2024 · grade A
- Power step: utility named“In 2025, SRP introduced the Large Customer Integration Process (LCIP) to address requests for electricity for new large-load customers”Company · Oct. 2026 · grade B
- County code: 04013“EdgeConneX Mesa campus, 93 acres (Maricopa County -> 04013; halls and substation on the one parcel).”Dataset · Oct. 2026 · grade B
- Building count: 3 buildings“The ambitious project aims to construct three buildings, totaling more than 1 million sq ft (92,900 sqm), along with an on-site substation.”Dataset · Oct. 2026 · grade B
- Operator: EdgeConneX“EdgeConneX serves the Phoenix Metro area with an existing Tier 3-designed, purpose-built data center in Tempe and an upcoming campus in Mesa: 100MW+ under development”Company · Oct. 2026 · grade B
- Project narrative in the Mesa application: phase 1 is a 180,000 sq ft data hall plus 50,000+ sq ft admin with two power blocks; later buildings of 301,072 and 481,017 gross sq ft“Second and third buildings that total 301,072 and 481,017 gross square feet make up the third and final phase, according to a project narrative submitted with EdgeConneX's application.”Dataset · Oct. 2026 · grade B
- EdgeConneX company site lists the Mesa campus as under development (100MW+ marketing line) alongside its operating Tempe facility“EdgeConneX serves the Phoenix Metro area with an existing Tier 3-designed, purpose-built data center in Tempe and an upcoming campus in Mesa: 100MW+ under development”Company · Oct. 2026 · grade B
- Project narrative includes an on-site substation as a plan element (signal only; no nameplate figure stated, not campus MW)“The ambitious project aims to construct three buildings, totaling more than 1 million sq ft (92,900 sqm), along with an on-site substation.”Dataset · Oct. 2026 · grade B
- Stated campus size: 115 MW“PHX11 | EdgeConneX | Mesa, Maricopa Co. | 115 MW planned | Planned | 2024 datasheet; no groundbreaking”News report · Sept. 2026 · grade C
- Queue MW 115 matches a tracker figure of 115 MW planned sourced to a 2024 EdgeConneX datasheet; no primary city or company document stating 115 MW was retrieved, so 115 MW stands as mw campus stated at press/tracker leve“PHX11 | EdgeConneX | Mesa, Maricopa Co. | 115 MW planned | Planned | 2024 datasheet; no groundbreaking”News report · Sept. 2026 · grade C
- Arizona tracker (2026): PHX11 115 MW planned per the 2024 datasheet; no groundbreaking reported“PHX11, EdgeConneX, Mesa, Maricopa Co., 115 MW planned, Planned, 2024 datasheet; no groundbreaking”News report · Sept. 2026 · grade C
Money and contracts (7)
- Land lease (recorded document): contract value USD“Recorded: Dec. 30, 2025 · Grantor: LOOP 202 & ELLIOT ROAD LLC · Grantee: EDGECONNEX PHX11 OPERATIONS LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Dec. 2025 · grade B
- Land lease (recorded document): contract value USD“Recorded: Dec. 30, 2025 · Grantor: LOOP 202 & ELLIOT ROAD LLC · Grantee: EDGECONNEX PHX12 OPERATIONS LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Dec. 2025 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Dec. 11, 2023 · Grantor: LOOP 202 & ELLIOT ROAD LLC · Grantee: LOOP 202 & ELLIOT ROAD LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Dec. 2023 · grade B
- Land purchase (recorded deed): contract value USD“Recorded: Aug. 29, 2023 · Grantor: LOOP 202 & ELLIOT ROAD PARCEL 2 LLC · Grantee: LOOP 202 & ELLIOT ROAD LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Aug. 2023 · grade B
- Land purchase (recorded deed): contract value 10236600 USD“Recorded: Aug. 22, 2017 · Price: $10,236,600 · Mortgage1amount: 15525000 · Grantee: LOOP 202 & ELLIOT ROAD LLC · Address: 000 ADDRESS EXCEPTION · City: CITY EXCEPTION”County deed records · Aug. 2017 · grade B
- Land transaction: Purchased for $10.2 million in 2017 via Loop 202 & Elliot Road LLC“EdgeConneX, through the Loop 202 & Elliot Road, LLC, purchased the land for $10.2 million in 2017”News report · July 2026 · grade C
- PHX11 site identity verified from Mesa-corridor records: 93 acres at Hawes Road and Loop 202 in the Elliot Road technology corridor, bought in 2017 for $10.2M by Loop 202 & Elliot Road LLC - a different site from CyrusOn“EdgeConneX, through the Loop 202 & Elliot Road, LLC, purchased the land for $10.2 million in 2017”News report · July 2026 · grade C
Permits and government (11)
- FAA OE/AAA: Determined - No Hazard“Proposed temp crane for hoisting HVAC equipment on existing permanent structure.”FAA · Aug. 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“Need crane for erection of structural steel.”FAA · March 2025 · grade A
- FAA OE/AAA: Determined - No Hazard“ASN 2024-AWP-15301-OE: Edge Connex, Crane, 190 ft AGL, 1574 ft AMSL, 33.3541,-111.65220278, Determined - No Hazard, submitted 2024-12-03”FAA · Dec. 2024 · grade A
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AWP-3246-OE: Edge PHX12, Crane, 200 ft AGL, 1588 ft AMSL, 33.35586,-111.64796, Determined - No Hazard, submitted 2026-04-06”FAA · April 2026 · grade B
- FAA obstruction evaluation (7460-1): Determined - No Hazard“ASN 2026-AWP-3726-OE: Edge Connex 2nd Building, Mobile Crane, 200 ft AGL, 1595 ft AMSL, 33.35403,-111.65288, Determined - No Hazard, submitted 2026-04-06”FAA · April 2026 · grade B
- FAA OE/AAA filings evidence vertical construction at EdgeConneX's PHX11 campus (Mesa AZ): two 200-ft cranes filed April 6, 2026 under the operator's own designations - 'Edge PHX12' and 'Edge Connex 2nd Building' - for the c“ASN 2026-AWP-3246-OE: Edge PHX12, Crane, 200 ft AGL, 1588 ft AMSL, 33.35586,-111.64796, Determined - No Hazard, submitted 2026-04-06”FAA · April 2026 · grade B
- SRP is a not-for-profit, board-governed utility: its prices are set by its publi: SRP Board approved updated E-67 commercial/industrial price plan and SRP introduced the Large Customer Integration Process (LCIP), both 20“SRP's updated E-67 commercial and industrial price plan, which was approved in 2025, requires new large customer accounts with at least 20 megawatts (MW) of forecasted load be subject to minimum billing requirements”Company · Feb. 2025 · grade B
- site plan / zoning (PAD): Site Plan/Zoning Approved for the Edge Connex PAD (PAD ID 3), as recorded in SRP CEC Exhibit H Table H-1“Edge Connex NKS Group III Limited Partnership Site Plan/Zoning Approved DRB17-00310 City of Mesa”Utility regulator · April 2022 · grade B
- PHX11 is EdgeConneX's planned Mesa campus (93 acres at Loop 202 & Elliot Road, h: no CEC application filed for EdgeConneX PHX11 facilities (status check)“PHX11 | EdgeConneX | Mesa, Maricopa Co. | 115 MW planned | Planned | 2024 datasheet; no groundbreaking”News report · Oct. 2026 · grade C
- city filing: EdgeConneX initially filed paperwork with the City of Mesa in 2023 (year only in source; no case number published in the source seen)“The company initially filed paperwork with the city in 2023.”News report · July 2026 · grade C
- STAGE CHECK (brief item 3): a non-FAA source confirms construction - the Arizona Republic (Jul 20, 2026), sourced to City of Mesa documents, reports the campus under construction (three buildings, four phases), and its S“Three buildings on 93 acres are coming to the area just a street away to the west from the Hawes Crossings neighborhood”News report · July 2026 · grade C
Site and other (9)
- Site acres: 93 acres“EdgeConneX is building a massive data center campus on a 93-acre land parcel it has owned since 2017 through Loop 202 & Elliot Road LLC.”Dataset · Oct. 2026 · grade B
- Phase count: 4 phases“The project will be built in four-phases.”News report · Sept. 2026 · grade C
- Project status: under construction“A massive data center campus is under construction in southeast Mesa near Loop 202 along Hawes Road”News report · July 2026 · grade C
- Project status: under construction“A massive data center campus is under construction in southeast Mesa near Loop 202 along Hawes Road”News report · July 2026 · grade C
- Site location: Hawes Road and Loop 202, southeast Mesa, AZ (west of Hawes Crossings, north of an Amazon distribution center)“Three buildings on 93 acres are coming to the area just a street away to the west from the Hawes Crossings neighborhood”News report · July 2026 · grade C
- Site coordinates: 33.352009,-111.647529“Location: Hawes Road and Loop 202 in Mesa.”News report · July 2026 · grade C
- EdgeConneX initially filed paperwork with the City of Mesa in 2023, and city documents from 2023 put total employment at 93 (Arizona Republic, sourced to City of Mesa)“The EdgeConneX data center will employ 93 total employees, according to city documents from 2023.”News report · July 2026 · grade C
- Campus under construction as of July 2026 (Arizona Republic, source: City of Mesa): three buildings on 93 acres built out in four phases; completion timeline not clear“A massive data center campus is under construction in southeast Mesa near Loop 202 along Hawes Road.”News report · July 2026 · grade C
- Local press explainer (Jul 2026) reports the campus under construction in southeast Mesa, with completion timing not yet clear“A massive data center campus is under construction in southeast Mesa near Loop 202 along Hawes Road”News report · July 2026 · grade C
Imagery and records: County deeds: ATTOM.