The site from above
Power and the grid
The plan on record is on-site gas generation. No utility agreement or generation permit is on record yet.
We checked utility filings, regulator dockets and air-permit records for this campus.
Permits checklist
6 checked, nothing on file
Approvals a campus like this normally needs (including an air permit for backup or on-site generators), and what we found.
- –Checked, nothing on file: Zoning approval, Site plan, Building permit, Air permit, Water and wetlands permits, Utility and grid approval
What happened, and what is due
- Oct. 1, 2026Power The proposal pairs up to 28 data center buildings with an on-site fracked-gas plant on the 550-acre Fiore site. News report · Oct. 2026
Since Oct. 2026: 1 satellite capture. Satellite · Oct. 2026
Owners, partners and builders
- Hendricks Group Developers, developer
Open questions
- Air permit and gas supply for the on-site plant.
- Whether site work has started.
13 records from 4 documents
Drawn from news reports, public and commercial datasets and satellite captures, each kept with its date and source. The bar shows documents by type.
Every quote behind this page
Grade key: A = the primary record itself (permit, filing, exhibit) · B = a dated official statement · C = news reporting. Map distances are our own measurements on OpenStreetMap and carry no grade. Allegations in lawsuits are marked as such in the quotes.
Power (5)
- Announced: Oct. 2026“A developer from Bucks County wants to build a 1-gigawatt (GW) natural gas-fired power plant and up to 28 data center buildings on a former U.S. Steel landfill in Elizabeth Township, Allegheny County”News report · Oct. 2026 · grade C
- Campus name: Hendricks Elizabeth Township data center and gas plant proposal“A developer from Bucks County wants to build a 1-gigawatt (GW) natural gas-fired power plant and up to 28 data center buildings on a former U.S. Steel landfill in Elizabeth Township”News report · Oct. 2026 · grade C
- Project status: proposed“wants to build a 1-gigawatt (GW) natural gas-fired power plant and up to 28 data center buildings on a former U.S. Steel landfill in Elizabeth Township, Allegheny County”News report · Oct. 2026 · grade C
- On-site generation: 1,000 MW“A developer from Bucks County wants to build a 1-gigawatt (GW) natural gas-fired power plant and up to 28 data center buildings”News report · Oct. 2026 · grade C
- The proposal pairs up to 28 data center buildings with an on-site fracked-gas plant on the 550-acre Fiore site, a former U.S. Steel landfill; the same site hosted Invenergy's failed Allegheny Energy Center gas plant prop“the site would contain up to 28 buildings and an on-site fracked gas plant”News report · Oct. 2026 · grade C
Site and other (3)
- Building count: 28 buildings“up to 28 data center buildings on a former U.S. Steel landfill in Elizabeth Township, Allegheny County”News report · Oct. 2026 · grade C
- Site acreage: 550 acres“The proposed project would be 550 acres off of Henderson Road in Elizabeth Township, an area known as the Fiore site”News report · Oct. 2026 · grade C
- County code: 42003“on a former U.S. Steel landfill in Elizabeth Township, Allegheny County”News report · Oct. 2026 · grade C
Imagery and records: Satellite imagery: Sentinel-2 (ESA Copernicus).